Dosti West County - Dosti Nest - Phase 2
by DOSTI ENTERPRISES · Balkum Thane, ThaneAlso near Naupada, Majiwada, Badlapur
Possession date of Dosti West County - Dosti Nest - Phase 2: 30 October 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700033663, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Dosti West County - Dosti Nest - Phase 2?
How the possession date of Dosti West County - Dosti Nest - Phase 2 has moved
30 June 2027
Completion date given when the project was registered
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Dosti West County - Dosti Nest - Phase 2’s extension records on MahaRERA (P51700033663), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Dosti West County - Dosti Nest - Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 12 court cases, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Dosti West County - Dosti Nest - Phase 1P51700033640 · possession 30 Oct 2027
- Dosti West County - Dosti Nest - Phase 3P51700049724 · possession 31 Dec 2027
- Dosti West County - Dosti Nest - Phase 4P51700050253 · possession 30 Apr 2028
- MahaRERA registration
- P51700033663
- Status
- Registered and active
- Builder
- DOSTI ENTERPRISES
- Location
- Balkum Thane, Thane · 400608
- Project type
- Residential / Group Housing
- Registered on
- 2 Mar 2022
- Completion date at registration
- June 2027
- Latest completion date
- October 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 373
- Sold or booked
- 99%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 12
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of Dosti West County - Dosti Nest - Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A of Dosti Dove Building | 100% | 100% | 100% | 57% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A of Dosti Dove Building: covers 27 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dosti West County - Dosti Nest - Phase 2 every month.
Dosti West County - Dosti Nest - Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A of Dosti Dove Building (37 floors, 373 units)
- Land: 2,460 sq m (about 0.6 acres) · sanctioned built-up 15,454 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects.
Read Google reviews of Dosti West County - Dosti Nest - Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Dosti West County - Dosti Nest - Phase 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Dosti West County - Dosti Nest - Phase 2
What is the possession date of Dosti West County - Dosti Nest - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Dosti West County - Dosti Nest - Phase 2 in Balkum Thane, Thane is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Dosti West County - Dosti Nest - Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Dosti West County - Dosti Nest - Phase 2's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Dosti West County - Dosti Nest - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Dosti West County - Dosti Nest - Phase 2 in Balkum Thane, Thane is P51700033663.
Is Dosti West County - Dosti Nest - Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2 is registered as P51700033663 and its status is "Registered and active".
What is the construction status of Dosti West County - Dosti Nest - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A of Dosti Dove Building is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Dosti West County - Dosti Nest - Phase 2 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Dosti West County - Dosti Nest - Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2 is registered on MahaRERA as P51700033663, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Dosti West County - Dosti Nest - Phase 2 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Dosti West County - Dosti Nest - Phase 1 (P51700033640, possession 30 Oct 2027); Dosti West County - Dosti Nest - Phase 3 (P51700049724, possession 31 Dec 2027); Dosti West County - Dosti Nest - Phase 4 (P51700050253, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Dosti West County - Dosti Nest - Phase 2's possession date changes?
The latest dates are on Dosti West County - Dosti Nest - Phase 2's MahaRERA page (P51700033663). GharKundli's Kundli Watch sends a free WhatsApp update on Dosti West County - Dosti Nest - Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Dosti West County - Dosti Nest - Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2 has one building filed: Wing A of Dosti Dove Building with 37 floors and 373 units.
How big is the land of Dosti West County - Dosti Nest - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2 stands on 2,460 sq m of land (about 0.6 acres), with 15,454 sq m of sanctioned built-up area.
What is the track record of Dosti West County - Dosti Nest - Phase 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Dosti West County - Dosti Nest - Phase 2?
Google Maps has reviews of Dosti West County - Dosti Nest - Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Dosti West County - Dosti Nest - Phase 2?
Dosti West County - Dosti Nest - Phase 2 by DOSTI ENTERPRISES is in Balkum Thane, Thane (pincode 400608), near Naupada, Majiwada, Badlapur, Maharashtra, and is registered on MahaRERA as P51700033663, per GharKundli's check of MahaRERA records.
How many homes are in Dosti West County - Dosti Nest - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2 has 373 homes in 1 tower registered on MahaRERA, and 99% of them are sold or booked.
When was Dosti West County - Dosti Nest - Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti West County - Dosti Nest - Phase 2 was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Dosti West County - Dosti Nest - Phase 2?
12 court cases are listed for Dosti West County - Dosti Nest - Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Dosti West County - Dosti Nest - Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DOSTI ENTERPRISES, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Dosti West County - Dosti Nest - Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400608
- HIGHLAND SPRINGS B4- C WING
- HIGHLAND SPRINGS B4 D WING
- Vaikunth Cluster 3 Tower 2
- Mahavir Bliss
- SHRADDHA PENINSULA
- MARKANDEY SQUARE
- Mangeshi heights
- ONE DOSTI
Other projects by DOSTI ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.