by Dosti Enterprises · Balkum, ThaneAlso near Kolshet, Sandozbaugh
Possession date of ONE DOSTI: 18 July 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PC1330002600012, and currently active. Its completion date is now July 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ONE DOSTI?
How the possession date of ONE DOSTI has moved
18 March 2031
Completion date given when the project was registered
18 July 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ONE DOSTI’s extension records on MahaRERA (PC1330002600012), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ONE DOSTI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 court cases, and how it ended
- Construction pace against the July 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PC1330002600012
- Status
- Registered and active
- Builder
- Dosti Enterprises
- Location
- Balkum, Thane · 400608
- Project type
- Commercial
- Registered on
- 6 Apr 2026
- Completion date at registration
- March 2031
- Latest completion date
- July 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 32%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of ONE DOSTI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG NO 1 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLDG NO 1: covers 14 floors
Latest CC order on MahaRERA: dated 20/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ONE DOSTI every month.
ONE DOSTI: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG NO 1 (14 floors, 240 units)
- Car parking: 628 covered
- Land: 7,680 sq m (about 1.9 acres) · sanctioned built-up 21,726 sq m · recreational space 719 sq m
- Boundaries filed include: BHIWANDI WADPA ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects.
Read Google reviews of ONE DOSTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ONE DOSTI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ONE DOSTI
What is the possession date of ONE DOSTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ONE DOSTI in Balkum, Thane is 18 July 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ONE DOSTI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ONE DOSTI's builder has filed on MahaRERA, the official one, is 18 July 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ONE DOSTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ONE DOSTI in Balkum, Thane is PC1330002600012.
Is ONE DOSTI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI is registered as PC1330002600012 and its status is "Registered and active".
What is the construction status of ONE DOSTI?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLDG NO 1 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does ONE DOSTI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ONE DOSTI safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI is registered on MahaRERA as PC1330002600012, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ONE DOSTI's possession date changes?
The latest dates are on ONE DOSTI's MahaRERA page (PC1330002600012). GharKundli's Kundli Watch sends a free WhatsApp update on ONE DOSTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ONE DOSTI have?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI has one building filed: BLDG NO 1 with 14 floors and 240 units.
How much parking does ONE DOSTI have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 628 covered car parking spaces for ONE DOSTI.
How big is the land of ONE DOSTI?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI stands on 7,680 sq m of land (about 1.9 acres), with 21,726 sq m of sanctioned built-up area and 719 sq m of recreational open space.
What is the track record of ONE DOSTI's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ONE DOSTI?
Google Maps has reviews of ONE DOSTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ONE DOSTI?
ONE DOSTI by Dosti Enterprises is in Balkum, Thane (pincode 400608), near Kolshet, Sandozbaugh, Maharashtra, and is registered on MahaRERA as PC1330002600012, per GharKundli's check of MahaRERA records. Its boundaries filed there include BHIWANDI WADPA ROAD.
How many homes are in ONE DOSTI?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI has 0 homes in 1 tower registered on MahaRERA, and 32% of them are sold or booked.
When was ONE DOSTI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ONE DOSTI was registered on MahaRERA on 6 April 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on ONE DOSTI?
5 court cases are listed for ONE DOSTI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ONE DOSTI?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Dosti Enterprises, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ONE DOSTI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in pincode 400608
- HIGHLAND SPRINGS B4- C WING
- HIGHLAND SPRINGS B4 D WING
- Vaikunth Cluster 3 Tower 2
- Mahavir Bliss
- SHRADDHA PENINSULA
- SUMEET ELITE
- MARKANDEY SQUARE
- Mangeshi heights
Other projects by Dosti Enterprises
- DOSTI PRIMUS-PHASE 1
- Dosti West County - Dosti Nest - Phase 4
- DOSTI WEST COUNTY - PHASE 4- DOSTI PINE
- DOSTI WEST COUNTY - DOSTI TULIP
- Dosti West County - Dosti Nest - Phase 1
- Dosti West County - Dosti Nest - Phase 3
- Dosti West County - Dosti Nest - Phase 2
- DOSTI WEST COUNTY - PHASE 5 - DOSTI OLIVE - WING A
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.