Harmony
by Trimity Constructions · Vishnu Nagar, Thane
Possession date of Harmony: 30 April 2027, moved from 30 March 2023 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700022306, and currently active. Its completion date has moved from March 2023 to April 2027: 45 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Harmony?
How the possession date of Harmony has moved
30 March 2023
Completion date given when the project was registered
29 March 2024
Extended at the builder's request (MahaRERA application EXT51700015407)
Reason the builder gave MahaRERA: “As per the attachment”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700019072)
Reason the builder gave MahaRERA: “As per the attachment”
31 December 2026
Extended at the builder's request (MahaRERA application EA31102518216)
Reason the builder gave MahaRERA:
“We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstan…” Read the full reason
“We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Further, the contractor who was en…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Harmony’s extension records on MahaRERA (P51700022306), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Harmony
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700022306
- Status
- Registered and active
- Builder
- Trimity Constructions
- Location
- Vishnu Nagar, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 9 Sep 2019
- Completion date at registration
- March 2023
- Latest completion date
- April 2027
- Delay so far
- 45 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Sold or booked
- 81%
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Harmony, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Harmony | 100% | 100% | 55% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Harmony: covers 13 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Harmony every month.
Harmony: buildings, flats and land, as filed on MahaRERA
- Buildings: Harmony (14 floors, 48 units)
- Car parking: 35 covered
- Land: 1,003 sq m (about 0.2 acres) · sanctioned built-up 3,529 sq m
- Boundaries filed include: Baji Prabhu Deshpande Marg
The builder’s record and reviews
Trimity Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 23 months); 3 still being built, 2 past the promised date (typically 23 months late). 8 complaints on MahaRERA across 2 projects.
Read Google reviews of Harmony →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Harmony: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Harmony
What is the possession date of Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Harmony in Vishnu Nagar, Thane is 30 April 2027 — 45 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Harmony?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Harmony's builder has filed on MahaRERA, the official one, is 30 April 2027, already 45 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Harmony extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony's builder applied to MahaRERA to extend the completion date 3 times: to 29 March 2024, giving the reason "As per the attachment"; to 31 December 2025, giving the reason "As per the attachment"; to 31 December 2026, giving the reason "We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Further, the contractor who was en…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Harmony in Vishnu Nagar, Thane is P51700022306.
Is Harmony registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony is registered as P51700022306 and its status is "Registered and active".
What is the construction status of Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Harmony is 100% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.
Does Harmony have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Harmony safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony is registered on MahaRERA as P51700022306, its completion date has moved 45 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Harmony's possession date changes?
The latest dates are on Harmony's MahaRERA page (P51700022306). GharKundli's Kundli Watch sends a free WhatsApp update on Harmony every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Harmony have?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony has one building filed: Harmony with 14 floors and 48 units.
How much parking does Harmony have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 35 covered car parking spaces for Harmony.
How big is the land of Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony stands on 1,003 sq m of land (about 0.2 acres), with 3,529 sq m of sanctioned built-up area.
What is the track record of Harmony's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 23 months); 3 still being built, 2 past the promised date (typically 23 months late). 8 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Harmony?
Google Maps has reviews of Harmony written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Harmony?
Harmony by Trimity Constructions is in Vishnu Nagar, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700022306, per GharKundli's check of MahaRERA records. Its boundaries filed there include Baji Prabhu Deshpande Marg.
How many homes are in Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony has 48 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.
When was Harmony registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony was registered on MahaRERA on 9 September 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Harmony?
No court cases are listed for Harmony on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Harmony?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Trimity Constructions, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Harmony
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Thane
- EKATVA SIGNET
- Sindhusmruti
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- GURUKRUPA NITYAM
- MAULI KRUPA
- Panache
- LOTUS
Other projects by Trimity Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.