SHRI SHIVANAND CHS
by Trimity Constructions · Bhaskar Colony, Thane
Possession: SHRI SHIVANAND CHS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700024183. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHRI SHIVANAND CHS?
How the possession date of SHRI SHIVANAND CHS has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT51700016808)
Reason the builder gave MahaRERA: “As per the attachment”
19 August 2024
Extended at the builder's request (MahaRERA application EXT51700025168)
Reason the builder gave MahaRERA: “As per attachment”
Source: SHRI SHIVANAND CHS’s extension records on MahaRERA (P51700024183), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHRI SHIVANAND CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the August 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700024183
- Status
- Completed
- Builder
- Trimity Constructions
- Location
- Bhaskar Colony, Thane · 400602
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2020
- Completion date at registration
- June 2023
- Latest completion date
- August 2024
- Delay so far
- 14 months
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SHRI SHIVANAND CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SBI Employees Shri Shivanand CHS Ltd | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI SHIVANAND CHS every month.
SHRI SHIVANAND CHS: buildings, flats and land, as filed on MahaRERA
- Buildings: SBI Employees Shri Shivanand CHS Ltd (9 floors)
- Land: 899 sq m (about 0.2 acres) · sanctioned built-up 899 sq m
- Boundaries filed include: RESERVE BANK OF INDIA CHSL, PUBLIC ROAD
The builder’s record and reviews
Trimity Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 23 months); 3 still being built, 2 past the promised date (typically 23 months late). 8 complaints on MahaRERA across 2 projects.
Read Google reviews of SHRI SHIVANAND CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHRI SHIVANAND CHS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHRI SHIVANAND CHS
What is the possession date of SHRI SHIVANAND CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRI SHIVANAND CHS in Bhaskar Colony, Thane is 19 August 2024 — 14 months later than 30 June 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHRI SHIVANAND CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI SHIVANAND CHS's builder has filed on MahaRERA, the official one, is 19 August 2024, already 14 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHRI SHIVANAND CHS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2024, giving the reason "As per the attachment"; to 19 August 2024, giving the reason "As per attachment".
What is the RERA number of SHRI SHIVANAND CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRI SHIVANAND CHS in Bhaskar Colony, Thane is P51700024183.
Is SHRI SHIVANAND CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS is registered as P51700024183 and its status is "Completed".
What is the construction status of SHRI SHIVANAND CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS's status on MahaRERA is "Completed". As filed by the builder, slab work on SBI Employees Shri Shivanand CHS Ltd is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHRI SHIVANAND CHS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHRI SHIVANAND CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS is registered on MahaRERA as P51700024183, its MahaRERA status is "Completed", its completion date has moved 14 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHRI SHIVANAND CHS's possession date changes?
The latest dates are on SHRI SHIVANAND CHS's MahaRERA page (P51700024183). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI SHIVANAND CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHRI SHIVANAND CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS has one building filed: SBI Employees Shri Shivanand CHS Ltd with 9 floors.
How big is the land of SHRI SHIVANAND CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS stands on 899 sq m of land (about 0.2 acres), with 899 sq m of sanctioned built-up area.
What is the track record of SHRI SHIVANAND CHS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimity Constructions (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 23 months); 3 still being built, 2 past the promised date (typically 23 months late). 8 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHRI SHIVANAND CHS?
Google Maps has reviews of SHRI SHIVANAND CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHRI SHIVANAND CHS?
SHRI SHIVANAND CHS by Trimity Constructions is in Bhaskar Colony, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700024183, per GharKundli's check of MahaRERA records. Its boundaries filed there include RESERVE BANK OF INDIA CHSL, PUBLIC ROAD.
When was SHRI SHIVANAND CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI SHIVANAND CHS was registered on MahaRERA on 24 January 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on SHRI SHIVANAND CHS?
No court cases are listed for SHRI SHIVANAND CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHRI SHIVANAND CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Trimity Constructions, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHRI SHIVANAND CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- RAMCHANDRA CO-OPERATIVE HOUSING SOCIETY LIMITED
- NEW THANA CHS
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- Panache
Other projects by Trimity Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.