What’s in the report? →Possession date of Jagdale Giriraj (MahaRERA P51800045510): 30 September 2026, moved from 1 September 2025 (12 months later), and it has already passed. It has 29 homes (1 Room Kitchen, 1 BHK and 2 BHK, 161–803 sq ft carpet), 55% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800045510. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800045510, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about Jagdale Giriraj?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Jagdale Giriraj has moved
1 September 2025
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EA25072502202)
Reason the builder gave MahaRERA:
“I would like to inform you that construction work on site is nearing completion, the completion of the project would be delayed by a year, due to constraint of movement space, as it adversely affects and hampers movement of materials and ma…” Read the full reason
“I would like to inform you that construction work on site is nearing completion, the completion of the project would be delayed by a year, due to constraint of movement space, as it adversely affects and hampers movement of materials and manpower. In spite of many adverse conditions 90% of construction work on site is completed in stipulated time. Attached herewith is Status Table of Items of work which shows that further extension of maximum 1 year would be required. You are requested to follow applicable MAHARERA guidelines for extension approval, and comply with the same to ensure timely…”30 September 2026
Extended at the builder's request (MahaRERA application EA14032620228)
Reason the builder gave MahaRERA:
“I would like to inform you that construction work on site is nearing completion, the completion of the project would be delayed by a year, due to constraint of movement space, as it adversely affects and hampers movement of materials and ma…” Read the full reason
“I would like to inform you that construction work on site is nearing completion, the completion of the project would be delayed by a year, due to constraint of movement space, as it adversely affects and hampers movement of materials and manpower. In spite of many adverse conditions 90% of construction work on site is completed in stipulated time. Attached herewith is Status Table of Items of work, which shows that further extension of maximum 1 year would be required. You are requested to follow applicable MAHARERA guidelines for extension approval, and comply with the same to ensure timel…”
Source: Jagdale Giriraj’s extension records on MahaRERA (P51800045510), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Jagdale Giriraj
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800045510
- Status
- Lapsed (registration period ended)
- Builder
- JAGDALE INFRASTRUCTURE PVT. LTD.
- Location
- Mulund East, Mumbai · 400081
- Project type
- Others
- Registered on
- 24 May 2022
- Completion date at registration
- September 2025
- Latest completion date
- September 2026
- Delay so far
- 12 months
- Homes
- 29
- Sold or booked
- 55%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Jagdale Giriraj, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GIRIRAJ | 100% | 100% | 100% | 60% |
Commencement certificate (CC), as filed on MahaRERA
- GIRIRAJ: covers PLINTH LEVEL
Latest CC order on MahaRERA: dated 19/05/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jagdale Giriraj every 1–2 months.
Jagdale Giriraj: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 511 – 577 | 21 |
| 1 Room Kitchen | 161 – 170 | 5 |
| Shops | 305 – 1,354 | 3 |
| 3 BHK | 669 – 803 | 2 |
| 1 BHK | 364 | 1 |
- Buildings: GIRIRAJ (17 floors, 32 units)
- Car parking: 32 covered
- Land: 701 sq m (about 0.2 acres) · sanctioned built-up 1,736 sq m
- Boundaries filed include: VB Phadke Marg
- Land, as filed: 545
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Jagdale Giriraj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Jagdale Giriraj: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Jagdale Giriraj
What is the possession date of Jagdale Giriraj?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jagdale Giriraj in Mulund East, Mumbai is 30 September 2026 — 12 months later than 1 September 2025, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Jagdale Giriraj?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Jagdale Giriraj's builder has filed on MahaRERA, the official one, is 30 September 2026, already 12 months later than the 1 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Jagdale Giriraj extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "I would like to inform you that construction work on site is nearing completion, the completion of the project would be delayed by a year, due to constraint of movement space, as it adversely affects and hampers movement of materials and manpower. In spite of many adverse conditions 90% of construction work on site is completed in stipulated time. Attached herewith is Status Table of Items of work which shows that further extension of maximum 1 year would be required. You are requested to follow applicable MAHARERA guidelines for extension approval, and comply with the same to ensure timely…"; to 30 September 2026, giving the reason "I would like to inform you that construction work on site is nearing completion, the completion of the project would be delayed by a year, due to constraint of movement space, as it adversely affects and hampers movement of materials and manpower. In spite of many adverse conditions 90% of construction work on site is completed in stipulated time. Attached herewith is Status Table of Items of work, which shows that further extension of maximum 1 year would be required. You are requested to follow applicable MAHARERA guidelines for extension approval, and comply with the same to ensure timel…".
What is the RERA number of Jagdale Giriraj?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jagdale Giriraj in Mulund East, Mumbai is P51800045510.
Is Jagdale Giriraj registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj is registered as P51800045510 and its status is "Lapsed (registration period ended)".
What is the current construction status of Jagdale Giriraj? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GIRIRAJ is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Jagdale Giriraj have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Jagdale Giriraj safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj is registered on MahaRERA as P51800045510, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Jagdale Giriraj?
Jagdale Giriraj isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Jagdale Giriraj are 161 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Jagdale Giriraj?
For a flat in Jagdale Giriraj (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Jagdale Giriraj received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Jagdale Giriraj?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Jagdale Giriraj a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Jagdale Giriraj uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Jagdale Giriraj was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Jagdale Giriraj's possession date changes?
The latest dates are on Jagdale Giriraj's MahaRERA page (P51800045510). GharKundli's Kundli Watch sends a free WhatsApp update on Jagdale Giriraj every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Jagdale Giriraj have?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj has one building filed: GIRIRAJ with 17 floors and 32 units.
What are the flat sizes (carpet area) in Jagdale Giriraj?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Jagdale Giriraj: 2 BHK: 511 to 577 sq ft carpet (21 homes); 1 Room Kitchen: 161 to 170 sq ft carpet (5 homes); 3 BHK: 669 to 803 sq ft carpet (2 homes); 1 BHK: 364 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Jagdale Giriraj have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for Jagdale Giriraj.
How big is the land of Jagdale Giriraj?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj stands on 701 sq m of land (about 0.2 acres), with 1,736 sq m of sanctioned built-up area.
What are the reviews of Jagdale Giriraj?
Google Maps has reviews of Jagdale Giriraj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Jagdale Giriraj?
Jagdale Giriraj by JAGDALE INFRASTRUCTURE PVT. LTD. is in Mulund East, Mumbai, pincode 400081 (near Mulund West, Tata Colony, Vile Parle East), Maharashtra, and is registered on MahaRERA as P51800045510, per GharKundli's check of MahaRERA records. Its boundaries filed there include VB Phadke Marg. Its land is filed as 545. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).
How many flats are in Jagdale Giriraj, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj has 29 homes in 1 tower registered on MahaRERA, and 55% of them are sold or booked.
When was Jagdale Giriraj registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jagdale Giriraj was registered on MahaRERA on 24 May 2022. GharKundli did not find a title report on the land on file there.
Does Jagdale Giriraj have any legal issues or court cases?
No court cases are listed for Jagdale Giriraj on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Jagdale Giriraj?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JAGDALE INFRASTRUCTURE PVT. LTD., which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Jagdale Giriraj
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Mulund East (400081)
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- Satre Elite
- Pearl
- Rbi Employees Shree Sahawas Co Op HSG Soc LTD
- New Usha Vihar Chsl
- Bimal Apartment CHSL
- Guru Ashish
- Ganesh Dham
Other projects by JAGDALE INFRASTRUCTURE PVT. LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.