Shreenath Royal Castle Phase 2

by SHREENATH DEVELOPERS · Ambernath, Thane 421501Also near PaleRegistered on MahaRERA as “ROYAL CASTLE PHASE 2”

What’s in the report? →

Possession date of Shreenath Royal Castle Phase 2 (MahaRERA P51700021992): 31 May 2027, moved from 30 December 2023 (37 months later). It has 106 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700021992, and currently active. Its completion date has moved from December 2023 to May 2027: 37 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700021992, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shreenath Royal Castle Phase 2?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shreenath Royal Castle Phase 2 has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 28 December 2024

    Extended at the builder's request (MahaRERA application EXT51700011475)

    Reason the builder gave MahaRERA:
    “Due to covid 19,Real estate sector have been badly hampered.In last two year due to labour constraint we could not start the constructon on time.However we tried our level best and could manage to arrange labour in late pandemic stages .but…” Read the full reason“Due to covid 19,Real estate sector have been badly hampered.In last two year due to labour constraint we could not start the constructon on time.However we tried our level best and could manage to arrange labour in late pandemic stages .but still we wont be able to complete the project as on 30-12-23 even after putting all required man ,machine ,material and money,so its our cordial request to you is to extend the period by one year .”
  3. 31 January 2027

    Extended at the builder's request (MahaRERA application EXT51700027429)

    Reason the builder gave MahaRERA: “THERE HAVE DELAY IN THE PROJECT DUE TO FINANCE AND LABOUR CRUNCH”
  4. 31 May 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shreenath Royal Castle Phase 2’s extension records on MahaRERA (P51700021992), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shreenath Royal Castle Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700021992
Status
Registered and active
Builder
SHREENATH DEVELOPERS
Location
Ambernath, Thane · 421501
Project type
Residential / Group Housing
Registered on
25 Aug 2019
Completion date at registration
December 2023
Latest completion date
May 2027
Delay so far
37 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
106
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Shreenath Royal Castle Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAIDEN CASTLE100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreenath Royal Castle Phase 2 every 1–2 months.

Shreenath Royal Castle Phase 2: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Dhanashree Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 still being built, 2 past the promised date (typically 41 months late); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Shreenath Royal Castle Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shreenath Royal Castle Phase 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shreenath Royal Castle Phase 2

What is the possession date of Shreenath Royal Castle Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreenath Royal Castle Phase 2 in Ambernath, Thane is 31 May 2027 — 37 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 37 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shreenath Royal Castle Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreenath Royal Castle Phase 2's builder has filed on MahaRERA, the official one, is 31 May 2027, already 37 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shreenath Royal Castle Phase 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2's builder applied to MahaRERA to extend the completion date 2 times: to 28 December 2024, giving the reason "Due to covid 19,Real estate sector have been badly hampered.In last two year due to labour constraint we could not start the constructon on time.However we tried our level best and could manage to arrange labour in late pandemic stages .but still we wont be able to complete the project as on 30-12-23 even after putting all required man ,machine ,material and money,so its our cordial request to you is to extend the period by one year ."; to 31 January 2027, giving the reason "THERE HAVE DELAY IN THE PROJECT DUE TO FINANCE AND LABOUR CRUNCH". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shreenath Royal Castle Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreenath Royal Castle Phase 2 in Ambernath, Thane is P51700021992.

Is Shreenath Royal Castle Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 is registered as P51700021992 and its status is "Registered and active".

What is the current construction status of Shreenath Royal Castle Phase 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MAIDEN CASTLE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shreenath Royal Castle Phase 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shreenath Royal Castle Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 is registered on MahaRERA as P51700021992, its completion date has moved 37 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shreenath Royal Castle Phase 2?

Shreenath Royal Castle Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shreenath Royal Castle Phase 2?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shreenath Royal Castle Phase 2: gharkundli.com/tools/property-cost-calculator

Has Shreenath Royal Castle Phase 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 is still under construction, with 31 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Shreenath Royal Castle Phase 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreenath Royal Castle Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shreenath Royal Castle Phase 2's possession date changes?

The latest dates are on Shreenath Royal Castle Phase 2's MahaRERA page (P51700021992). GharKundli's Kundli Watch sends a free WhatsApp update on Shreenath Royal Castle Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shreenath Royal Castle Phase 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 has one building filed: MAIDEN CASTLE with 7 floors.

How big is the land of Shreenath Royal Castle Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 stands on 3,300 sq m of land (about 0.8 acres), with 3,868 sq m of sanctioned built-up area and 266 sq m of recreational open space.

What is the track record of Shreenath Royal Castle Phase 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Dhanashree Developers (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 still being built, 2 past the promised date (typically 41 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shreenath Royal Castle Phase 2?

Google Maps has reviews of Shreenath Royal Castle Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shreenath Royal Castle Phase 2?

Shreenath Royal Castle Phase 2 by SHREENATH DEVELOPERS is in Ambernath, Thane, pincode 421501 (near Pale), Maharashtra, and is registered on MahaRERA as P51700021992, per GharKundli's check of MahaRERA records. Its land is filed as S NO 83 H NO 1 PLOT NO 2. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).

How many flats are in Shreenath Royal Castle Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 has 106 homes in 1 tower registered on MahaRERA.

When was Shreenath Royal Castle Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shreenath Royal Castle Phase 2 was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.

Does Shreenath Royal Castle Phase 2 have any legal issues or court cases?

No court cases are listed for Shreenath Royal Castle Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shreenath Royal Castle Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREENATH DEVELOPERS, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Ambernath (421501)

All 486 projects in Ambernath (421501) →

Other projects by SHREENATH DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.