Olive - Phase III - Pranjee Garden City
by Pranjee Properties Pvt. Ltd · Katrap, Thane 421503
What’s in the report? →Possession date of Olive - Phase III - Pranjee Garden City (MahaRERA P51700025487): 30 October 2026, moved from 30 June 2024 (24 months later), and it has already passed. It has 172 homes, 67% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700025487, and currently active. Its completion date has moved from June 2024 to October 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700025487, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Olive - Phase III - Pranjee Garden City?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Olive - Phase III - Pranjee Garden City has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT51700024058)
Reason the builder gave MahaRERA:
“As it very well aware about bad situation/phase of Real Estate / Construction Industry, due to Covid 19 Pandemic and its after effects , which there has been drastically slow down in speed of construction throughout the industry, we are als…” Read the full reason
“As it very well aware about bad situation/phase of Real Estate / Construction Industry, due to Covid 19 Pandemic and its after effects , which there has been drastically slow down in speed of construction throughout the industry, we are also facing same issues at our project too. We hereby request to please provide us extension of 12 months till 30th June, 25 for completion of all pending work and handover peaceful possession to customer in our project.”31 December 2025
Extended at the builder's request (MahaRERA application EA15072502070)
Reason the builder gave MahaRERA:
“We respectfully request an extension for the OLIVE – PHASE III – PRANJEE GARDEN CITY project. While construction is substantially complete and interior finishing works are currently in progress, we have encountered certain unanticipated sit…” Read the full reason
“We respectfully request an extension for the OLIVE – PHASE III – PRANJEE GARDEN CITY project. While construction is substantially complete and interior finishing works are currently in progress, we have encountered certain unanticipated site challenges and delays in obtaining statutory approvals required for securing the Occupancy Certificate (OC). These unforeseen factors have affected the final stages of the project timeline. Although we are actively addressing these issues and are optimistic about obtaining the OC within the next six months, we are seeking this extension as a precautiona…”30 June 2026
Extended at the builder's request (MahaRERA application EA12122518659)
Reason the builder gave MahaRERA:
“The Promoter requests an extension for the project, as construction is nearly complete but certain site challenges and delays in obtaining approvals have caused unforeseen delays. The required compliances for securing the Occupancy Certific…” Read the full reason
“The Promoter requests an extension for the project, as construction is nearly complete but certain site challenges and delays in obtaining approvals have caused unforeseen delays. The required compliances for securing the Occupancy Certificate (OC) and related NOCs are currently being completed, and the OC application is expected to be submitted around December. Additionally, during the previous extension cycle, a delay in processing caused the project to temporarily lapse, resulting in the halt of new-flat registrations on the portal and disrupting the project’s cash flow. Despite this set…”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Olive - Phase III - Pranjee Garden City’s extension records on MahaRERA (P51700025487), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Olive - Phase III - Pranjee Garden City
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700025487
- Status
- Registered and active
- Builder
- Pranjee Properties Pvt. Ltd
- Location
- Katrap, Thane · 421503
- Project type
- Others
- Registered on
- 8 Jun 2020
- Completion date at registration
- June 2024
- Latest completion date
- October 2026
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 172
- Sold or booked
- 67%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Olive - Phase III - Pranjee Garden City, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Olive | 100% | 100% | 96% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Olive: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Olive - Phase III - Pranjee Garden City every 1–2 months.
Olive - Phase III - Pranjee Garden City: buildings, flats and land, as filed on MahaRERA
- Buildings: Olive (13 floors, 172 units)
- Car parking: 98 covered
- Land: 9,801 sq m (about 2.4 acres) · sanctioned built-up 7,738 sq m · recreational space 4,300 sq m
- Land, as filed: Plot No. 5 Part
- Map: Get directions
The builder’s record and reviews
Pranjee Properties has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 11 months); 2 still being built, 2 past the promised date (typically 57 months late). 8 complaints on MahaRERA across 3 projects.
