Possession date of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700025834, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE has moved

  1. 30 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DOSTI WEST COUNTY - PHASE 4- DOSTI PINE’s extension records on MahaRERA (P51700025834), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DOSTI WEST COUNTY - PHASE 4- DOSTI PINE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints and 11 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700025834
Status
Registered and active
Builder
DOSTI ENTERPRISES
Location
Balkum, Thane · 400607
Project type
Others
Registered on
19 Jul 2020
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
897
Sold or booked
96%
Towers
5
Complaints on MahaRERA
3
Court cases listed
11
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DOSTI PINE- WING A100%100%100%100%
DOSTI PINE WING B100%100%100%100%
DOSTI PINE WING C100%100%100%100%
DOSTI PINE WING D100%100%100%93%
DOSTI PINE WING E100%100%90%68%

Commencement certificate (CC), as filed on MahaRERA

  • DOSTI PINE- WING A: covers 30 floors
  • DOSTI PINE WING B: covers 30 floors
  • DOSTI PINE WING C: covers 30 floors
  • DOSTI PINE WING D: covers 30 floors
  • DOSTI PINE WING E: covers 30 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DOSTI WEST COUNTY - PHASE 4- DOSTI PINE every month.

DOSTI WEST COUNTY - PHASE 4- DOSTI PINE: buildings, flats and land, as filed on MahaRERA

  • Buildings: DOSTI PINE- WING A (40 floors, 215 units) · DOSTI PINE WING B (40 floors, 243 units) · DOSTI PINE WING C (40 floors, 153 units) · DOSTI PINE WING D (40 floors, 115 units) · DOSTI PINE WING E (33 floors, 175 units)
  • Land: 2,940 sq m (about 0.7 acres) · sanctioned built-up 54,684 sq m · recreational space 13,437 sq m

The builder’s record and reviews

Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects.

Read Google reviews of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DOSTI WEST COUNTY - PHASE 4- DOSTI PINE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DOSTI WEST COUNTY - PHASE 4- DOSTI PINE

What is the possession date of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DOSTI WEST COUNTY - PHASE 4- DOSTI PINE in Balkum, Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DOSTI WEST COUNTY - PHASE 4- DOSTI PINE's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE in Balkum, Thane is P51700025834.

Is DOSTI WEST COUNTY - PHASE 4- DOSTI PINE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE is registered as P51700025834 and its status is "Registered and active".

What is the construction status of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does DOSTI WEST COUNTY - PHASE 4- DOSTI PINE have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is DOSTI WEST COUNTY - PHASE 4- DOSTI PINE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE is registered on MahaRERA as P51700025834, its completion date has not been moved by the builder and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DOSTI WEST COUNTY - PHASE 4- DOSTI PINE's possession date changes?

The latest dates are on DOSTI WEST COUNTY - PHASE 4- DOSTI PINE's MahaRERA page (P51700025834). GharKundli's Kundli Watch sends a free WhatsApp update on DOSTI WEST COUNTY - PHASE 4- DOSTI PINE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DOSTI WEST COUNTY - PHASE 4- DOSTI PINE have?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE has 5 buildings filed: DOSTI PINE- WING A with 40 floors and 215 units; DOSTI PINE WING B with 40 floors and 243 units; DOSTI PINE WING C with 40 floors and 153 units; DOSTI PINE WING D with 40 floors and 115 units; DOSTI PINE WING E with 33 floors and 175 units.

How big is the land of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE stands on 2,940 sq m of land (about 0.7 acres), with 54,684 sq m of sanctioned built-up area and 13,437 sq m of recreational open space.

What is the track record of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

Google Maps has reviews of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

DOSTI WEST COUNTY - PHASE 4- DOSTI PINE by DOSTI ENTERPRISES is in Balkum, Thane (pincode 400607), near Sandozbaugh, Maharashtra, and is registered on MahaRERA as P51700025834, per GharKundli's check of MahaRERA records.

How many homes are in DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE has 897 homes in 5 towers registered on MahaRERA, and 96% of them are sold or booked.

When was DOSTI WEST COUNTY - PHASE 4- DOSTI PINE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WEST COUNTY - PHASE 4- DOSTI PINE was registered on MahaRERA on 19 July 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

11 court cases are listed for DOSTI WEST COUNTY - PHASE 4- DOSTI PINE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of DOSTI WEST COUNTY - PHASE 4- DOSTI PINE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DOSTI ENTERPRISES, which has 14 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Balkum

All 218 projects in Sandozbaugh (400607) →

Other projects by DOSTI ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.