GharKundli

GURU ASHISH

by SHIVCORP INFRA (OPC) PRIVATE LIMITED · Mulund east, MumbaiAlso near Mulund West, Vile Parle East, Bhandup west

Possession date of GURU ASHISH: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800053415, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GURU ASHISH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GURU ASHISH has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA04042620559)

    Reason the builder gave MahaRERA:
    “Construction works did not progress as expected and around 60% work of the project is completed so far and for the completion of the construction of the building, it will take around 9-10 months. Thereafter, the procedure for issue of Occup…” Read the full reason“Construction works did not progress as expected and around 60% work of the project is completed so far and for the completion of the construction of the building, it will take around 9-10 months. Thereafter, the procedure for issue of Occupancy Certificate by BMC will also take about 2-3 months.”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GURU ASHISH’s extension records on MahaRERA (P51800053415), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GURU ASHISH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800053415
Status
Registered and active
Builder
SHIVCORP INFRA (OPC) PRIVATE LIMITED
Location
Mulund east, Mumbai · 400081
Project type
Residential / Group Housing
Registered on
31 Oct 2023
Completion date at registration
March 2026
Latest completion date
July 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
29
Sold or booked
32%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GURU ASHISH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GURU ASHISH100%92%42%0%

Commencement certificate (CC), as filed on MahaRERA

  • GURU ASHISH: covers 12 floors

Latest CC order on MahaRERA: dated 29/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GURU ASHISH every month.

GURU ASHISH: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK1 – 71615
3 BHK8157
1 BHK19 – 6305
1 Room Kitchen6 – 3002
  • Buildings: GURU ASHISH (14 floors, 29 units)
  • Car parking: 33 covered
  • Land: 615 sq m (about 0.2 acres) · sanctioned built-up 606 sq m
  • Boundaries filed include: Neelam nagar building 3, Neelam nagar building 5
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GURU ASHISH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GURU ASHISH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GURU ASHISH

What is the possession date of GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GURU ASHISH in Mulund east, Mumbai is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GURU ASHISH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GURU ASHISH's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GURU ASHISH extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Construction works did not progress as expected and around 60% work of the project is completed so far and for the completion of the construction of the building, it will take around 9-10 months. Thereafter, the procedure for issue of Occupancy Certificate by BMC will also take about 2-3 months.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GURU ASHISH in Mulund east, Mumbai is P51800053415.

Is GURU ASHISH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH is registered as P51800053415 and its status is "Registered and active".

What is the construction status of GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GURU ASHISH is 92% done and internal work 42%. GharKundli's full report compares construction progress with the deadline.

Does GURU ASHISH have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GURU ASHISH safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH is registered on MahaRERA as P51800053415, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GURU ASHISH's possession date changes?

The latest dates are on GURU ASHISH's MahaRERA page (P51800053415). GharKundli's Kundli Watch sends a free WhatsApp update on GURU ASHISH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GURU ASHISH have?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH has one building filed: GURU ASHISH with 14 floors and 29 units.

What are the flat sizes (carpet area) in GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GURU ASHISH: 2 BHK: 1 to 716 sq ft carpet (15 homes); 3 BHK: 815 sq ft carpet (7 homes); 1 BHK: 19 to 630 sq ft carpet (5 homes); 1 Room Kitchen: 6 to 300 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does GURU ASHISH have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for GURU ASHISH.

How big is the land of GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH stands on 615 sq m of land (about 0.2 acres), with 606 sq m of sanctioned built-up area.

Where can I read reviews of GURU ASHISH?

Google Maps has reviews of GURU ASHISH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GURU ASHISH?

GURU ASHISH by SHIVCORP INFRA (OPC) PRIVATE LIMITED is in Mulund east, Mumbai (pincode 400081), near Mulund West, Vile Parle East, Bhandup west, Maharashtra, and is registered on MahaRERA as P51800053415, per GharKundli's check of MahaRERA records. Its boundaries filed there include Neelam nagar building 3, Neelam nagar building 5.

How many homes are in GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH has 29 homes in 1 tower registered on MahaRERA, and 32% of them are sold or booked.

When was GURU ASHISH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GURU ASHISH was registered on MahaRERA on 31 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on GURU ASHISH?

No court cases are listed for GURU ASHISH on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GURU ASHISH?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIVCORP INFRA (OPC) PRIVATE LIMITED.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400081

All 124 projects in Mulund East (400081) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.