RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
by SIDDHI SAI ENTERPRISES · Gavanpada, Mumbai
Possession date of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD: 30 April 2028, moved from 31 July 2019 (101 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800002621, and currently active. Its completion date has moved from July 2019 to April 2028: 101 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
How the possession date of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD has moved
31 July 2019
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51800024240)
Reason the builder gave MahaRERA: “as per attachment”
31 December 2027
Extended at the builder's request (MahaRERA application EA31032620509)
Reason the builder gave MahaRERA:
“The redevelopment of the RBI Employees Shree-Sahawas CHSL, originally a 20-flat building from 1979, is currently stalled due to regulatory changes following a Supreme Court judgment regarding road width requirements. Although Siddhi Sai Ent…” Read the full reason
“The redevelopment of the RBI Employees Shree-Sahawas CHSL, originally a 20-flat building from 1979, is currently stalled due to regulatory changes following a Supreme Court judgment regarding road width requirements. Although Siddhi Sai Enterprises had successfully completed RCC work up to the 7th slab and brickwork up to the 5th floor based on original 2011 approvals, the project hit a bottleneck when a 6.00-meter wide access road became a mandatory condition for building heights exceeding 24.00 meters. To resolve this, the developer has coordinated with the MCGM under the DCPR 2034 to han…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD’s extension records on MahaRERA (P51800002621), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800002621
- Status
- Registered and active
- Builder
- SIDDHI SAI ENTERPRISES
- Location
- Gavanpada, Mumbai · 400081
- Project type
- Others
- Registered on
- 2 Aug 2017
- Completion date at registration
- July 2019
- Latest completion date
- April 2028
- Delay so far
- 101 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 36
- Sold or booked
- 50%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE SAHAWAS | 100% | 70% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHREE SAHAWAS: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD every month.
RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 496 – 724 | 22 |
| 3 BHK | 614 – 746 | 10 |
| 1 BHK | 415 – 657 | 4 |
- Buildings: SHREE SAHAWAS (10 floors, 36 units)
- Land: 1,027 sq m (about 0.3 acres) · sanctioned built-up 1,807 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
What is the possession date of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD in Gavanpada, Mumbai is 30 April 2028 — 101 months later than 31 July 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD's builder has filed on MahaRERA, the official one, is 30 April 2028, already 101 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "as per attachment"; to 31 December 2027, giving the reason "The redevelopment of the RBI Employees Shree-Sahawas CHSL, originally a 20-flat building from 1979, is currently stalled due to regulatory changes following a Supreme Court judgment regarding road width requirements. Although Siddhi Sai Enterprises had successfully completed RCC work up to the 7th slab and brickwork up to the 5th floor based on original 2011 approvals, the project hit a bottleneck when a 6.00-meter wide access road became a mandatory condition for building heights exceeding 24.00 meters. To resolve this, the developer has coordinated with the MCGM under the DCPR 2034 to han…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD in Gavanpada, Mumbai is P51800002621.
Is RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD is registered as P51800002621 and its status is "Registered and active".
What is the construction status of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE SAHAWAS is 70% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD is registered on MahaRERA as P51800002621, its completion date has moved 101 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD's possession date changes?
The latest dates are on RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD's MahaRERA page (P51800002621). GharKundli's Kundli Watch sends a free WhatsApp update on RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD has one building filed: SHREE SAHAWAS with 10 floors and 36 units.
What are the flat sizes (carpet area) in RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD: 2 BHK: 496 to 724 sq ft carpet (22 homes); 3 BHK: 614 to 746 sq ft carpet (10 homes); 1 BHK: 415 to 657 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD stands on 1,027 sq m of land (about 0.3 acres), with 1,807 sq m of sanctioned built-up area.
Where can I read reviews of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
Google Maps has reviews of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD by SIDDHI SAI ENTERPRISES is in Gavanpada, Mumbai (pincode 400081), Maharashtra, and is registered on MahaRERA as P51800002621, per GharKundli's check of MahaRERA records.
How many homes are in RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD has 36 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.
When was RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD was registered on MahaRERA on 2 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
No court cases are listed for RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHI SAI ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Kurla
- Construction of 406 TR TS 442 EWS 258 MIG TS at Gavanpada Mulund east Mumbai
- Saptashringi
- SUDHANSHU HEIGHTS
- Jai Arihant
- Kanakdhara
- Privilon
- Heritage Lakeside
- Kalyan Kutir Co-operative Housing Society Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.