Pannash
by TECHNICON · Sunil Nagar, Thane 421201Also near Dombivli East, Ramnagar, Ram Nagar
What’s in the report? →Possession date of Pannash (MahaRERA P51700022008): 31 December 2026, moved from 30 December 2023 (32 months later). It has 56 homes, 93% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700022008, and currently active. Its completion date has moved from December 2023 to December 2026: 32 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700022008, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Pannash?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Pannash has moved
30 December 2023
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51700019067)
Reason the builder gave MahaRERA: “UNSOLD UNIT”
31 August 2026
Extended at the builder's request (MahaRERA application EA01102518000)
Reason the builder gave MahaRERA: “Due to shortage of funds and non ability of material”
31 December 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Pannash’s extension records on MahaRERA (P51700022008), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pannash
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700022008
- Status
- Registered and active
- Builder
- TECHNICON
- Location
- Sunil Nagar, Thane · 421201
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2023
- Latest completion date
- December 2026
- Delay so far
- 32 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Pannash, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PANNASH | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- PANNASH: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pannash every 1–2 months.
Pannash: buildings, flats and land, as filed on MahaRERA
- Buildings: PANNASH (15 floors, 56 units)
- Car parking: 10 open
- Land: 1,280 sq m (about 0.3 acres) · sanctioned built-up 1,419 sq m
- Land, as filed: SURVEY NO 95A2 PART AND SURVEY NO 10106
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Pannash →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pannash: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Pannash
What is the possession date of Pannash?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pannash in Sunil Nagar, Thane is 31 December 2026 — 32 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 32 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Pannash?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pannash's builder has filed on MahaRERA, the official one, is 31 December 2026, already 32 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pannash extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "UNSOLD UNIT"; to 31 August 2026, giving the reason "Due to shortage of funds and non ability of material". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Pannash?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pannash in Sunil Nagar, Thane is P51700022008.
Is Pannash registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash is registered as P51700022008 and its status is "Registered and active".
What is the current construction status of Pannash? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PANNASH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Pannash have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Pannash safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash is registered on MahaRERA as P51700022008, its completion date has moved 32 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Pannash?
Pannash is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Pannash?
For a flat in Pannash (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Pannash received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Pannash is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Pannash uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Pannash was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Pannash's possession date changes?
The latest dates are on Pannash's MahaRERA page (P51700022008). GharKundli's Kundli Watch sends a free WhatsApp update on Pannash every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pannash have?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash has one building filed: PANNASH with 15 floors and 56 units.
How much parking does Pannash have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 open car parking spaces for Pannash.
How big is the land of Pannash?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash stands on 1,280 sq m of land (about 0.3 acres), with 1,419 sq m of sanctioned built-up area.
What are the reviews of Pannash?
Google Maps has reviews of Pannash written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Pannash?
Pannash by TECHNICON is in Sunil Nagar, Thane, pincode 421201 (near Dombivli East, Ramnagar, Ram Nagar), Maharashtra, and is registered on MahaRERA as P51700022008, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 95A2 PART AND SURVEY NO 10106. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).
How many flats are in Pannash, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash has 56 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was Pannash registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pannash was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Does Pannash have any legal issues or court cases?
No court cases are listed for Pannash on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Pannash?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TECHNICON.
Check it yourself on MahaRERA
- How to check the possession date of Pannash
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan
- Nav-himalay CHS LTD
- Shree Astaganesh CHS
- Jayram Sadan
- Royal Hills
- Majesty Heights
- Vidhi Impression
- Mangeshi Dhara
- Om Trimurti Darshan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.