Silver Sagar Apt
by Silver & Rashi Constructions · Bhayander East, Thane 401105Also near Navghar, Bhayandar West, GoddevRegistered on MahaRERA as “Sagar Apt”
What’s in the report? →Possession date of Silver Sagar Apt (MahaRERA P51700023901): 30 November 2027, moved from 1 September 2024 (34 months later). It has 130 homes, 84% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700023901, and currently active. Its completion date has moved from September 2024 to November 2027: 34 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700023901, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Silver Sagar Apt?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Silver Sagar Apt has moved
1 September 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025201)
Reason the builder gave MahaRERA:
“Unforeseen delays have impacted our project timeline due to supply chain disruptions, labor shortages, and delays in the procurement of essential materials. These challenges are beyond the control of the developer and have necessitated addi…” Read the full reason
“Unforeseen delays have impacted our project timeline due to supply chain disruptions, labor shortages, and delays in the procurement of essential materials. These challenges are beyond the control of the developer and have necessitated additional time to ensure the project meets the required quality standards and complies with safety regulations. Furthermore, we anticipate that obtaining the No Objection Certificate (NOC) and Occupancy Certificate (OC) may require additional time; however, we have already applied for the Fire NOC to facilitate this process.”30 July 2027
Extended at the builder's request (MahaRERA application EA05022619729)
Reason the builder gave MahaRERA:
“The primary cause of delays has been a shortage of skilled labour and contractor resources, which significantly impacted the project's timeline. In addition, unforeseen disruptions in the supply chain—particularly from May to December—due t…” Read the full reason
“The primary cause of delays has been a shortage of skilled labour and contractor resources, which significantly impacted the project's timeline. In addition, unforeseen disruptions in the supply chain—particularly from May to December—due to issues with contractors and distributors, affected the timely availability of critical materials, further compounding the delays.”30 November 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Silver Sagar Apt’s extension records on MahaRERA (P51700023901), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Silver Sagar Apt
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700023901
- Status
- Registered and active
- Builder
- Silver & Rashi Constructions
- Location
- Bhayander East, Thane · 401105
- Project type
- Residential / Group Housing
- Registered on
- 10 Jan 2020
- Completion date at registration
- September 2024
- Latest completion date
- November 2027
- Delay so far
- 34 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 130
- Sold or booked
- 84%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Silver Sagar Apt, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sagar Apartment | 100% | 100% | 100% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- Sagar Apartment: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Silver Sagar Apt every 1–2 months.
Silver Sagar Apt: buildings, flats and land, as filed on MahaRERA
- Buildings: Sagar Apartment (11 floors, 130 units)
- Land: 1,350 sq m (about 0.3 acres) · sanctioned built-up 3,153 sq m · recreational space 130 sq m
- Land, as filed: 99/7A New 114/7P Old
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Silver & Rashi Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Silver Sagar Apt →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Silver Sagar Apt: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Silver Sagar Apt
What is the possession date of Silver Sagar Apt?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Silver Sagar Apt in Bhayander East, Thane is 30 November 2027 — 34 months later than 1 September 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 34 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Silver Sagar Apt?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Silver Sagar Apt's builder has filed on MahaRERA, the official one, is 30 November 2027, already 34 months later than the 1 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Silver Sagar Apt extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Unforeseen delays have impacted our project timeline due to supply chain disruptions, labor shortages, and delays in the procurement of essential materials. These challenges are beyond the control of the developer and have necessitated additional time to ensure the project meets the required quality standards and complies with safety regulations. Furthermore, we anticipate that obtaining the No Objection Certificate (NOC) and Occupancy Certificate (OC) may require additional time; however, we have already applied for the Fire NOC to facilitate this process."; to 30 July 2027, giving the reason "The primary cause of delays has been a shortage of skilled labour and contractor resources, which significantly impacted the project's timeline. In addition, unforeseen disruptions in the supply chain—particularly from May to December—due to issues with contractors and distributors, affected the timely availability of critical materials, further compounding the delays.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Silver Sagar Apt?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Silver Sagar Apt in Bhayander East, Thane is P51700023901.
Is Silver Sagar Apt registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt is registered as P51700023901 and its status is "Registered and active".
What is the current construction status of Silver Sagar Apt? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sagar Apartment is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Silver Sagar Apt have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Silver Sagar Apt safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt is registered on MahaRERA as P51700023901, its completion date has moved 34 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Silver Sagar Apt?
Silver Sagar Apt is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Silver Sagar Apt?
For a flat in Silver Sagar Apt (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Silver Sagar Apt received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt is still under construction, with 30 November 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Silver Sagar Apt a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt is a redevelopment: 66 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Silver Sagar Apt uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Silver Sagar Apt was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Silver Sagar Apt's possession date changes?
The latest dates are on Silver Sagar Apt's MahaRERA page (P51700023901). GharKundli's Kundli Watch sends a free WhatsApp update on Silver Sagar Apt every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Silver Sagar Apt have?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt has one building filed: Sagar Apartment with 11 floors and 130 units.
How big is the land of Silver Sagar Apt?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt stands on 1,350 sq m of land (about 0.3 acres), with 3,153 sq m of sanctioned built-up area and 130 sq m of recreational open space.
What is the track record of Silver Sagar Apt's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver & Rashi Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Silver Sagar Apt?
Google Maps has reviews of Silver Sagar Apt written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Silver Sagar Apt?
Silver Sagar Apt by Silver & Rashi Constructions is in Bhayander East, Thane, pincode 401105 (near Navghar, Bhayandar West, Goddev), Maharashtra, and is registered on MahaRERA as P51700023901, per GharKundli's check of MahaRERA records. Its land is filed as 99/7A New 114/7P Old. GharKundli lists all 99 MahaRERA projects in Bhayander East (401105).
How many flats are in Silver Sagar Apt, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt has 130 homes in 1 tower registered on MahaRERA, and 84% of them are sold or booked.
When was Silver Sagar Apt registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Silver Sagar Apt was registered on MahaRERA on 10 January 2020. GharKundli did not find a title report on the land on file there.
Does Silver Sagar Apt have any legal issues or court cases?
No court cases are listed for Silver Sagar Apt on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Silver Sagar Apt?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Silver & Rashi Constructions, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Silver Sagar Apt
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Bhayander East (401105)
All 99 projects in Bhayander East (401105) →Other projects by Silver & Rashi Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.