by KRISHA ENTERPRISES · Titwala, Thane 421605Also near Manda, KalyanRegistered on MahaRERA as “DIYA WOODS”

What’s in the report? →

Possession: Krisha Diya Woods (MahaRERA P51700021634) is marked completed on MahaRERA. It has 102 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700021634. Status: Completed.

Source: MahaRERA website — records for P51700021634, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Krisha Diya Woods?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Krisha Diya Woods has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 29 December 2023

    Extended at the builder's request (MahaRERA application EXT51700013649)

    Reason the builder gave MahaRERA:
    “The project is located at Titwala -EAST, which is a rural area much away from Mumbai limit by about 40 Km. Initially, the project got CC up to 7th Floor on 10/04/2019, when the project was registered. We expected Full CC very soon. However,…” Read the full reason“The project is located at Titwala -EAST, which is a rural area much away from Mumbai limit by about 40 Km. Initially, the project got CC up to 7th Floor on 10/04/2019, when the project was registered. We expected Full CC very soon. However, full CC up to 12th floor was finally received on 30/06/22 after much delay. The delay in full CC coupled with the covid pandemic and related restrictions on construction activity in the area, adversely affected sales and labour/material supply in the project area and caused the delay, because of which the project could not be completed before December, 2…”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51700018754)

    Reason the builder gave MahaRERA:
    “However, due to Occupancy Certificate not get till date & customer booking, Registration of Agreement is still in process, so far the construction of the project could be completed about 80%. Therefore, we expect the project to be completed…” Read the full reason“However, due to Occupancy Certificate not get till date & customer booking, Registration of Agreement is still in process, so far the construction of the project could be completed about 80%. Therefore, we expect the project to be completed by 30.06.2024”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51700023017)

    Reason the builder gave MahaRERA: “Till date almost 90% work is completed and balance finishing work is in progress. We expect completion of the project and issue of Occupancy Certificate by 31.12.2024”
  5. 14 January 2025

    Extended at the builder's request (MahaRERA application EXT51700028291)

    Reason the builder gave MahaRERA:
    “We were under bonafide belief that as we had completed works & applied for OC before the proposed date of completion i.e. 31/12/2024 and it was issued within short period of time i.e. after 14 days from the proposed completion date there is…” Read the full reason“We were under bonafide belief that as we had completed works & applied for OC before the proposed date of completion i.e. 31/12/2024 and it was issued within short period of time i.e. after 14 days from the proposed completion date there is no need for requesting for extension of proposed completion date. Accordingly we uploaded Form 4. Now we received your email dated 17/02/2025 in this regards and accordingly we apply for extension of proposed completion date till 14/01/2025 i.e. date of issue of OC.”

Source: Krisha Diya Woods’s extension records on MahaRERA (P51700021634), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Krisha Diya Woods

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700021634
Status
Completed
Builder
KRISHA ENTERPRISES
Location
Titwala, Thane · 421605
Project type
Others
Registered on
15 Jul 2019
Completion date at registration
December 2022
Latest completion date
January 2025
Delay so far
25 months
Homes
102
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Krisha Diya Woods, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OLIVE100%100%100%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krisha Diya Woods every 1–2 months.

Krisha Diya Woods: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Vraj Realty (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 12 months); 3 still being built, none past the promised date yet; 3 lapsed. 4 complaints on MahaRERA across 3 projects.

Read Google reviews of Krisha Diya Woods →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Krisha Diya Woods: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Krisha Diya Woods

What is the possession date of Krisha Diya Woods?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Krisha Diya Woods in Titwala, Thane is 14 January 2025 — 25 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Krisha Diya Woods?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Krisha Diya Woods's builder has filed on MahaRERA, the official one, is 14 January 2025, already 25 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Krisha Diya Woods extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2023, giving the reason "The project is located at Titwala -EAST, which is a rural area much away from Mumbai limit by about 40 Km. Initially, the project got CC up to 7th Floor on 10/04/2019, when the project was registered. We expected Full CC very soon. However, full CC up to 12th floor was finally received on 30/06/22 after much delay. The delay in full CC coupled with the covid pandemic and related restrictions on construction activity in the area, adversely affected sales and labour/material supply in the project area and caused the delay, because of which the project could not be completed before December, 2…"; to 30 June 2024, giving the reason "However, due to Occupancy Certificate not get till date & customer booking, Registration of Agreement is still in process, so far the construction of the project could be completed about 80%. Therefore, we expect the project to be completed by 30.06.2024"; to 31 December 2024, giving the reason "Till date almost 90% work is completed and balance finishing work is in progress. We expect completion of the project and issue of Occupancy Certificate by 31.12.2024"; to 14 January 2025, giving the reason "We were under bonafide belief that as we had completed works & applied for OC before the proposed date of completion i.e. 31/12/2024 and it was issued within short period of time i.e. after 14 days from the proposed completion date there is no need for requesting for extension of proposed completion date. Accordingly we uploaded Form 4. Now we received your email dated 17/02/2025 in this regards and accordingly we apply for extension of proposed completion date till 14/01/2025 i.e. date of issue of OC.".

What is the RERA number of Krisha Diya Woods?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Krisha Diya Woods in Titwala, Thane is P51700021634.

Is Krisha Diya Woods registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods is registered as P51700021634 and its status is "Completed".

What is the current construction status of Krisha Diya Woods? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods's status on MahaRERA is "Completed". As filed by the builder, slab work on OLIVE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Krisha Diya Woods have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Krisha Diya Woods safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods is registered on MahaRERA as P51700021634, its MahaRERA status is "Completed", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Krisha Diya Woods?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Krisha Diya Woods?

For a flat in Krisha Diya Woods (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Krisha Diya Woods received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Krisha Diya Woods completed?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods is marked completed on MahaRERA, and the completion date filed there is 14 January 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Krisha Diya Woods uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Krisha Diya Woods was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Krisha Diya Woods's possession date changes?

The latest dates are on Krisha Diya Woods's MahaRERA page (P51700021634). GharKundli's Kundli Watch sends a free WhatsApp update on Krisha Diya Woods every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Krisha Diya Woods have?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods has one building filed: OLIVE with 29 floors.

How big is the land of Krisha Diya Woods?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods stands on 2,562 sq m of land (about 0.6 acres), with 3,821 sq m of sanctioned built-up area and 384 sq m of recreational open space.

What is the track record of Krisha Diya Woods's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vraj Realty (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 12 months); 3 still being built, none past the promised date yet; 3 lapsed. 4 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Krisha Diya Woods?

Google Maps has reviews of Krisha Diya Woods written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Krisha Diya Woods?

Krisha Diya Woods by KRISHA ENTERPRISES is in Titwala, Thane, pincode 421605 (near Manda, Kalyan), Maharashtra, and is registered on MahaRERA as P51700021634, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 1 SURVEY NO 113 114,116 HISS N0. 1, 7, 1A. GharKundli lists all 174 MahaRERA projects in Titwala (421605).

How many flats are in Krisha Diya Woods?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods has 102 homes in 1 tower registered on MahaRERA.

When was Krisha Diya Woods registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krisha Diya Woods was registered on MahaRERA on 15 July 2019. GharKundli did not find a title report on the land on file there.

Does Krisha Diya Woods have any legal issues or court cases?

No court cases are listed for Krisha Diya Woods on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Krisha Diya Woods?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KRISHA ENTERPRISES.

Other projects in Titwala (421605)

All 174 projects in Titwala (421605) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.