Palm
by Pranjee Properties Pvt. Ltd · Katrap, Thane
Possession: Palm is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700004695. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Palm?
How the possession date of Palm has moved
28 May 2021
Completion date given when the project was registered
28 February 2022
Extended at the builder's request (MahaRERA application EXT51700009665)
Reason the builder gave MahaRERA: “Covid 19 Pandemic and related lock down made the sales, collections and construction work slow.”
28 August 2022
Revised completion date on MahaRERA
Source: Palm’s extension records on MahaRERA (P51700004695), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Palm
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the August 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700004695
- Status
- Completed
- Builder
- Pranjee Properties Pvt. Ltd
- Location
- Katrap, Thane · 421503
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- May 2021
- Latest completion date
- August 2022
- Delay so far
- 15 months
- Homes
- 602
- Towers
- 5
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Palm, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Pine | 0% | 0% | 0% | 0% |
| Fern | 0% | 0% | 0% | 0% |
| Palm | 100% | 100% | 0% | 0% |
| Olive | 0% | 0% | 0% | 0% |
| Mahogany | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Palm every month.
Palm: buildings, flats and land, as filed on MahaRERA
- Buildings: Pine (13 floors) · Fern (21 floors) · Palm (13 floors) · Olive (13 floors) · Mahogany (13 floors)
- Land: 9,801 sq m (about 2.4 acres) · sanctioned built-up 5,101 sq m · recreational space 4,300 sq m
The builder’s record and reviews
Pranjee Properties has 6 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 11 months); 1 still being built, 1 past the promised date (typically 18 months late). 8 complaints on MahaRERA across 3 projects.
Read Google reviews of Palm →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Palm: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Palm
What is the possession date of Palm?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Palm in Katrap, Thane is 28 August 2022 — 15 months later than 28 May 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Palm?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Palm's builder has filed on MahaRERA, the official one, is 28 August 2022, already 15 months later than the 28 May 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Palm extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm's builder applied to MahaRERA to extend the completion date once: to 28 February 2022, giving the reason "Covid 19 Pandemic and related lock down made the sales, collections and construction work slow.".
What is the RERA number of Palm?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Palm in Katrap, Thane is P51700004695.
Is Palm registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm is registered as P51700004695 and its status is "Completed".
What is the construction status of Palm?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Palm have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Palm safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm is registered on MahaRERA as P51700004695, its MahaRERA status is "Completed", its completion date has moved 15 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Palm's possession date changes?
The latest dates are on Palm's MahaRERA page (P51700004695). GharKundli's Kundli Watch sends a free WhatsApp update on Palm every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Palm have?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm has 5 buildings filed: Pine with 13 floors; Fern with 21 floors; Palm with 13 floors; Olive with 13 floors; Mahogany with 13 floors.
How big is the land of Palm?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm stands on 9,801 sq m of land (about 2.4 acres), with 5,101 sq m of sanctioned built-up area and 4,300 sq m of recreational open space.
What is the track record of Palm's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Pranjee Properties has 6 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 11 months); 1 still being built, 1 past the promised date (typically 18 months late). 8 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Palm?
Google Maps has reviews of Palm written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Palm?
Palm by Pranjee Properties Pvt. Ltd is in Katrap, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700004695, per GharKundli's check of MahaRERA records.
How many homes are in Palm?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm has 602 homes in 5 towers registered on MahaRERA.
When was Palm registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Palm was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Palm?
No court cases are listed for Palm on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Palm?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Pranjee Properties Pvt. Ltd, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Palm
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Katrap
- Olive - Phase III - Pranjee Garden City
- Ram Regalia
- THANEKAR BKC VISTA
- Durvankur Co-op Hsg Soc Ltd
- THANEKAR BKC PARAMOUNT
- Gurudev 1
- Shivansh Enclave
- Jalaram Jyot Co-op Housing Society Ltd.
Other projects by Pranjee Properties Pvt. Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.