Vaikunth Cluster 3 Tower 2

by PEPL Developers Pvt Ltd (PRL) · Balkum, ThaneAlso near Jekegram

Possession date of Vaikunth Cluster 3 Tower 2: 30 June 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700024580, and currently active. 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Vaikunth Cluster 3 Tower 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vaikunth Cluster 3 Tower 2 has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA02062621195)

    Reason the builder gave MahaRERA:
    “1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in…” Read the full reason“1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in the matter. Such revision mandatorily required prior approval from the Ministry of Environment, Forest and Climate Change (“MoEF”), without which further construction could not legally proceed. The situation was further aggravated by the complete non functioning of the concerned MoEF Committee from January 2024 to May 2024, a circumstance wholly beyond th…”

Source: Vaikunth Cluster 3 Tower 2’s extension records on MahaRERA (P51700024580), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vaikunth Cluster 3 Tower 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints and 4 court cases, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700024580
Status
Registered and active
Builder
PEPL Developers Pvt Ltd
Location
Balkum, Thane · 400608
Project type
Residential / Group Housing
Registered on
24 Feb 2020
Completion date at registration
June 2026
Latest completion date
June 2027
Delay so far
12 months
Homes
635
Sold or booked
95%
Towers
1
Complaints on MahaRERA
9
Court cases listed
4
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Vaikunth Cluster 3 Tower 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vind100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Vind: covers Lower ground + upper Gr. + 1st to 41st floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vaikunth Cluster 3 Tower 2 every month.

Vaikunth Cluster 3 Tower 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vind (46 floors, 635 units)
  • Land: 1,239 sq m (about 0.3 acres) · sanctioned built-up 38,952 sq m

The builder’s record and reviews

Piramal Estate (a group of 4 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 22 GharKundli has checked: 12 finished, all within the promised date; 8 still being built, none past the promised date yet; 2 lapsed. 131 complaints on MahaRERA across 16 projects.

Read Google reviews of Vaikunth Cluster 3 Tower 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vaikunth Cluster 3 Tower 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vaikunth Cluster 3 Tower 2

What is the possession date of Vaikunth Cluster 3 Tower 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vaikunth Cluster 3 Tower 2 in Balkum, Thane is 30 June 2027 — 12 months later than 30 June 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Vaikunth Cluster 3 Tower 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vaikunth Cluster 3 Tower 2's builder has filed on MahaRERA, the official one, is 30 June 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vaikunth Cluster 3 Tower 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in the matter. Such revision mandatorily required prior approval from the Ministry of Environment, Forest and Climate Change (“MoEF”), without which further construction could not legally proceed. The situation was further aggravated by the complete non functioning of the concerned MoEF Committee from January 2024 to May 2024, a circumstance wholly beyond th…".

What is the RERA number of Vaikunth Cluster 3 Tower 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vaikunth Cluster 3 Tower 2 in Balkum, Thane is P51700024580.

Is Vaikunth Cluster 3 Tower 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2 is registered as P51700024580 and its status is "Registered and active".

What is the construction status of Vaikunth Cluster 3 Tower 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vind is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vaikunth Cluster 3 Tower 2 have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Vaikunth Cluster 3 Tower 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2 is registered on MahaRERA as P51700024580, its completion date has moved 12 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Vaikunth Cluster 3 Tower 2 have other wings or phases?

Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: Vaikunth Cluster 1 (P51700003535, possession 30 Dec 2022); Vaikunth Cluster 2 (P51700003793, possession 30 Dec 2024); Vaikunth Cluster 3 T1 (P51700024023, possession 30 Jun 2027); Vaikunth Cluster 3 Tower 3 (PR1332022601156, possession 30 Oct 2032); Vaikunth Cluster 4 (P51700003283, possession 30 Dec 2023); Vaikunth Cluster 4A (P51700005256, possession 31 Jul 2024). Check that your agreement names the registration of your own wing.

How can I get updates if Vaikunth Cluster 3 Tower 2's possession date changes?

The latest dates are on Vaikunth Cluster 3 Tower 2's MahaRERA page (P51700024580). GharKundli's Kundli Watch sends a free WhatsApp update on Vaikunth Cluster 3 Tower 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vaikunth Cluster 3 Tower 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2 has one building filed: Vind with 46 floors and 635 units.

How big is the land of Vaikunth Cluster 3 Tower 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2 stands on 1,239 sq m of land (about 0.3 acres), with 38,952 sq m of sanctioned built-up area.

What is the track record of Vaikunth Cluster 3 Tower 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Piramal Estate (a group of 4 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 22 GharKundli has checked: 12 finished, all within the promised date; 8 still being built, none past the promised date yet; 2 lapsed. 131 complaints on MahaRERA across 16 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Vaikunth Cluster 3 Tower 2?

Google Maps has reviews of Vaikunth Cluster 3 Tower 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vaikunth Cluster 3 Tower 2?

Vaikunth Cluster 3 Tower 2 by PEPL Developers Pvt Ltd (PRL) is in Balkum, Thane (pincode 400608), near Jekegram, Maharashtra, and is registered on MahaRERA as P51700024580, per GharKundli's check of MahaRERA records.

How many homes are in Vaikunth Cluster 3 Tower 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2 has 635 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.

When was Vaikunth Cluster 3 Tower 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vaikunth Cluster 3 Tower 2 was registered on MahaRERA on 24 February 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Vaikunth Cluster 3 Tower 2?

4 court cases are listed for Vaikunth Cluster 3 Tower 2 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Vaikunth Cluster 3 Tower 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PEPL Developers Pvt Ltd, the company PRL files this project under, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in pincode 400608

All 55 projects in Balkum (400608) →

Other projects by PEPL Developers Pvt Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.