by A S D C DEVELOPERS · Bhadrawati Peth, SolapurAlso near Railway Lines, Majrewadi

Possession date of SNC GRAND RESIDENCE: 31 July 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52600046941. Status: Lapsed (registration period ended). Its completion date is now July 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about SNC GRAND RESIDENCE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SNC GRAND RESIDENCE has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SNC GRAND RESIDENCE’s extension records on MahaRERA (P52600046941), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SNC GRAND RESIDENCE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52600046941
Status
Lapsed (registration period ended)
Builder
A S D C DEVELOPERS
Location
Bhadrawati Peth, Solapur · 413005
Project type
Residential / Group Housing
Registered on
26 Sep 2022
Completion date at registration
March 2026
Latest completion date
July 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SNC GRAND RESIDENCE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SNC GRAND RESIDENCE100%90%40%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SNC GRAND RESIDENCE every month.

SNC GRAND RESIDENCE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SNC GRAND RESIDENCE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SNC GRAND RESIDENCE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SNC GRAND RESIDENCE

What is the possession date of SNC GRAND RESIDENCE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SNC GRAND RESIDENCE in Bhadrawati Peth, Solapur is 31 July 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SNC GRAND RESIDENCE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SNC GRAND RESIDENCE's builder has filed on MahaRERA, the official one, is 31 July 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SNC GRAND RESIDENCE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SNC GRAND RESIDENCE in Bhadrawati Peth, Solapur is P52600046941.

Is SNC GRAND RESIDENCE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE is registered as P52600046941 and its status is "Lapsed (registration period ended)".

What is the construction status of SNC GRAND RESIDENCE?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SNC GRAND RESIDENCE is 90% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does SNC GRAND RESIDENCE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SNC GRAND RESIDENCE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE is registered on MahaRERA as P52600046941, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SNC GRAND RESIDENCE's possession date changes?

The latest dates are on SNC GRAND RESIDENCE's MahaRERA page (P52600046941). GharKundli's Kundli Watch sends a free WhatsApp update on SNC GRAND RESIDENCE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SNC GRAND RESIDENCE have?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE has one building filed: SNC GRAND RESIDENCE with 7 floors.

How big is the land of SNC GRAND RESIDENCE?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE stands on 485 sq m of land (about 0.1 acres), with 1,399 sq m of sanctioned built-up area.

Where can I read reviews of SNC GRAND RESIDENCE?

Google Maps has reviews of SNC GRAND RESIDENCE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SNC GRAND RESIDENCE?

SNC GRAND RESIDENCE by A S D C DEVELOPERS is in Bhadrawati Peth, Solapur (pincode 413005), near Railway Lines, Majrewadi, Maharashtra, and is registered on MahaRERA as P52600046941, per GharKundli's check of MahaRERA records.

How many homes are in SNC GRAND RESIDENCE?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE has 20 homes in 1 tower registered on MahaRERA.

When was SNC GRAND RESIDENCE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SNC GRAND RESIDENCE was registered on MahaRERA on 26 September 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SNC GRAND RESIDENCE?

No court cases are listed for SNC GRAND RESIDENCE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SNC GRAND RESIDENCE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is A S D C DEVELOPERS.

All projects with possession due in 2026 in Solapur →

Other projects in Solapur North

All 20 projects in Daji Peth (413005) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.