GOVIND PRAKASH SRA CHS LTD
by OMSAI DEVELOPERS · Mulund East, MumbaiAlso near Mulund West, Vile Parle East, Bhandup west
Possession date of GOVIND PRAKASH SRA CHS LTD: 31 December 2026, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800032427, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GOVIND PRAKASH SRA CHS LTD?
How the possession date of GOVIND PRAKASH SRA CHS LTD has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800025546)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Ce…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 90% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and takin…”31 December 2026
Extended at the builder's request (MahaRERA application EA22052621056)
Reason the builder gave MahaRERA:
“The project requires an extension of the registration period due to delays in obtaining statutory approvals, specifically the Fire No Objection Certificate (Fire NOC) and the Full Occupation Certificate (OC) from the concerned authorities.…” Read the full reason
“The project requires an extension of the registration period due to delays in obtaining statutory approvals, specifically the Fire No Objection Certificate (Fire NOC) and the Full Occupation Certificate (OC) from the concerned authorities. Despite completion of major construction activities in line with sanctioned plans, the issuance of the Fire NOC is pending due to procedural timelines and compliance verifications by the Fire Department. Consequently, the application for the Full OC, which is dependent on the Fire NOC, is also under process with the local municipal authority. The delay is…”
Source: GOVIND PRAKASH SRA CHS LTD’s extension records on MahaRERA (P51800032427), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GOVIND PRAKASH SRA CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Govind Prakash SRA CHS LTDP51800006380 · possession 31 Dec 2018
- MahaRERA registration
- P51800032427
- Status
- Registered and active
- Builder
- OMSAI DEVELOPERS
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 4 Jan 2022
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 27
- Sold or booked
- 78%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of GOVIND PRAKASH SRA CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VINAYAK BUILDING NO 2 OF GOVIND PRAKASH SRA CHS LTD | 100% | 100% | 100% | 100% |
| BUILDING NO 3 SIDDHI APARTMENT | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- VINAYAK BUILDING NO 2 OF GOVIND PRAKASH SRA CHS LTD: covers 24(G+ 23 Floor)
- BUILDING NO 3 SIDDHI APARTMENT: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOVIND PRAKASH SRA CHS LTD every month.
GOVIND PRAKASH SRA CHS LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Unspecified | — | 198 |
| 1 BHK | 385 – 390 | 25 |
| 1 Room Kitchen | 165 | 2 |
- Buildings: VINAYAK BUILDING NO 2 OF GOVIND PRAKASH SRA CHS LTD (25 floors, 27 units) · BUILDING NO 3 SIDDHI APARTMENT (9 floors)
- Land: 880 sq m (about 0.2 acres) · sanctioned built-up 2,487 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Om Sai Developers has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.
Read Google reviews of GOVIND PRAKASH SRA CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GOVIND PRAKASH SRA CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GOVIND PRAKASH SRA CHS LTD
What is the possession date of GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOVIND PRAKASH SRA CHS LTD in Mulund East, Mumbai is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for GOVIND PRAKASH SRA CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GOVIND PRAKASH SRA CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GOVIND PRAKASH SRA CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, delays in obtaining the Occupancy Certificate (OC), and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 90% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and takin…"; to 31 December 2026, giving the reason "The project requires an extension of the registration period due to delays in obtaining statutory approvals, specifically the Fire No Objection Certificate (Fire NOC) and the Full Occupation Certificate (OC) from the concerned authorities. Despite completion of major construction activities in line with sanctioned plans, the issuance of the Fire NOC is pending due to procedural timelines and compliance verifications by the Fire Department. Consequently, the application for the Full OC, which is dependent on the Fire NOC, is also under process with the local municipal authority. The delay is…".
What is the RERA number of GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GOVIND PRAKASH SRA CHS LTD in Mulund East, Mumbai is P51800032427.
Is GOVIND PRAKASH SRA CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD is registered as P51800032427 and its status is "Registered and active".
What is the construction status of GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does GOVIND PRAKASH SRA CHS LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is GOVIND PRAKASH SRA CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD is registered on MahaRERA as P51800032427, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does GOVIND PRAKASH SRA CHS LTD have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Govind Prakash SRA CHS LTD (P51800006380, possession 31 Dec 2018). Check that your agreement names the registration of your own wing.
How can I get updates if GOVIND PRAKASH SRA CHS LTD's possession date changes?
The latest dates are on GOVIND PRAKASH SRA CHS LTD's MahaRERA page (P51800032427). GharKundli's Kundli Watch sends a free WhatsApp update on GOVIND PRAKASH SRA CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GOVIND PRAKASH SRA CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD has 2 buildings filed: VINAYAK BUILDING NO 2 OF GOVIND PRAKASH SRA CHS LTD with 25 floors and 27 units; BUILDING NO 3 SIDDHI APARTMENT with 9 floors.
What are the flat sizes (carpet area) in GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GOVIND PRAKASH SRA CHS LTD: 1 BHK: 385 to 390 sq ft carpet (25 homes); 1 Room Kitchen: 165 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD stands on 880 sq m of land (about 0.2 acres), with 2,487 sq m of sanctioned built-up area.
What is the track record of GOVIND PRAKASH SRA CHS LTD's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sai Developers has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GOVIND PRAKASH SRA CHS LTD?
Google Maps has reviews of GOVIND PRAKASH SRA CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GOVIND PRAKASH SRA CHS LTD?
GOVIND PRAKASH SRA CHS LTD by OMSAI DEVELOPERS is in Mulund East, Mumbai (pincode 400081), near Mulund West, Vile Parle East, Bhandup west, Maharashtra, and is registered on MahaRERA as P51800032427, per GharKundli's check of MahaRERA records.
How many homes are in GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD has 27 homes in 2 towers registered on MahaRERA, and 78% of them are sold or booked.
When was GOVIND PRAKASH SRA CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GOVIND PRAKASH SRA CHS LTD was registered on MahaRERA on 4 January 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on GOVIND PRAKASH SRA CHS LTD?
No court cases are listed for GOVIND PRAKASH SRA CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of GOVIND PRAKASH SRA CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OMSAI DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GOVIND PRAKASH SRA CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400081
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
- BIMAL APARTMENT CHSL
- GURU ASHISH
- Ganesh Dham
- SATRE ELITE
- PEARL
- New Usha Vihar Chsl
Other projects by OMSAI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.