Moreshwar Parshuram Tower
by MORESHWAR CONSTRUCTIONS · Taluka Kalayn, Thane 421301Registered on MahaRERA as “PARSHURAM TOWER”
What’s in the report? →Possession date of Moreshwar Parshuram Tower (MahaRERA P51700025480): 30 September 2026, moved from 30 September 2025 (12 months later), and it has already passed. It has 42 homes, 53% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700025480. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700025480, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about Moreshwar Parshuram Tower?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Moreshwar Parshuram Tower has moved
30 September 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EXT51700019608)
Source: Moreshwar Parshuram Tower’s extension records on MahaRERA (P51700025480), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Moreshwar Parshuram Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700025480
- Status
- Lapsed (registration period ended)
- Builder
- MORESHWAR CONSTRUCTIONS
- Location
- Taluka Kalayn, Thane · 421301
- Project type
- Others
- Registered on
- 6 Jun 2020
- Completion date at registration
- September 2025
- Latest completion date
- September 2026
- Delay so far
- 12 months
- Homes
- 42
- Sold or booked
- 53%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Moreshwar Parshuram Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 3 | 100% | 100% | 48% | 0% |
| BUILDING NO 4 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 3: covers 7 floors
- BUILDING NO 4: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Moreshwar Parshuram Tower every 1–2 months.
Moreshwar Parshuram Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 3 (9 floors, 42 units) · BUILDING NO 4 (9 floors, 31 units)
- Land: 2,825 sq m (about 0.7 acres) · sanctioned built-up 2,391 sq m
- Land, as filed: OLD SURVEY NO 65 HISSA NO 1 AND 7A NEW SURVEY NO 5 HISSA NO 1 AND 7A
- Map: Get directions
The builder’s record and reviews
Moreshwar Constructions has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 67 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Moreshwar Parshuram Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Moreshwar Parshuram Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Moreshwar Parshuram Tower
What is the possession date of Moreshwar Parshuram Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Moreshwar Parshuram Tower in Taluka Kalayn, Thane is 30 September 2026 — 12 months later than 30 September 2025, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Moreshwar Parshuram Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Moreshwar Parshuram Tower's builder has filed on MahaRERA, the official one, is 30 September 2026, already 12 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Moreshwar Parshuram Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower's builder applied to MahaRERA to extend the completion date once: to 30 September 2026.
What is the RERA number of Moreshwar Parshuram Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Moreshwar Parshuram Tower in Taluka Kalayn, Thane is P51700025480.
Is Moreshwar Parshuram Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower is registered as P51700025480 and its status is "Lapsed (registration period ended)".
What is the current construction status of Moreshwar Parshuram Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Moreshwar Parshuram Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Moreshwar Parshuram Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower is registered on MahaRERA as P51700025480, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Moreshwar Parshuram Tower?
Moreshwar Parshuram Tower isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Moreshwar Parshuram Tower?
For a flat in Moreshwar Parshuram Tower (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Moreshwar Parshuram Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Moreshwar Parshuram Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Moreshwar Parshuram Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Moreshwar Parshuram Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Moreshwar Parshuram Tower's possession date changes?
The latest dates are on Moreshwar Parshuram Tower's MahaRERA page (P51700025480). GharKundli's Kundli Watch sends a free WhatsApp update on Moreshwar Parshuram Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Moreshwar Parshuram Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower has 2 buildings filed: BUILDING NO 3 with 9 floors and 42 units; BUILDING NO 4 with 9 floors and 31 units.
How big is the land of Moreshwar Parshuram Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower stands on 2,825 sq m of land (about 0.7 acres), with 2,391 sq m of sanctioned built-up area.
What is the track record of Moreshwar Parshuram Tower's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Constructions has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 67 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Moreshwar Parshuram Tower?
Google Maps has reviews of Moreshwar Parshuram Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Moreshwar Parshuram Tower?
Moreshwar Parshuram Tower by MORESHWAR CONSTRUCTIONS is in Taluka Kalayn, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700025480, per GharKundli's check of MahaRERA records. Its land is filed as OLD SURVEY NO 65 HISSA NO 1 AND 7A NEW SURVEY NO 5 HISSA NO 1 AND 7A. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Moreshwar Parshuram Tower, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower has 42 homes in 2 towers registered on MahaRERA, and 53% of them are sold or booked.
When was Moreshwar Parshuram Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Moreshwar Parshuram Tower was registered on MahaRERA on 6 June 2020. GharKundli did not find a title report on the land on file there.
Does Moreshwar Parshuram Tower have any legal issues or court cases?
No court cases are listed for Moreshwar Parshuram Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Moreshwar Parshuram Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MORESHWAR CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of Moreshwar Parshuram Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.