Vishnu Vatika NX Phase II D & H Wing
by M/S. VISHNU GROUP · Badlapur Gaon, Thane 421503Also near Kulgaon
What’s in the report? →Possession date of Vishnu Vatika NX Phase II D & H Wing (MahaRERA P51700021437): 31 October 2026, moved from 30 October 2025 (12 months later), and it has already passed. It has 147 homes, 72% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700021437, and currently active.
Source: MahaRERA website — records for P51700021437, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Vishnu Vatika NX Phase II D & H Wing?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vishnu Vatika NX Phase II D & H Wing has moved
30 October 2025
Completion date given when the project was registered
31 October 2026
Extended at the builder's request (MahaRERA application EA15112518337)
Reason the builder gave MahaRERA:
“The Project consist of Two wings that is Wing D and Wing H. Construction work of Wing D is 100% complete and it is evident from Table A of Form 1. Similarly, RCC Structure of Wing H along with the internal work is almost complete except the…” Read the full reason
“The Project consist of Two wings that is Wing D and Wing H. Construction work of Wing D is 100% complete and it is evident from Table A of Form 1. Similarly, RCC Structure of Wing H along with the internal work is almost complete except the installation of lift. It is evident from the above table that sale of the wing H is very less sales. Being lower than expected sale has effected the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project because of which the project couldn’t be completed within given timeline. Uncertain oper…”
Source: Vishnu Vatika NX Phase II D & H Wing’s extension records on MahaRERA (P51700021437), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vishnu Vatika NX Phase II D & H Wing
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700021437
- Status
- Registered and active
- Builder
- M/S. VISHNU GROUP
- Location
- Badlapur Gaon, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 28 Jun 2019
- Completion date at registration
- October 2025
- Latest completion date
- October 2026
- Delay so far
- 12 months
- Homes
- 147
- Sold or booked
- 72%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Vishnu Vatika NX Phase II D & H Wing, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| D WING | 100% | 100% | 100% | 100% |
| H WING | 100% | 100% | 96% | 62% |
| G WING | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- D WING: covers 8 floors
- H WING: covers 12 floors
- G WING: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vishnu Vatika NX Phase II D & H Wing every 1–2 months.
Vishnu Vatika NX Phase II D & H Wing: buildings, flats and land, as filed on MahaRERA
- Buildings: D WING (8 floors, 40 units) · H WING (12 floors, 107 units) · G WING (8 floors)
- Land: 9,990 sq m (about 2.5 acres) · sanctioned built-up 295 sq m · recreational space 997 sq m
- Land, as filed: S NO.131/1 AND 132/2 AND 132/5
- Map: Get directions
The builder’s record and reviews
Vishnu Group has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date. No complaints on MahaRERA.
Read Google reviews of Vishnu Vatika NX Phase II D & H Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vishnu Vatika NX Phase II D & H Wing: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vishnu Vatika NX Phase II D & H Wing
What is the possession date of Vishnu Vatika NX Phase II D & H Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vishnu Vatika NX Phase II D & H Wing in Badlapur Gaon, Thane is 31 October 2026 — 12 months later than 30 October 2025, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vishnu Vatika NX Phase II D & H Wing?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vishnu Vatika NX Phase II D & H Wing's builder has filed on MahaRERA, the official one, is 31 October 2026, already 12 months later than the 30 October 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vishnu Vatika NX Phase II D & H Wing extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing's builder applied to MahaRERA to extend the completion date once: to 31 October 2026, giving the reason "The Project consist of Two wings that is Wing D and Wing H. Construction work of Wing D is 100% complete and it is evident from Table A of Form 1. Similarly, RCC Structure of Wing H along with the internal work is almost complete except the installation of lift. It is evident from the above table that sale of the wing H is very less sales. Being lower than expected sale has effected the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project because of which the project couldn’t be completed within given timeline. Uncertain oper…".
What is the RERA number of Vishnu Vatika NX Phase II D & H Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vishnu Vatika NX Phase II D & H Wing in Badlapur Gaon, Thane is P51700021437.
Is Vishnu Vatika NX Phase II D & H Wing registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing is registered as P51700021437 and its status is "Registered and active".
What is the current construction status of Vishnu Vatika NX Phase II D & H Wing? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Vishnu Vatika NX Phase II D & H Wing have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vishnu Vatika NX Phase II D & H Wing safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing is registered on MahaRERA as P51700021437, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vishnu Vatika NX Phase II D & H Wing?
Vishnu Vatika NX Phase II D & H Wing is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vishnu Vatika NX Phase II D & H Wing?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vishnu Vatika NX Phase II D & H Wing: gharkundli.com/tools/property-cost-calculator
Has Vishnu Vatika NX Phase II D & H Wing received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing is still under construction, with 31 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vishnu Vatika NX Phase II D & H Wing uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vishnu Vatika NX Phase II D & H Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vishnu Vatika NX Phase II D & H Wing's possession date changes?
The latest dates are on Vishnu Vatika NX Phase II D & H Wing's MahaRERA page (P51700021437). GharKundli's Kundli Watch sends a free WhatsApp update on Vishnu Vatika NX Phase II D & H Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vishnu Vatika NX Phase II D & H Wing have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing has 3 buildings filed: D WING with 8 floors and 40 units; H WING with 12 floors and 107 units; G WING with 8 floors.
How big is the land of Vishnu Vatika NX Phase II D & H Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing stands on 9,990 sq m of land (about 2.5 acres), with 295 sq m of sanctioned built-up area and 997 sq m of recreational open space.
What is the track record of Vishnu Vatika NX Phase II D & H Wing's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Group has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vishnu Vatika NX Phase II D & H Wing?
Google Maps has reviews of Vishnu Vatika NX Phase II D & H Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vishnu Vatika NX Phase II D & H Wing?
Vishnu Vatika NX Phase II D & H Wing by M/S. VISHNU GROUP is in Badlapur Gaon, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700021437, per GharKundli's check of MahaRERA records. Its land is filed as S NO.131/1 AND 132/2 AND 132/5. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Vishnu Vatika NX Phase II D & H Wing, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing has 147 homes in 3 towers registered on MahaRERA, and 72% of them are sold or booked.
When was Vishnu Vatika NX Phase II D & H Wing registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vishnu Vatika NX Phase II D & H Wing was registered on MahaRERA on 28 June 2019. GharKundli did not find a title report on the land on file there.
Does Vishnu Vatika NX Phase II D & H Wing have any legal issues or court cases?
No court cases are listed for Vishnu Vatika NX Phase II D & H Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vishnu Vatika NX Phase II D & H Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S. VISHNU GROUP.
Check it yourself on MahaRERA
- How to check the possession date of Vishnu Vatika NX Phase II D & H Wing
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kulgaon (421503)
- Sai Universe
- Mery Villa CHSL
- Mahavir Heritage
- Infinity Meadows
- Gokul Heights
- Shiv Tirth B Wing
- Prabhu Darshan Co-operative Housing Society Limited
- Dattatray Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.