Shakti Ramabai Paradise
by SHREE SAI SHAKTI DEVELOPERS · Behind New Golden Nest, Thane 401105Registered on MahaRERA as “RAMABAI PARADISE”
What’s in the report? →Possession date of Shakti Ramabai Paradise (MahaRERA P51700022175): 30 April 2028, moved from 30 December 2025 (24 months later). It has 39 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700022175, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700022175, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shakti Ramabai Paradise?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shakti Ramabai Paradise has moved
30 December 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA05012619285)
Reason the builder gave MahaRERA:
“The delay in completion of the project “Ramabai Paradise” is due to reasons beyond the control of the promoter. Although the Mira Bhayandar Municipal Corporation (MBMC) issued the Original Commencement Certificate (CC) on 29/03/2019, MBMC i…” Read the full reason
“The delay in completion of the project “Ramabai Paradise” is due to reasons beyond the control of the promoter. Although the Mira Bhayandar Municipal Corporation (MBMC) issued the Original Commencement Certificate (CC) on 29/03/2019, MBMC imposed a stay on the said CC vide its letter dated 26/09/2019 pursuant to a complaint filed by Mr. Nandkumar Moreshwar Patil. The said complaint was dismissed by the Hon’ble Court vide order dated 07/12/2023. Thereafter, MBMC, vide its orders dated 19/12/2024, lifted/withdrew the stay and permitted commencement of construction. Accordingly, extension of t…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shakti Ramabai Paradise’s extension records on MahaRERA (P51700022175), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shakti Ramabai Paradise
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700022175
- Status
- Registered and active
- Builder
- SHREE SAI SHAKTI DEVELOPERS
- Location
- Behind New Golden Nest, Thane · 401105
- Project type
- Residential / Group Housing
- Registered on
- 4 Sep 2019
- Completion date at registration
- December 2025
- Latest completion date
- April 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 39
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Shakti Ramabai Paradise, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAMABAI PARADISE - BLDG 2 | 100% | 0% | 0% | 0% |
| RAMABAI PARADISE - BLDG 1 | 100% | 15% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RAMABAI PARADISE - BLDG 2: covers 9 floors
- RAMABAI PARADISE - BLDG 1: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shakti Ramabai Paradise every 1–2 months.
Shakti Ramabai Paradise: buildings, flats and land, as filed on MahaRERA
- Buildings: RAMABAI PARADISE - BLDG 2 (34 floors, 35 units) · RAMABAI PARADISE - BLDG 1 (26 floors, 4 units)
- Land: 4,020 sq m (about 1.0 acres) · sanctioned built-up 3,379 sq m · recreational space 603 sq m
- Boundaries filed include: SHALINI COMPLEX
- Land, as filed: S. NO.329 OLD 28 NEW H. NO.8 S. NO. OLD 330 NEW 37 H. NO. 3
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shakti Ramabai Paradise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shakti Ramabai Paradise: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shakti Ramabai Paradise
What is the possession date of Shakti Ramabai Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shakti Ramabai Paradise in Behind New Golden Nest, Thane is 30 April 2028 — 24 months later than 30 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shakti Ramabai Paradise?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shakti Ramabai Paradise's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shakti Ramabai Paradise extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The delay in completion of the project “Ramabai Paradise” is due to reasons beyond the control of the promoter. Although the Mira Bhayandar Municipal Corporation (MBMC) issued the Original Commencement Certificate (CC) on 29/03/2019, MBMC imposed a stay on the said CC vide its letter dated 26/09/2019 pursuant to a complaint filed by Mr. Nandkumar Moreshwar Patil. The said complaint was dismissed by the Hon’ble Court vide order dated 07/12/2023. Thereafter, MBMC, vide its orders dated 19/12/2024, lifted/withdrew the stay and permitted commencement of construction. Accordingly, extension of t…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Shakti Ramabai Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shakti Ramabai Paradise in Behind New Golden Nest, Thane is P51700022175.
Is Shakti Ramabai Paradise registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise is registered as P51700022175 and its status is "Registered and active".
What is the current construction status of Shakti Ramabai Paradise? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 15% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Shakti Ramabai Paradise have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shakti Ramabai Paradise safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise is registered on MahaRERA as P51700022175, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shakti Ramabai Paradise?
Shakti Ramabai Paradise is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shakti Ramabai Paradise?
For a flat in Shakti Ramabai Paradise (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shakti Ramabai Paradise received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shakti Ramabai Paradise uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shakti Ramabai Paradise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shakti Ramabai Paradise's possession date changes?
The latest dates are on Shakti Ramabai Paradise's MahaRERA page (P51700022175). GharKundli's Kundli Watch sends a free WhatsApp update on Shakti Ramabai Paradise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shakti Ramabai Paradise have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise has 2 buildings filed: RAMABAI PARADISE - BLDG 2 with 34 floors and 35 units; RAMABAI PARADISE - BLDG 1 with 26 floors and 4 units.
How big is the land of Shakti Ramabai Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise stands on 4,020 sq m of land (about 1.0 acres), with 3,379 sq m of sanctioned built-up area and 603 sq m of recreational open space.
What are the reviews of Shakti Ramabai Paradise?
Google Maps has reviews of Shakti Ramabai Paradise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shakti Ramabai Paradise?
Shakti Ramabai Paradise by SHREE SAI SHAKTI DEVELOPERS is in Behind New Golden Nest, Thane, pincode 401105, Maharashtra, and is registered on MahaRERA as P51700022175, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHALINI COMPLEX. Its land is filed as S. NO.329 OLD 28 NEW H. NO.8 S. NO. OLD 330 NEW 37 H. NO. 3. GharKundli lists all 99 MahaRERA projects in Bhayander East (401105).
How many flats are in Shakti Ramabai Paradise, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise has 39 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Shakti Ramabai Paradise registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shakti Ramabai Paradise was registered on MahaRERA on 4 September 2019. GharKundli did not find a title report on the land on file there.
Does Shakti Ramabai Paradise have any legal issues or court cases?
No court cases are listed for Shakti Ramabai Paradise on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shakti Ramabai Paradise?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SAI SHAKTI DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shakti Ramabai Paradise
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in Thane
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Mauli Krupa
- Gurukrupa Nityam
- Lotus
- Urban Reserve Wing B
- Asavari Co Op HSG Soc LTD
- Panache
Other projects by SHREE SAI SHAKTI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.