Vaikunth Cluster 3 T1
by PEPL Developers Pvt Ltd (PRL) · Sandozbaugh, Thane
Possession date of Vaikunth Cluster 3 T1: 30 June 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700024023, and currently active. 9 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vaikunth Cluster 3 T1?
How the possession date of Vaikunth Cluster 3 T1 has moved
30 June 2026
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EA02062621194)
Reason the builder gave MahaRERA:
“1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in…” Read the full reason
“1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in the matter. Such revision mandatorily required prior approval from the Ministry of Environment, Forest and Climate Change (“MoEF”), without which further construction could not legally proceed. The situation was further aggravated by the complete non functioning of the concerned MoEF Committee from January 2024 to May 2024, a circumstance wholly beyond th…”
Source: Vaikunth Cluster 3 T1’s extension records on MahaRERA (P51700024023), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vaikunth Cluster 3 T1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 9 complaints and 8 court cases, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Vaikunth Cluster 1P51700003535 · possession 30 Dec 2022
- Vaikunth Cluster 2P51700003793 · possession 30 Dec 2024
- Vaikunth Cluster 3 Tower 2P51700024580 · possession 30 Jun 2027
- Vaikunth Cluster 3 Tower 3PR1332022601156 · possession 30 Oct 2032
- Vaikunth Cluster 4P51700003283 · possession 30 Dec 2023
- Vaikunth Cluster 4AP51700005256 · possession 31 Jul 2024
- MahaRERA registration
- P51700024023
- Status
- Registered and active
- Builder
- PEPL Developers Pvt Ltd
- Location
- Sandozbaugh, Thane · 400607
- Project type
- Residential / Group Housing
- Registered on
- 14 Jan 2020
- Completion date at registration
- June 2026
- Latest completion date
- June 2027
- Delay so far
- 12 months
- Homes
- 557
- Sold or booked
- 93%
- Towers
- 1
- Complaints on MahaRERA
- 9
- Court cases listed
- 8
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Vaikunth Cluster 3 T1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vidya | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Vidya: covers Lower ground + upper Gr. + 1st to 41st floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vaikunth Cluster 3 T1 every month.
Vaikunth Cluster 3 T1: buildings, flats and land, as filed on MahaRERA
- Buildings: Vidya (46 floors, 557 units)
- Car parking: 279 covered
- Land: 727 sq m (about 0.2 acres) · sanctioned built-up 22,690 sq m
The builder’s record and reviews
Piramal Estate (a group of 4 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 22 GharKundli has checked: 12 finished, all within the promised date; 8 still being built, none past the promised date yet; 2 lapsed. 131 complaints on MahaRERA across 16 projects.
Read Google reviews of Vaikunth Cluster 3 T1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vaikunth Cluster 3 T1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vaikunth Cluster 3 T1
What is the possession date of Vaikunth Cluster 3 T1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vaikunth Cluster 3 T1 in Sandozbaugh, Thane is 30 June 2027 — 12 months later than 30 June 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Vaikunth Cluster 3 T1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vaikunth Cluster 3 T1's builder has filed on MahaRERA, the official one, is 30 June 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vaikunth Cluster 3 T1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in the matter. Such revision mandatorily required prior approval from the Ministry of Environment, Forest and Climate Change (“MoEF”), without which further construction could not legally proceed. The situation was further aggravated by the complete non functioning of the concerned MoEF Committee from January 2024 to May 2024, a circumstance wholly beyond th…".
What is the RERA number of Vaikunth Cluster 3 T1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vaikunth Cluster 3 T1 in Sandozbaugh, Thane is P51700024023.
Is Vaikunth Cluster 3 T1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1 is registered as P51700024023 and its status is "Registered and active".
What is the construction status of Vaikunth Cluster 3 T1?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vidya is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vaikunth Cluster 3 T1 have complaints on MahaRERA?
9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Vaikunth Cluster 3 T1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1 is registered on MahaRERA as P51700024023, its completion date has moved 12 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Vaikunth Cluster 3 T1 have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: Vaikunth Cluster 1 (P51700003535, possession 30 Dec 2022); Vaikunth Cluster 2 (P51700003793, possession 30 Dec 2024); Vaikunth Cluster 3 Tower 2 (P51700024580, possession 30 Jun 2027); Vaikunth Cluster 3 Tower 3 (PR1332022601156, possession 30 Oct 2032); Vaikunth Cluster 4 (P51700003283, possession 30 Dec 2023); Vaikunth Cluster 4A (P51700005256, possession 31 Jul 2024). Check that your agreement names the registration of your own wing.
How can I get updates if Vaikunth Cluster 3 T1's possession date changes?
The latest dates are on Vaikunth Cluster 3 T1's MahaRERA page (P51700024023). GharKundli's Kundli Watch sends a free WhatsApp update on Vaikunth Cluster 3 T1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vaikunth Cluster 3 T1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1 has one building filed: Vidya with 46 floors and 557 units.
How much parking does Vaikunth Cluster 3 T1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 279 covered car parking spaces for Vaikunth Cluster 3 T1.
How big is the land of Vaikunth Cluster 3 T1?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1 stands on 727 sq m of land (about 0.2 acres), with 22,690 sq m of sanctioned built-up area.
What is the track record of Vaikunth Cluster 3 T1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Piramal Estate (a group of 4 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 22 GharKundli has checked: 12 finished, all within the promised date; 8 still being built, none past the promised date yet; 2 lapsed. 131 complaints on MahaRERA across 16 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vaikunth Cluster 3 T1?
Google Maps has reviews of Vaikunth Cluster 3 T1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vaikunth Cluster 3 T1?
Vaikunth Cluster 3 T1 by PEPL Developers Pvt Ltd (PRL) is in Sandozbaugh, Thane (pincode 400607), Maharashtra, and is registered on MahaRERA as P51700024023, per GharKundli's check of MahaRERA records.
How many homes are in Vaikunth Cluster 3 T1?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1 has 557 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.
When was Vaikunth Cluster 3 T1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 T1 was registered on MahaRERA on 14 January 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on Vaikunth Cluster 3 T1?
8 court cases are listed for Vaikunth Cluster 3 T1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Vaikunth Cluster 3 T1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PEPL Developers Pvt Ltd, the company PRL files this project under, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vaikunth Cluster 3 T1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400607
- UNIQUE VISTAS-BLDG. NO. 3
- UNIQUE VISTAS-BLDG. NO. 5
- Godrej Exquisite
- Elanor - Tower 1
- Elanor - Tower 2
- Lodha Kolshet A2 - Tower 3
- Sector B- Tower A and B
- Hiranandani Westgate - Hampstead
Other projects by PEPL Developers Pvt Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.