Skip to content
GharKundli

Shivnath Habitat

by SHIVNATH DEVELOPER · Padale Village, Thane 421204Also near Manpada, Vishnunagar

What’s in the report? →

Possession date of Shivnath Habitat (MahaRERA P51700020976): 30 June 2026, moved from 30 May 2024 (25 months later), and it has already passed. It has 139 homes, 34% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700020976. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51700020976, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Shivnath Habitat?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shivnath Habitat has moved

  1. 30 May 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700023007)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 60% allottees for purpose of extension of RERA registration period of the said project.”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA29102518193)

    Reason the builder gave MahaRERA:
    “The delay in the project has been caused by a combination of unforeseen circumstances, including procurement challenges, and certain site-related issues. In particular, we would like to highlight the following key reasons: 1. STP Plant Loca…” Read the full reason“The delay in the project has been caused by a combination of unforeseen circumstances, including procurement challenges, and certain site-related issues. In particular, we would like to highlight the following key reasons: 1. STP Plant Location Not Finalized: The location of the Sewage Treatment Plant (STP) could not be finalized as we have recently incorporated an additional plot into the same project. We have already applied for TMC approval for the newly proposed Building No. B5 (Stilt + 19 stories), which necessitated a reassessment of overall infrastructure planning. 2. UG Tank & Fire…”

Source: Shivnath Habitat’s extension records on MahaRERA (P51700020976), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shivnath Habitat

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700020976
Status
Lapsed (registration period ended)
Builder
SHIVNATH DEVELOPER
Location
Padale Village, Thane · 421204
Project type
Residential / Group Housing
Registered on
27 May 2019
Completion date at registration
May 2024
Latest completion date
June 2026
Delay so far
25 months
Homes
139
Sold or booked
34%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Shivnath Habitat, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B3100%100%100%100%
B4100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • B3: covers 8 floors
  • B4: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shivnath Habitat every 1–2 months.

Shivnath Habitat: buildings, flats and land, as filed on MahaRERA

  • Buildings: B3 (9 floors, 34 units) · B4 (20 floors, 126 units)
  • Land: 12,051 sq m (about 3.0 acres) · sanctioned built-up 6,350 sq m · recreational space 728 sq m
  • Land, as filed: 117/1A PART, 119/1,2, 120/3 PART, 121/11,12
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shivnath Habitat →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shivnath Habitat: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shivnath Habitat

What is the possession date of Shivnath Habitat?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shivnath Habitat in Padale Village, Thane is 30 June 2026 — 25 months later than 30 May 2024, the date given at registration. That date has already passed.

The date has already moved 25 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shivnath Habitat?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shivnath Habitat's builder has filed on MahaRERA, the official one, is 30 June 2026, already 25 months later than the 30 May 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shivnath Habitat extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 60% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2026, giving the reason "The delay in the project has been caused by a combination of unforeseen circumstances, including procurement challenges, and certain site-related issues. In particular, we would like to highlight the following key reasons: 1. STP Plant Location Not Finalized: The location of the Sewage Treatment Plant (STP) could not be finalized as we have recently incorporated an additional plot into the same project. We have already applied for TMC approval for the newly proposed Building No. B5 (Stilt + 19 stories), which necessitated a reassessment of overall infrastructure planning. 2. UG Tank & Fire…".

What is the RERA number of Shivnath Habitat?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shivnath Habitat in Padale Village, Thane is P51700020976.

Is Shivnath Habitat registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat is registered as P51700020976 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shivnath Habitat? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Shivnath Habitat have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shivnath Habitat safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat is registered on MahaRERA as P51700020976, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shivnath Habitat?

Shivnath Habitat isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shivnath Habitat?

For a flat in Shivnath Habitat (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shivnath Habitat received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shivnath Habitat?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shivnath Habitat uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shivnath Habitat was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shivnath Habitat's possession date changes?

The latest dates are on Shivnath Habitat's MahaRERA page (P51700020976). GharKundli's Kundli Watch sends a free WhatsApp update on Shivnath Habitat every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shivnath Habitat have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat has 2 buildings filed: B3 with 9 floors and 34 units; B4 with 20 floors and 126 units.

How big is the land of Shivnath Habitat?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat stands on 12,051 sq m of land (about 3.0 acres), with 6,350 sq m of sanctioned built-up area and 728 sq m of recreational open space.

What are the reviews of Shivnath Habitat?

Google Maps has reviews of Shivnath Habitat written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shivnath Habitat?

Shivnath Habitat by SHIVNATH DEVELOPER is in Padale Village, Thane, pincode 421204 (near Manpada, Vishnunagar), Maharashtra, and is registered on MahaRERA as P51700020976, per GharKundli's check of MahaRERA records. Its land is filed as 117/1A PART, 119/1,2, 120/3 PART, 121/11,12. GharKundli lists all 252 MahaRERA projects in Manpada (421204).

How many flats are in Shivnath Habitat, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat has 139 homes in 2 towers registered on MahaRERA, and 34% of them are sold or booked.

When was Shivnath Habitat registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shivnath Habitat was registered on MahaRERA on 27 May 2019. GharKundli did not find a title report on the land on file there.

Does Shivnath Habitat have any legal issues or court cases?

No court cases are listed for Shivnath Habitat on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shivnath Habitat?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVNATH DEVELOPER, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Manpada (421204)

All 252 projects in Manpada (421204) →

Other projects by SHIVNATH DEVELOPER

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.