Akshar Rose Tower
by AKSHAR SHANTI REALTORS PRIVATE LIMITED · Shanti Garden, Thane 401107Also near Mira Road East, Pleasant Park, Mira BhayandarRegistered on MahaRERA as “Rose Tower”
What’s in the report? →Possession date of Akshar Rose Tower (MahaRERA P51700024772): 30 April 2031, moved from 30 December 2026 (48 months later). It has 140 homes, 6% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700024772, and currently active. Its completion date has moved from December 2026 to April 2031: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700024772, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Akshar Rose Tower?
9 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Akshar Rose Tower has moved
30 December 2026
Completion date given when the project was registered
31 December 2030
Extended at the builder's request (MahaRERA application EA20022619925)
Reason the builder gave MahaRERA:
“1) Post-COVID-19 Impact: Construction was temporarily halted due to government restrictions and safety protocols. Even after reopening, labour shortages, supply chain disruptions, delayed material procurement, and reduced site productivity…” Read the full reason
“1) Post-COVID-19 Impact: Construction was temporarily halted due to government restrictions and safety protocols. Even after reopening, labour shortages, supply chain disruptions, delayed material procurement, and reduced site productivity slowed project progress. 2) Delay in Construction Start: Pandemic-related constraints prevented construction from commencing as per the original schedule, shifting the overall project timeline. 3) Revision in Planning: Project plans were revised to address updated requirements, regulatory changes, and design modifications, requiring reworked drawings, fre…”30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Akshar Rose Tower’s extension records on MahaRERA (P51700024772), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Akshar Rose Tower
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 9 court cases, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700024772
- Status
- Registered and active
- Builder
- AKSHAR SHANTI REALTORS PRIVATE LIMITED
- Location
- Shanti Garden, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 5 Mar 2020
- Completion date at registration
- December 2026
- Latest completion date
- April 2031
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 140
- Sold or booked
- 6%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 9
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Akshar Rose Tower, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C WING | 100% | 24% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- C WING: covers G+P+24
Latest CC order on MahaRERA: dated 02/12/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Akshar Rose Tower every 1–2 months.
Akshar Rose Tower: buildings, flats and land, as filed on MahaRERA
- Buildings: C WING (26 floors, 140 units)
- Car parking: 68 covered
- Land: 10,090 sq m (about 2.5 acres) · sanctioned built-up 7,717 sq m · recreational space 836 sq m
- Boundaries filed include: MIRA DHAM CO-OPERATIVE SOCIETY, ROYAL GARDEN C H S
- Land, as filed: 12/1
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Akshar Shanti Realtors (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, none past the promised date yet. 15 complaints on MahaRERA across 2 projects.
Read Google reviews of Akshar Rose Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Akshar Rose Tower: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Akshar Rose Tower
What is the possession date of Akshar Rose Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Akshar Rose Tower in Shanti Garden, Thane is 30 April 2031 — 48 months later than 30 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Akshar Rose Tower?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Akshar Rose Tower's builder has filed on MahaRERA, the official one, is 30 April 2031, already 48 months later than the 30 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Akshar Rose Tower extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "1) Post-COVID-19 Impact: Construction was temporarily halted due to government restrictions and safety protocols. Even after reopening, labour shortages, supply chain disruptions, delayed material procurement, and reduced site productivity slowed project progress. 2) Delay in Construction Start: Pandemic-related constraints prevented construction from commencing as per the original schedule, shifting the overall project timeline. 3) Revision in Planning: Project plans were revised to address updated requirements, regulatory changes, and design modifications, requiring reworked drawings, fre…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Akshar Rose Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Akshar Rose Tower in Shanti Garden, Thane is P51700024772.
Is Akshar Rose Tower registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower is registered as P51700024772 and its status is "Registered and active".
What is the current construction status of Akshar Rose Tower? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower's status on MahaRERA is "Registered and active". As filed by the builder, slab work on C WING is 24% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Akshar Rose Tower have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Akshar Rose Tower safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower is registered on MahaRERA as P51700024772, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Akshar Rose Tower?
Akshar Rose Tower is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Akshar Rose Tower?
For a flat in Akshar Rose Tower (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Akshar Rose Tower received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Akshar Rose Tower uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Akshar Rose Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Akshar Rose Tower's possession date changes?
The latest dates are on Akshar Rose Tower's MahaRERA page (P51700024772). GharKundli's Kundli Watch sends a free WhatsApp update on Akshar Rose Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Akshar Rose Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower has one building filed: C WING with 26 floors and 140 units.
How much parking does Akshar Rose Tower have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 68 covered car parking spaces for Akshar Rose Tower.
How big is the land of Akshar Rose Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower stands on 10,090 sq m of land (about 2.5 acres), with 7,717 sq m of sanctioned built-up area and 836 sq m of recreational open space.
What is the track record of Akshar Rose Tower's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Shanti Realtors (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, none past the promised date yet. 15 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Akshar Rose Tower?
Google Maps has reviews of Akshar Rose Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Akshar Rose Tower?
Akshar Rose Tower by AKSHAR SHANTI REALTORS PRIVATE LIMITED is in Shanti Garden, Thane, pincode 401107 (near Mira Road East, Pleasant Park, Mira Bhayandar), Maharashtra, and is registered on MahaRERA as P51700024772, per GharKundli's check of MahaRERA records. Its boundaries filed there include MIRA DHAM CO-OPERATIVE SOCIETY, ROYAL GARDEN C H S. Its land is filed as 12/1. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).
How many flats are in Akshar Rose Tower, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower has 140 homes in 1 tower registered on MahaRERA, and 6% of them are sold or booked.
When was Akshar Rose Tower registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Rose Tower was registered on MahaRERA on 5 March 2020. GharKundli did not find a title report on the land on file there.
Does Akshar Rose Tower have any legal issues or court cases?
9 court cases are listed for Akshar Rose Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Akshar Rose Tower?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AKSHAR SHANTI REALTORS PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Akshar Rose Tower
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in Thane
- Imperial Heights Phase I - A and B Wing
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Gurukrupa Nityam
- Mauli Krupa
- Urban Reserve Wing B
- Panache
- Lotus
Other projects by AKSHAR SHANTI REALTORS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.