Possession date of Royale Grand Central: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700034467, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Royale Grand Central?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Royale Grand Central has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Royale Grand Central’s extension records on MahaRERA (P51700034467), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Royale Grand Central

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints and 1 court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700034467
Status
Registered and active
Builder
M/s. Sai Shiva Infra Developers
Location
Near Sai Baba Mandir, Thane · 400606
Project type
Others
Registered on
11 Apr 2022
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
264
Sold or booked
60%
Towers
1
Complaints on MahaRERA
3
Court cases listed
1
Title report on file
Not found

Construction progress of Royale Grand Central, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Royale2%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Royale: covers 39 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Royale Grand Central every month.

Royale Grand Central: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK310 – 506153
1 BHK310 – 498111
Shops80 – 41315
  • Buildings: Royale (41 floors, 279 units)
  • Car parking: 184 covered
  • Land: 1,871 sq m (about 0.5 acres) · sanctioned built-up 14,445 sq m

The builder’s record and reviews

Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 6 finished, all within the promised date; 21 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects.

Read Google reviews of Royale Grand Central →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Royale Grand Central: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Royale Grand Central

What is the possession date of Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Royale Grand Central in Near Sai Baba Mandir, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Royale Grand Central?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Royale Grand Central's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Royale Grand Central in Near Sai Baba Mandir, Thane is P51700034467.

Is Royale Grand Central registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central is registered as P51700034467 and its status is "Registered and active".

What is the construction status of Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Royale is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Royale Grand Central have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Royale Grand Central safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central is registered on MahaRERA as P51700034467, its completion date has not been moved by the builder and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Royale Grand Central's possession date changes?

The latest dates are on Royale Grand Central's MahaRERA page (P51700034467). GharKundli's Kundli Watch sends a free WhatsApp update on Royale Grand Central every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Royale Grand Central have?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central has one building filed: Royale with 41 floors and 279 units.

What are the flat sizes (carpet area) in Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Royale Grand Central: 2 BHK: 310 to 506 sq ft carpet (153 homes); 1 BHK: 310 to 498 sq ft carpet (111 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Royale Grand Central have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 184 covered car parking spaces for Royale Grand Central.

How big is the land of Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central stands on 1,871 sq m of land (about 0.5 acres), with 14,445 sq m of sanctioned built-up area.

What is the track record of Royale Grand Central's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Puranik Builders (a group of 8 linked companies) has 44 projects on MahaRERA since 2017, this one included. Of the 29 GharKundli has checked: 6 finished, all within the promised date; 21 still being built, none past the promised date yet; 2 lapsed. 217 complaints on MahaRERA across 21 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Royale Grand Central?

Google Maps has reviews of Royale Grand Central written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Royale Grand Central?

Royale Grand Central by M/s. Sai Shiva Infra Developers (Puranik) is in Near Sai Baba Mandir, Thane (pincode 400606), near Jekegram, Balkum, Maharashtra, and is registered on MahaRERA as P51700034467, per GharKundli's check of MahaRERA records.

How many homes are in Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central has 264 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.

When was Royale Grand Central registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Royale Grand Central was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Royale Grand Central?

1 court case is listed for Royale Grand Central on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Royale Grand Central?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. Sai Shiva Infra Developers, the company Puranik files this project under.

All projects with possession due in 2030 in Thane →

Other projects in Thane

All 83 projects in Jekegram (400606) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.