Madhusudan Building
by MADHUSUDAN BUILDCON · Kansai Section, Thane 421501Also near Ambernath, Kher Section, Kohoj Khuntavali
What’s in the report? →Possession date of Madhusudan Building (MahaRERA P51700035033): 30 April 2027, moved from 31 December 2023 (36 months later). It has 12 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700035033, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700035033, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Madhusudan Building?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Madhusudan Building has moved
31 December 2023
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700027771)
Reason the builder gave MahaRERA: “Due to financial difficulty and due to non booking of units unable to complete the project within time”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Madhusudan Building’s extension records on MahaRERA (P51700035033), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Madhusudan Building
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700035033
- Status
- Registered and active
- Builder
- MADHUSUDAN BUILDCON
- Location
- Kansai Section, Thane · 421501
- Project type
- Residential / Group Housing
- Registered on
- 29 Apr 2022
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 12
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Madhusudan Building, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MADHUSUDAN APARTMENT | 0% | 6% | 10% | 30% |
Commencement certificate (CC), as filed on MahaRERA
- MADHUSUDAN APARTMENT: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Madhusudan Building every 1–2 months.
Madhusudan Building: buildings, flats and land, as filed on MahaRERA
- Buildings: MADHUSUDAN APARTMENT (8 floors, 13 units)
- Car parking: 1 covered, 1 open
- Land: 581 sq m (about 0.1 acres) · sanctioned built-up 783 sq m
- Boundaries filed include: MUNICIPLA SCHOOL
- Land, as filed: PLOT NO. 138, CTS NOS. 3918 TO 3924
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Madhusudan Building →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Madhusudan Building: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Madhusudan Building
What is the possession date of Madhusudan Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Madhusudan Building in Kansai Section, Thane is 30 April 2027 — 36 months later than 31 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Madhusudan Building?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Madhusudan Building's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Madhusudan Building extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to financial difficulty and due to non booking of units unable to complete the project within time". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Madhusudan Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Madhusudan Building in Kansai Section, Thane is P51700035033.
Is Madhusudan Building registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building is registered as P51700035033 and its status is "Registered and active".
What is the current construction status of Madhusudan Building? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MADHUSUDAN APARTMENT is 6% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Madhusudan Building have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Madhusudan Building safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building is registered on MahaRERA as P51700035033, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Madhusudan Building?
Madhusudan Building is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Madhusudan Building?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Madhusudan Building: gharkundli.com/tools/property-cost-calculator
Has Madhusudan Building received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Madhusudan Building uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Madhusudan Building was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Madhusudan Building's possession date changes?
The latest dates are on Madhusudan Building's MahaRERA page (P51700035033). GharKundli's Kundli Watch sends a free WhatsApp update on Madhusudan Building every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Madhusudan Building have?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building has one building filed: MADHUSUDAN APARTMENT with 8 floors and 13 units.
How much parking does Madhusudan Building have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 1 open car parking spaces for Madhusudan Building.
How big is the land of Madhusudan Building?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building stands on 581 sq m of land (about 0.1 acres), with 783 sq m of sanctioned built-up area.
What are the reviews of Madhusudan Building?
Google Maps has reviews of Madhusudan Building written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Madhusudan Building?
Madhusudan Building by MADHUSUDAN BUILDCON is in Kansai Section, Thane, pincode 421501 (near Ambernath, Kher Section, Kohoj Khuntavali), Maharashtra, and is registered on MahaRERA as P51700035033, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPLA SCHOOL. Its land is filed as PLOT NO. 138, CTS NOS. 3918 TO 3924. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Madhusudan Building, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building has 12 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Madhusudan Building registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhusudan Building was registered on MahaRERA on 29 April 2022. GharKundli did not find a title report on the land on file there.
Does Madhusudan Building have any legal issues or court cases?
No court cases are listed for Madhusudan Building on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Madhusudan Building?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MADHUSUDAN BUILDCON.
Check it yourself on MahaRERA
- How to check the possession date of Madhusudan Building
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Ambernath (421501)
- Paritosh Co Operative Housing Society Limited
- New Neelgagan CHS
- Next Crown Landmark
- Mahadev Heights
- Chadha Residency
- Panvelkar Daffodils-Plot No. 11,12,13
- Neelkanth Royale Palms - F Wing Phase II
- Ishwar Jay Jay Shankara Co-op. Housing Society LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.