ATHANG RESIDENCY
by Subodh Dattatray Salvi · Ganpatipule, Ratnagiri
Possession date of ATHANG RESIDENCY: 30 June 2025, moved from 30 June 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52800028870. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2025) has passed.
What do you want to know about ATHANG RESIDENCY?
How the possession date of ATHANG RESIDENCY has moved
30 June 2023
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT52800016985)
Reason the builder gave MahaRERA: “Due to labor issues and some financial constraints, we are not able to finish within the given deadline.”
Source: ATHANG RESIDENCY’s extension records on MahaRERA (P52800028870), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ATHANG RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800028870
- Status
- Lapsed (registration period ended)
- Builder
- Subodh Dattatray Salvi
- Location
- Ganpatipule, Ratnagiri · 415615
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2021
- Completion date at registration
- June 2023
- Latest completion date
- June 2025
- Delay so far
- 24 months
- Homes
- 18
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ATHANG RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ATHANG RESIDENCY | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ATHANG RESIDENCY every month.
ATHANG RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: ATHANG RESIDENCY (3 floors)
- Land: 755 sq m (about 0.2 acres) · sanctioned built-up 833 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ATHANG RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ATHANG RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ATHANG RESIDENCY
What is the possession date of ATHANG RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ATHANG RESIDENCY in Ganpatipule, Ratnagiri is 30 June 2025 — 24 months later than 30 June 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for ATHANG RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ATHANG RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2025, already 24 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ATHANG RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 June 2025, giving the reason "Due to labor issues and some financial constraints, we are not able to finish within the given deadline.".
What is the RERA number of ATHANG RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ATHANG RESIDENCY in Ganpatipule, Ratnagiri is P52800028870.
Is ATHANG RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY is registered as P52800028870 and its status is "Lapsed (registration period ended)".
What is the construction status of ATHANG RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ATHANG RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ATHANG RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ATHANG RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY is registered on MahaRERA as P52800028870, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ATHANG RESIDENCY's possession date changes?
The latest dates are on ATHANG RESIDENCY's MahaRERA page (P52800028870). GharKundli's Kundli Watch sends a free WhatsApp update on ATHANG RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ATHANG RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY has one building filed: ATHANG RESIDENCY with 3 floors.
How big is the land of ATHANG RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY stands on 755 sq m of land (about 0.2 acres), with 833 sq m of sanctioned built-up area.
Where can I read reviews of ATHANG RESIDENCY?
Google Maps has reviews of ATHANG RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ATHANG RESIDENCY?
ATHANG RESIDENCY by Subodh Dattatray Salvi is in Ganpatipule, Ratnagiri (pincode 415615), Maharashtra, and is registered on MahaRERA as P52800028870, per GharKundli's check of MahaRERA records.
How many homes are in ATHANG RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY has 18 homes in 1 tower registered on MahaRERA.
When was ATHANG RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATHANG RESIDENCY was registered on MahaRERA on 5 April 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on ATHANG RESIDENCY?
No court cases are listed for ATHANG RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ATHANG RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Subodh Dattatray Salvi.
Check it yourself on MahaRERA
- How to check the possession date of ATHANG RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ratnagiri
- EKDANT HEIGHTS
- Shreejee Ocean View
- LAXMI KEHSAV NAGAR PHASE II
- ASHTVINAYAK GAURAV SANKUL
- RAM VIJAY
- SHUBHANKAR PRARAMBH
- SAI SANGAM RESIDENCY
- KOHINOOR CHAITANYA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.