Read Google reviews of Olive - Phase III - Pranjee Garden City →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Olive - Phase III - Pranjee Garden City: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Olive - Phase III - Pranjee Garden City
What is the possession date of Olive - Phase III - Pranjee Garden City?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Olive - Phase III - Pranjee Garden City in Katrap, Thane is 30 October 2026 — 24 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Olive - Phase III - Pranjee Garden City?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Olive - Phase III - Pranjee Garden City's builder has filed on MahaRERA, the official one, is 30 October 2026, already 24 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Olive - Phase III - Pranjee Garden City extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2025, giving the reason "As it very well aware about bad situation/phase of Real Estate / Construction Industry, due to Covid 19 Pandemic and its after effects , which there has been drastically slow down in speed of construction throughout the industry, we are also facing same issues at our project too. We hereby request to please provide us extension of 12 months till 30th June, 25 for completion of all pending work and handover peaceful possession to customer in our project."; to 31 December 2025, giving the reason "We respectfully request an extension for the OLIVE – PHASE III – PRANJEE GARDEN CITY project. While construction is substantially complete and interior finishing works are currently in progress, we have encountered certain unanticipated site challenges and delays in obtaining statutory approvals required for securing the Occupancy Certificate (OC). These unforeseen factors have affected the final stages of the project timeline. Although we are actively addressing these issues and are optimistic about obtaining the OC within the next six months, we are seeking this extension as a precautiona…"; to 30 June 2026, giving the reason "The Promoter requests an extension for the project, as construction is nearly complete but certain site challenges and delays in obtaining approvals have caused unforeseen delays. The required compliances for securing the Occupancy Certificate (OC) and related NOCs are currently being completed, and the OC application is expected to be submitted around December. Additionally, during the previous extension cycle, a delay in processing caused the project to temporarily lapse, resulting in the halt of new-flat registrations on the portal and disrupting the project’s cash flow. Despite this set…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Olive - Phase III - Pranjee Garden City?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Olive - Phase III - Pranjee Garden City in Katrap, Thane is P51700025487.
Is Olive - Phase III - Pranjee Garden City registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City is registered as P51700025487 and its status is "Registered and active".
What is the current construction status of Olive - Phase III - Pranjee Garden City? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Olive is 100% done and internal work 96%. GharKundli's full report compares construction progress with the deadline.
Does Olive - Phase III - Pranjee Garden City have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Olive - Phase III - Pranjee Garden City safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City is registered on MahaRERA as P51700025487, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Olive - Phase III - Pranjee Garden City?
Olive - Phase III - Pranjee Garden City is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Olive - Phase III - Pranjee Garden City?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Olive - Phase III - Pranjee Garden City: gharkundli.com/tools/property-cost-calculator
Has Olive - Phase III - Pranjee Garden City received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Olive - Phase III - Pranjee Garden City uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Olive - Phase III - Pranjee Garden City was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Olive - Phase III - Pranjee Garden City's possession date changes?
The latest dates are on Olive - Phase III - Pranjee Garden City's MahaRERA page (P51700025487). GharKundli's Kundli Watch sends a free WhatsApp update on Olive - Phase III - Pranjee Garden City every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Olive - Phase III - Pranjee Garden City have?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City has one building filed: Olive with 13 floors and 172 units.
How much parking does Olive - Phase III - Pranjee Garden City have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 98 covered car parking spaces for Olive - Phase III - Pranjee Garden City.
How big is the land of Olive - Phase III - Pranjee Garden City?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City stands on 9,801 sq m of land (about 2.4 acres), with 7,738 sq m of sanctioned built-up area and 4,300 sq m of recreational open space.
What is the track record of Olive - Phase III - Pranjee Garden City's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pranjee Properties has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 11 months); 2 still being built, 2 past the promised date (typically 57 months late). 8 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Olive - Phase III - Pranjee Garden City?
Google Maps has reviews of Olive - Phase III - Pranjee Garden City written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Olive - Phase III - Pranjee Garden City?
Olive - Phase III - Pranjee Garden City by Pranjee Properties Pvt. Ltd is in Katrap, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700025487, per GharKundli's check of MahaRERA records. Its land is filed as Plot No. 5 Part. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Olive - Phase III - Pranjee Garden City, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City has 172 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.
When was Olive - Phase III - Pranjee Garden City registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Olive - Phase III - Pranjee Garden City was registered on MahaRERA on 8 June 2020. GharKundli did not find a title report on the land on file there.
Does Olive - Phase III - Pranjee Garden City have any legal issues or court cases?
No court cases are listed for Olive - Phase III - Pranjee Garden City on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Olive - Phase III - Pranjee Garden City?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pranjee Properties Pvt. Ltd, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Olive - Phase III - Pranjee Garden City
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kulgaon (421503)
- Ram Regalia
- Thanekar BKC Vista
- Durvankur Co-op Hsg Soc Ltd
- Thanekar BKC Paramount
- Gurudev 1
- Shivansh Enclave
- Jalaram Jyot Co-op Housing Society Ltd.
- Panvelkar Evoke Co-op Housing Society Ltd
Other projects by Pranjee Properties Pvt. Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.