Skip to content
GharKundli

GHP Aurum

by Shree GHP Housing · Thane 400601Also near Kalwa, JekegramRegistered on MahaRERA as “AURUM”

What’s in the report? →

Possession date of GHP Aurum (MahaRERA P51700022870): 15 January 2027, moved from 15 September 2023 (36 months later). It has 61 homes, 29% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700022870, and currently active. Its completion date has moved from September 2023 to January 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700022870, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about GHP Aurum?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of GHP Aurum has moved

  1. 15 September 2023

    Completion date given when the project was registered

  2. 15 September 2025

    Extended at the builder's request (MahaRERA application EXT51700018960)

    Reason the builder gave MahaRERA:
    “The construction was delayed due to DP road from 9 mtrs to 12 mtrs. was not sanctioned, so we are not getting permission of construction above 10 floors. Now DP road sanctioned from TMC and we have received CC upto 16th floors of the projec…” Read the full reason“The construction was delayed due to DP road from 9 mtrs to 12 mtrs. was not sanctioned, so we are not getting permission of construction above 10 floors. Now DP road sanctioned from TMC and we have received CC upto 16th floors of the project as on date 15.01.2024”
  3. 15 September 2026

    Extended at the builder's request (MahaRERA application EA07082502320)

    Reason the builder gave MahaRERA: “we got the CC, but due to delay period the Labour contractor was not willing to work as per the old rate, therefore we had to search for other Labour contractors.”
  4. 15 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GHP Aurum’s extension records on MahaRERA (P51700022870), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GHP Aurum

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700022870
Status
Registered and active
Builder
Shree GHP Housing
Location
Thane · 400601
Project type
Residential / Group Housing
Registered on
1 Nov 2019
Completion date at registration
September 2023
Latest completion date
January 2027
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
61
Sold or booked
29%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GHP Aurum, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AURUM100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • AURUM: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GHP Aurum every 1–2 months.

GHP Aurum: buildings, flats and land, as filed on MahaRERA

  • Buildings: AURUM (17 floors, 63 units)
  • Car parking: 67 covered
  • Land: 2,184 sq m (about 0.5 acres) · sanctioned built-up 5,094 sq m · recreational space 393 sq m
  • Land, as filed: 28 and 36 Tika No.5
  • Map: Get directions

The builder’s record and reviews

Sunrise Housing (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 9 months); 3 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.

Read Google reviews of GHP Aurum →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GHP Aurum: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about GHP Aurum

What is the possession date of GHP Aurum?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GHP Aurum in Thane is 15 January 2027 — 36 months later than 15 September 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for GHP Aurum?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GHP Aurum's builder has filed on MahaRERA, the official one, is 15 January 2027, already 36 months later than the 15 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GHP Aurum extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum's builder applied to MahaRERA to extend the completion date 2 times: to 15 September 2025, giving the reason "The construction was delayed due to DP road from 9 mtrs to 12 mtrs. was not sanctioned, so we are not getting permission of construction above 10 floors. Now DP road sanctioned from TMC and we have received CC upto 16th floors of the project as on date 15.01.2024"; to 15 September 2026, giving the reason "we got the CC, but due to delay period the Labour contractor was not willing to work as per the old rate, therefore we had to search for other Labour contractors.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GHP Aurum?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GHP Aurum in Thane is P51700022870.

Is GHP Aurum registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum is registered as P51700022870 and its status is "Registered and active".

What is the current construction status of GHP Aurum? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AURUM is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GHP Aurum have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GHP Aurum safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum is registered on MahaRERA as P51700022870, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in GHP Aurum?

GHP Aurum is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in GHP Aurum?

For a flat in GHP Aurum (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has GHP Aurum received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum is still under construction, with 15 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has GHP Aurum uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for GHP Aurum was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if GHP Aurum's possession date changes?

The latest dates are on GHP Aurum's MahaRERA page (P51700022870). GharKundli's Kundli Watch sends a free WhatsApp update on GHP Aurum every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GHP Aurum have?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum has one building filed: AURUM with 17 floors and 63 units.

How much parking does GHP Aurum have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 67 covered car parking spaces for GHP Aurum.

How big is the land of GHP Aurum?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum stands on 2,184 sq m of land (about 0.5 acres), with 5,094 sq m of sanctioned built-up area and 393 sq m of recreational open space.

What is the track record of GHP Aurum's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Housing (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 9 months); 3 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of GHP Aurum?

Google Maps has reviews of GHP Aurum written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of GHP Aurum?

GHP Aurum by Shree GHP Housing is in Thane, pincode 400601 (near Kalwa, Jekegram), Maharashtra, and is registered on MahaRERA as P51700022870, per GharKundli's check of MahaRERA records. Its land is filed as 28 and 36 Tika No.5. GharKundli lists all 178 MahaRERA projects in Thane (400601).

How many flats are in GHP Aurum, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum has 61 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.

When was GHP Aurum registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GHP Aurum was registered on MahaRERA on 1 November 2019. GharKundli did not find a title report on the land on file there.

Does GHP Aurum have any legal issues or court cases?

No court cases are listed for GHP Aurum on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of GHP Aurum?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree GHP Housing.

All projects with possession due in 2027 in Thane →

Other projects in Thane (400601)

All 178 projects in Thane (400601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.