NEW NEELGAGAN CHS

by SCGKCORP · Ambernath, ThaneAlso near Vadavali, Village Kansai, Kher Section

Possession date of NEW NEELGAGAN CHS: 30 October 2030, moved from 31 May 2026 (49 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700053902, and currently active. Its completion date has moved from May 2026 to October 2030: 49 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NEW NEELGAGAN CHS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NEW NEELGAGAN CHS has moved

  1. 31 May 2026

    Completion date given when the project was registered

  2. 30 June 2030

    Extended at the builder's request (MahaRERA application EA04062621239)

    Reason the builder gave MahaRERA: “due to certain technical glitches the completion date got delayed”
  3. 30 October 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NEW NEELGAGAN CHS’s extension records on MahaRERA (P51700053902), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NEW NEELGAGAN CHS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700053902
Status
Registered and active
Builder
SCGKCORP
Location
Ambernath, Thane · 421501
Project type
Residential / Group Housing
Registered on
8 Dec 2023
Completion date at registration
May 2026
Latest completion date
October 2030
Delay so far
49 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
25
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NEW NEELGAGAN CHS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NEW NEELGAGAN CHS PVT LTD100%90%70%0%

Commencement certificate (CC), as filed on MahaRERA

  • NEW NEELGAGAN CHS PVT LTD: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NEW NEELGAGAN CHS every month.

NEW NEELGAGAN CHS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK446 – 49218
1 BHK320 – 3407

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NEW NEELGAGAN CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NEW NEELGAGAN CHS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NEW NEELGAGAN CHS

What is the possession date of NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NEW NEELGAGAN CHS in Ambernath, Thane is 30 October 2030 — 49 months later than 31 May 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NEW NEELGAGAN CHS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NEW NEELGAGAN CHS's builder has filed on MahaRERA, the official one, is 30 October 2030, already 49 months later than the 31 May 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NEW NEELGAGAN CHS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS's builder applied to MahaRERA to extend the completion date once: to 30 June 2030, giving the reason "due to certain technical glitches the completion date got delayed". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NEW NEELGAGAN CHS in Ambernath, Thane is P51700053902.

Is NEW NEELGAGAN CHS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS is registered as P51700053902 and its status is "Registered and active".

What is the construction status of NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NEW NEELGAGAN CHS PVT LTD is 90% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does NEW NEELGAGAN CHS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is NEW NEELGAGAN CHS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS is registered on MahaRERA as P51700053902, its completion date has moved 49 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NEW NEELGAGAN CHS's possession date changes?

The latest dates are on NEW NEELGAGAN CHS's MahaRERA page (P51700053902). GharKundli's Kundli Watch sends a free WhatsApp update on NEW NEELGAGAN CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

What are the flat sizes (carpet area) in NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NEW NEELGAGAN CHS: 2 BHK: 446 to 492 sq ft carpet (18 homes); 1 BHK: 320 to 340 sq ft carpet (7 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS stands on 1,283 sq m of land (about 0.3 acres), with 1,283 sq m of sanctioned built-up area.

Where can I read reviews of NEW NEELGAGAN CHS?

Google Maps has reviews of NEW NEELGAGAN CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NEW NEELGAGAN CHS?

NEW NEELGAGAN CHS by SCGKCORP is in Ambernath, Thane (pincode 421501), near Vadavali, Village Kansai, Kher Section, Maharashtra, and is registered on MahaRERA as P51700053902, per GharKundli's check of MahaRERA records.

How many homes are in NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS has 25 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was NEW NEELGAGAN CHS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NEW NEELGAGAN CHS was registered on MahaRERA on 8 December 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on NEW NEELGAGAN CHS?

No court cases are listed for NEW NEELGAGAN CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NEW NEELGAGAN CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SCGKCORP.

All projects with possession due in 2030 in Thane →

Other projects in pincode 421501

All 486 projects in Ambernath (421501) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.