Possession date of BASERA HEIGHTS: 30 April 2027, moved from 30 March 2024 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700025078, and currently active. Its completion date has moved from March 2024 to April 2027: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 10 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about BASERA HEIGHTS?
How the possession date of BASERA HEIGHTS has moved
30 March 2024
Completion date given when the project was registered
30 March 2025
Extended at the builder's request (MahaRERA application EXT51700017375)
Reason the builder gave MahaRERA: “EXTENSION FOR ACQUIRING OCCUPANCY CERTIFICATE”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700028193)
Reason the builder gave MahaRERA: “project not completed”
31 December 2026
Extended at the builder's request (MahaRERA application EA25032620373)
Reason the builder gave MahaRERA:
“The delay in completion of the project is attributable to multiple interrelated factors affecting various stages of construction as per the PERT chart . Initially, the structural and RCC works, including slab casting and superstructure deve…” Read the full reason
“The delay in completion of the project is attributable to multiple interrelated factors affecting various stages of construction as per the PERT chart . Initially, the structural and RCC works, including slab casting and superstructure development, were delayed due to intermittent labour shortages, disruption in supply of key construction materials such as cement and steel, and adverse weather conditions during critical execution periods. These delays had a cascading effect on subsequent activities such as internal wall construction and plastering, which are dependent on structural completi…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: BASERA HEIGHTS’s extension records on MahaRERA (P51700025078), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BASERA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 10 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700025078
- Status
- Registered and active
- Builder
- KAMRUDDIN HASMULLAH SIDDIQUE
- Location
- Bhayander East, Thane · 401105
- Project type
- Others
- Registered on
- 18 Mar 2020
- Completion date at registration
- March 2024
- Latest completion date
- April 2027
- Delay so far
- 33 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 68
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 10
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of BASERA HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BASERA HEIGHTS | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- BASERA HEIGHTS: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BASERA HEIGHTS every month.
BASERA HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: BASERA HEIGHTS (17 floors, 85 units)
- Car parking: 1 covered, 96 open
- Land: 842 sq m (about 0.2 acres) · sanctioned built-up 4,067 sq m · recreational space 15 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of BASERA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BASERA HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BASERA HEIGHTS
What is the possession date of BASERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for BASERA HEIGHTS in Bhayander East, Thane is 30 April 2027 — 33 months later than 30 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for BASERA HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BASERA HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 33 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BASERA HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2025, giving the reason "EXTENSION FOR ACQUIRING OCCUPANCY CERTIFICATE"; to 31 December 2025, giving the reason "project not completed"; to 31 December 2026, giving the reason "The delay in completion of the project is attributable to multiple interrelated factors affecting various stages of construction as per the PERT chart . Initially, the structural and RCC works, including slab casting and superstructure development, were delayed due to intermittent labour shortages, disruption in supply of key construction materials such as cement and steel, and adverse weather conditions during critical execution periods. These delays had a cascading effect on subsequent activities such as internal wall construction and plastering, which are dependent on structural completi…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of BASERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of BASERA HEIGHTS in Bhayander East, Thane is P51700025078.
Is BASERA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS is registered as P51700025078 and its status is "Registered and active".
What is the construction status of BASERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BASERA HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does BASERA HEIGHTS have complaints on MahaRERA?
10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BASERA HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS is registered on MahaRERA as P51700025078, its completion date has moved 33 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if BASERA HEIGHTS's possession date changes?
The latest dates are on BASERA HEIGHTS's MahaRERA page (P51700025078). GharKundli's Kundli Watch sends a free WhatsApp update on BASERA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BASERA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS has one building filed: BASERA HEIGHTS with 17 floors and 85 units.
How much parking does BASERA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 96 open car parking spaces for BASERA HEIGHTS.
How big is the land of BASERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS stands on 842 sq m of land (about 0.2 acres), with 4,067 sq m of sanctioned built-up area and 15 sq m of recreational open space.
Where can I read reviews of BASERA HEIGHTS?
Google Maps has reviews of BASERA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BASERA HEIGHTS?
BASERA HEIGHTS by KAMRUDDIN HASMULLAH SIDDIQUE is in Bhayander East, Thane (pincode 401105), Maharashtra, and is registered on MahaRERA as P51700025078, per GharKundli's check of MahaRERA records.
How many homes are in BASERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS has 68 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was BASERA HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), BASERA HEIGHTS was registered on MahaRERA on 18 March 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on BASERA HEIGHTS?
No court cases are listed for BASERA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of BASERA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KAMRUDDIN HASMULLAH SIDDIQUE.
Check it yourself on MahaRERA
- How to check the possession date of BASERA HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →