Valencia

by IMPRESSIONS · Mahatma Phule Road, Thane 421202Also near Dombivli West, Ramnagar, Dombivli East

What’s in the report? →

Possession date of Valencia (MahaRERA P51700024879): 31 July 2027, moved from 30 June 2024 (33 months later). It has 34 homes, 76% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700024879, and currently active. Its completion date has moved from June 2024 to July 2027: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700024879, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Valencia?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Valencia has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700027273)

    Reason the builder gave MahaRERA: “Project work is almost completed and the balance work will be completed by March 2025.”
  3. 31 March 2027

    Extended at the builder's request (MahaRERA application EA20042620676)

    Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
  4. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Valencia’s extension records on MahaRERA (P51700024879), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Valencia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700024879
Status
Registered and active
Builder
IMPRESSIONS
Location
Mahatma Phule Road, Thane · 421202
Project type
Residential / Group Housing
Registered on
9 Mar 2020
Completion date at registration
June 2024
Latest completion date
July 2027
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
34
Sold or booked
76%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Valencia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VALENCIA100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • VALENCIA: covers 15 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Valencia every 1–2 months.

Valencia: buildings, flats and land, as filed on MahaRERA

  • Buildings: VALENCIA (15 floors, 56 units)
  • Car parking: 19 covered
  • Land: 888 sq m (about 0.2 acres) · sanctioned built-up 4,220 sq m
  • Boundaries filed include: KARVE ROAD, MAHATMA PHULE ROAD
  • Land, as filed: C T S NO 2065 TO 2068, 1465 AND 1466
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Valencia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Valencia: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Valencia

What is the possession date of Valencia?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Valencia in Mahatma Phule Road, Thane is 31 July 2027 — 33 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Valencia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Valencia's builder has filed on MahaRERA, the official one, is 31 July 2027, already 33 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Valencia extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Project work is almost completed and the balance work will be completed by March 2025."; to 31 March 2027, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Valencia?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Valencia in Mahatma Phule Road, Thane is P51700024879.

Is Valencia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia is registered as P51700024879 and its status is "Registered and active".

What is the current construction status of Valencia? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VALENCIA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Valencia have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Valencia safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia is registered on MahaRERA as P51700024879, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Valencia?

Valencia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Valencia?

For a flat in Valencia (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Valencia received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Valencia is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Valencia a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia is a redevelopment: 7 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Valencia uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Valencia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Valencia's possession date changes?

The latest dates are on Valencia's MahaRERA page (P51700024879). GharKundli's Kundli Watch sends a free WhatsApp update on Valencia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Valencia have?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia has one building filed: VALENCIA with 15 floors and 56 units.

How much parking does Valencia have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 19 covered car parking spaces for Valencia.

How big is the land of Valencia?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia stands on 888 sq m of land (about 0.2 acres), with 4,220 sq m of sanctioned built-up area.

What are the reviews of Valencia?

Google Maps has reviews of Valencia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Valencia?

Valencia by IMPRESSIONS is in Mahatma Phule Road, Thane, pincode 421202 (near Dombivli West, Ramnagar, Dombivli East), Maharashtra, and is registered on MahaRERA as P51700024879, per GharKundli's check of MahaRERA records. Its boundaries filed there include KARVE ROAD, MAHATMA PHULE ROAD. Its land is filed as C T S NO 2065 TO 2068, 1465 AND 1466. GharKundli lists all 226 MahaRERA projects in Vishnunagar (421202).

How many flats are in Valencia, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia has 34 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.

When was Valencia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Valencia was registered on MahaRERA on 9 March 2020. GharKundli did not find a title report on the land on file there.

Does Valencia have any legal issues or court cases?

No court cases are listed for Valencia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Valencia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is IMPRESSIONS, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 226 projects in Vishnunagar (421202) →

Other projects by IMPRESSIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.