by JAGDALE INFRASTRUCTURE PVT. LTD. · Jekegram, Thane

Possession date of JAGDALE AASTHA: 31 December 2026, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700026770, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about JAGDALE AASTHA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of JAGDALE AASTHA has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 29 December 2025

    Extended at the builder's request (MahaRERA application EXT51700025298)

    Reason the builder gave MahaRERA:
    “It is submitted that because of which development could not be started in spite of commencement certificate issued by Thane Municipal Corporation. It is submitted that since March 2020 till April 2022 there was period of lockdown in the Ind…” Read the full reason“It is submitted that because of which development could not be started in spite of commencement certificate issued by Thane Municipal Corporation. It is submitted that since March 2020 till April 2022 there was period of lockdown in the India. Because of which no labour for construction were available. And t is submitted that the said property is situated in the midst of slum area in Lokmanya Nagar of Thane City. It is also made aware that in last 5-10 years slum development has increased at a very large scale in Lokmanya Nagar. And because of which roads have become narrow. The Lokmanya Na…”
  3. 30 June 2026

    Extended at the builder's request (MahaRERA application EA11112518307)

    Reason the builder gave MahaRERA:
    “We, [JAGDALE INFRASTRUCTURE PVT. LTD), are the promoters of the real estate project known as "Jagdale Aastha" bearing MahaRERA Registration No. P51700026770. We would like to respectfully bring to your attention that the project has encount…” Read the full reason“We, [JAGDALE INFRASTRUCTURE PVT. LTD), are the promoters of the real estate project known as "Jagdale Aastha" bearing MahaRERA Registration No. P51700026770. We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be re…”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA20062621452)

    Reason the builder gave MahaRERA:
    “1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safet…” Read the full reason“1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from BMC, and other government authorities which led to a delay in the commencement of construction. which impacted construction timelines despite our continuous follow-up. 3. Unforeseen Soil Conditions During the excavat…”

Source: JAGDALE AASTHA’s extension records on MahaRERA (P51700026770), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JAGDALE AASTHA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700026770
Status
Registered and active
Builder
JAGDALE INFRASTRUCTURE PVT. LTD.
Location
Jekegram, Thane · 400606
Project type
Residential / Group Housing
Registered on
22 Oct 2020
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
60
Sold or booked
7%
Towers
1
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of JAGDALE AASTHA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AASTHA100%75%10%0%

Commencement certificate (CC), as filed on MahaRERA

  • AASTHA: covers HABITABLE FLOORS

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JAGDALE AASTHA every month.

JAGDALE AASTHA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of JAGDALE AASTHA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JAGDALE AASTHA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about JAGDALE AASTHA

What is the possession date of JAGDALE AASTHA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JAGDALE AASTHA in Jekegram, Thane is 31 December 2026 — 24 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for JAGDALE AASTHA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JAGDALE AASTHA's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of JAGDALE AASTHA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2025, giving the reason "It is submitted that because of which development could not be started in spite of commencement certificate issued by Thane Municipal Corporation. It is submitted that since March 2020 till April 2022 there was period of lockdown in the India. Because of which no labour for construction were available. And t is submitted that the said property is situated in the midst of slum area in Lokmanya Nagar of Thane City. It is also made aware that in last 5-10 years slum development has increased at a very large scale in Lokmanya Nagar. And because of which roads have become narrow. The Lokmanya Na…"; to 30 June 2026, giving the reason "We, [JAGDALE INFRASTRUCTURE PVT. LTD), are the promoters of the real estate project known as "Jagdale Aastha" bearing MahaRERA Registration No. P51700026770. We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be re…"; to 31 December 2026, giving the reason "1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from BMC, and other government authorities which led to a delay in the commencement of construction. which impacted construction timelines despite our continuous follow-up. 3. Unforeseen Soil Conditions During the excavat…".

What is the RERA number of JAGDALE AASTHA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JAGDALE AASTHA in Jekegram, Thane is P51700026770.

Is JAGDALE AASTHA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA is registered as P51700026770 and its status is "Registered and active".

What is the construction status of JAGDALE AASTHA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AASTHA is 75% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.

Does JAGDALE AASTHA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is JAGDALE AASTHA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA is registered on MahaRERA as P51700026770, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if JAGDALE AASTHA's possession date changes?

The latest dates are on JAGDALE AASTHA's MahaRERA page (P51700026770). GharKundli's Kundli Watch sends a free WhatsApp update on JAGDALE AASTHA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does JAGDALE AASTHA have?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA has one building filed: AASTHA with 9 floors and 60 units.

How much parking does JAGDALE AASTHA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 covered car parking spaces for JAGDALE AASTHA.

How big is the land of JAGDALE AASTHA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA stands on 906 sq m of land (about 0.2 acres), with 1,930 sq m of sanctioned built-up area.

Where can I read reviews of JAGDALE AASTHA?

Google Maps has reviews of JAGDALE AASTHA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is JAGDALE AASTHA?

JAGDALE AASTHA by JAGDALE INFRASTRUCTURE PVT. LTD. is in Jekegram, Thane (pincode 400606), Maharashtra, and is registered on MahaRERA as P51700026770, per GharKundli's check of MahaRERA records.

How many homes are in JAGDALE AASTHA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA has 60 homes in 1 tower registered on MahaRERA, and 7% of them are sold or booked.

When was JAGDALE AASTHA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAGDALE AASTHA was registered on MahaRERA on 22 October 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on JAGDALE AASTHA?

2 court cases are listed for JAGDALE AASTHA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of JAGDALE AASTHA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAGDALE INFRASTRUCTURE PVT. LTD., which has 4 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in pincode 400606

All 83 projects in Jekegram (400606) →

Other projects by JAGDALE INFRASTRUCTURE PVT. LTD.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.