Mahavir Bliss
by M/s. Shivshakti Engineers (Vinayak) · Balkum, ThaneAlso near Dhokali
Possession date of Mahavir Bliss: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700033859, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Mahavir Bliss?
How the possession date of Mahavir Bliss has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA01122518478)
Reason the builder gave MahaRERA:
“Pertaining to the matter under the above caption, we would like to inform you that clause 25 of the Agreement for Sale executed with the flat purchasers as well as copy of the Agreement for Sale uploaded on the MahaRERA portal provides for…” Read the full reason
“Pertaining to the matter under the above caption, we would like to inform you that clause 25 of the Agreement for Sale executed with the flat purchasers as well as copy of the Agreement for Sale uploaded on the MahaRERA portal provides for a moratorium period of 12 (twelve) months from the agreed date of possession for completing the project. We would further like to state that due to shortage of semi-skilled labour on site we are unable to complete the project within the stipulated time period. We tried reaching out to the customers for their consent for applying for an extension for the s…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mahavir Bliss’s extension records on MahaRERA (P51700033859), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahavir Bliss
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700033859
- Status
- Registered and active
- Builder
- M/s. Shivshakti Engineers
- Location
- Balkum, Thane · 400608
- Project type
- Others
- Registered on
- 14 Mar 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 178
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Mahavir Bliss, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Mahavir Bliss | 100% | 100% | 78% | 19% |
Commencement certificate (CC), as filed on MahaRERA
- Mahavir Bliss: covers ground + 1st to 23rd Floors
Latest CC order on MahaRERA: dated 12/08/2022.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahavir Bliss every month.
Mahavir Bliss: buildings, flats and land, as filed on MahaRERA
- Buildings: Mahavir Bliss (24 floors, 184 units)
- Car parking: 83 covered
- Land: 2,402 sq m (about 0.6 acres) · sanctioned built-up 8,195 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects.
Read Google reviews of Mahavir Bliss →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahavir Bliss: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mahavir Bliss
What is the possession date of Mahavir Bliss?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mahavir Bliss in Balkum, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Mahavir Bliss?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahavir Bliss's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mahavir Bliss extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Pertaining to the matter under the above caption, we would like to inform you that clause 25 of the Agreement for Sale executed with the flat purchasers as well as copy of the Agreement for Sale uploaded on the MahaRERA portal provides for a moratorium period of 12 (twelve) months from the agreed date of possession for completing the project. We would further like to state that due to shortage of semi-skilled labour on site we are unable to complete the project within the stipulated time period. We tried reaching out to the customers for their consent for applying for an extension for the s…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Mahavir Bliss?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mahavir Bliss in Balkum, Thane is P51700033859.
Is Mahavir Bliss registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss is registered as P51700033859 and its status is "Registered and active".
What is the construction status of Mahavir Bliss?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Mahavir Bliss is 100% done and internal work 78%. GharKundli's full report compares construction progress with the deadline.
Does Mahavir Bliss have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mahavir Bliss safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss is registered on MahaRERA as P51700033859, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mahavir Bliss's possession date changes?
The latest dates are on Mahavir Bliss's MahaRERA page (P51700033859). GharKundli's Kundli Watch sends a free WhatsApp update on Mahavir Bliss every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahavir Bliss have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss has one building filed: Mahavir Bliss with 24 floors and 184 units.
How much parking does Mahavir Bliss have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 83 covered car parking spaces for Mahavir Bliss.
How big is the land of Mahavir Bliss?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss stands on 2,402 sq m of land (about 0.6 acres), with 8,195 sq m of sanctioned built-up area.
What is the track record of Mahavir Bliss's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Mahavir Bliss?
Google Maps has reviews of Mahavir Bliss written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mahavir Bliss?
Mahavir Bliss by M/s. Shivshakti Engineers (Vinayak) is in Balkum, Thane (pincode 400608), near Dhokali, Maharashtra, and is registered on MahaRERA as P51700033859, per GharKundli's check of MahaRERA records.
How many homes are in Mahavir Bliss?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss has 178 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was Mahavir Bliss registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Bliss was registered on MahaRERA on 14 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Mahavir Bliss?
No court cases are listed for Mahavir Bliss on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Mahavir Bliss?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Shivshakti Engineers, the company Vinayak files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Mahavir Bliss
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400608
- HIGHLAND SPRINGS B4- C WING
- HIGHLAND SPRINGS B4 D WING
- Vaikunth Cluster 3 Tower 2
- SHRADDHA PENINSULA
- SUMEET ELITE
- MARKANDEY SQUARE
- Mangeshi heights
- ONE DOSTI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.