KOKAN PARK

by MAHESH RAJARAM MESTRY · Rampur S.O (Ratnagiri), Ratnagiri

Possession date of KOKAN PARK: 31 December 2023, moved from 30 June 2021 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52800010404. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about KOKAN PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KOKAN PARK has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52800010634)

    Reason the builder gave MahaRERA: “Due to lockdown Because of covid -19 pandemic construction work was stop held in ratnagiri Maharashtra from march 20 to till date .”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52800013640)

    Reason the builder gave MahaRERA:
    “1. In 2020 due to the Pandemic situation of COVID-19 and locked down imposed by the government we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation…” Read the full reason“1. In 2020 due to the Pandemic situation of COVID-19 and locked down imposed by the government we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation service. 3. Due to the issuance of the UNIFIED DEVELOPMENT CONTROL AND PROMOTION REGULATIONS, 2021, there were changes in the FSI of the project, hence we needed to apply for the revised Plan approvals and Amended Commencement Certificate, which is still in the process with the Planning Department. 4. Due to delays in the Process of the Planning departme…”

Source: KOKAN PARK’s extension records on MahaRERA (P52800010404), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KOKAN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800010404
Status
Lapsed (registration period ended)
Builder
MAHESH RAJARAM MESTRY
Location
Rampur S.O (Ratnagiri), Ratnagiri · 415701
Project type
Others
Registered on
24 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2023
Delay so far
30 months
Homes
72
Towers
8
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of KOKAN PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%100%100%
B WING100%100%100%100%
OTHER0%0%0%0%
OTHER0%0%0%0%
G WING0%100%75%50%
H WING0%100%75%50%
OTHER0%0%0%0%
OTHER0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KOKAN PARK every month.

KOKAN PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (6 floors) · B WING (6 floors) · G WING (6 floors) · H WING (6 floors)
  • Land: 5,800 sq m (about 1.4 acres) · sanctioned built-up 6,081 sq m · recreational space 580 sq m

The builder’s record and reviews

Mahesh Rajaram Mestry has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of KOKAN PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KOKAN PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KOKAN PARK

What is the possession date of KOKAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KOKAN PARK in Rampur S.O (Ratnagiri), Ratnagiri is 31 December 2023 — 30 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KOKAN PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KOKAN PARK's builder has filed on MahaRERA, the official one, is 31 December 2023, already 30 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KOKAN PARK extended?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "Due to lockdown Because of covid -19 pandemic construction work was stop held in ratnagiri Maharashtra from march 20 to till date ."; to 31 December 2023, giving the reason "1. In 2020 due to the Pandemic situation of COVID-19 and locked down imposed by the government we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation service. 3. Due to the issuance of the UNIFIED DEVELOPMENT CONTROL AND PROMOTION REGULATIONS, 2021, there were changes in the FSI of the project, hence we needed to apply for the revised Plan approvals and Amended Commencement Certificate, which is still in the process with the Planning Department. 4. Due to delays in the Process of the Planning departme…".

What is the RERA number of KOKAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KOKAN PARK in Rampur S.O (Ratnagiri), Ratnagiri is P52800010404.

Is KOKAN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK is registered as P52800010404 and its status is "Lapsed (registration period ended)".

What is the construction status of KOKAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does KOKAN PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KOKAN PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK is registered on MahaRERA as P52800010404, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KOKAN PARK's possession date changes?

The latest dates are on KOKAN PARK's MahaRERA page (P52800010404). GharKundli's Kundli Watch sends a free WhatsApp update on KOKAN PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KOKAN PARK have?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK has 4 buildings filed: A WING with 6 floors; B WING with 6 floors; G WING with 6 floors; H WING with 6 floors.

How big is the land of KOKAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK stands on 5,800 sq m of land (about 1.4 acres), with 6,081 sq m of sanctioned built-up area and 580 sq m of recreational open space.

What is the track record of KOKAN PARK's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mahesh Rajaram Mestry has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KOKAN PARK?

Google Maps has reviews of KOKAN PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KOKAN PARK?

KOKAN PARK by MAHESH RAJARAM MESTRY is in Rampur S.O (Ratnagiri), Ratnagiri (pincode 415701), Maharashtra, and is registered on MahaRERA as P52800010404, per GharKundli's check of MahaRERA records.

How many homes are in KOKAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK has 72 homes in 8 towers registered on MahaRERA.

When was KOKAN PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KOKAN PARK was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KOKAN PARK?

No court cases are listed for KOKAN PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KOKAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHESH RAJARAM MESTRY, which has 2 other projects registered on MahaRERA.