Siddhi Rajeshwari Residency Phase II

by SHREE SIDDHI CONSTRUCTION · Umbharani, Thane 421301Registered on MahaRERA as “RAJESHWARI RESIDENCY PHASE II”

What’s in the report? →

Possession date of Siddhi Rajeshwari Residency Phase II (MahaRERA P51700025220): 31 December 2027, moved from 30 March 2025 (33 months later). It has 42 homes, 50% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700025220, and currently active.

Source: MahaRERA website — records for P51700025220, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Siddhi Rajeshwari Residency Phase II?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Siddhi Rajeshwari Residency Phase II has moved

  1. 30 March 2025

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51700028359)

    Reason the builder gave MahaRERA: “As per submission attached.”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EA27022620043)

    Reason the builder gave MahaRERA:
    “We, M/s RAJESHWARI RESIDENCY PHASE II, ("SHREE SIDDHI"), and we are writing you with regards to our application for extension of time till 31st December, 2027; 1. As you are aware that the company is engaged in the constructing a real estat…” Read the full reason“We, M/s RAJESHWARI RESIDENCY PHASE II, ("SHREE SIDDHI"), and we are writing you with regards to our application for extension of time till 31st December, 2027; 1. As you are aware that the company is engaged in the constructing a real estate project at Kalyan, Maharashtra on its plot of land comprising of 1 Building Wings having 7 floors.” [hereinafter collectively referred to as "the Proiect"). 2. We say that we obtained the Rera registration number P51700025220 on 23-03-2020 for Project RAJESHWARI RESIDENCY PHASE II at Kalyan, Thane. 3. We say that we have applied for the Part Occupancy C…”

Source: Siddhi Rajeshwari Residency Phase II’s extension records on MahaRERA (P51700025220), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Siddhi Rajeshwari Residency Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700025220
Status
Registered and active
Builder
SHREE SIDDHI CONSTRUCTION
Location
Umbharani, Thane · 421301
Project type
Residential / Group Housing
Registered on
23 Mar 2020
Completion date at registration
March 2025
Latest completion date
December 2027
Delay so far
33 months
Homes
42
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Siddhi Rajeshwari Residency Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RAJESHWARI RESIDENCY100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • RAJESHWARI RESIDENCY: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Siddhi Rajeshwari Residency Phase II every 1–2 months.

Siddhi Rajeshwari Residency Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: RAJESHWARI RESIDENCY (8 floors, 42 units)
  • Land: 1,428 sq m (about 0.4 acres) · sanctioned built-up 1,428 sq m
  • Land, as filed: SURVEY NO 30/2, 30/3/2/1, 30/3/2/2
  • Map: Get directions

The builder’s record and reviews

Shree Siddhi Construction has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 7 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Siddhi Rajeshwari Residency Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Siddhi Rajeshwari Residency Phase II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Siddhi Rajeshwari Residency Phase II

What is the possession date of Siddhi Rajeshwari Residency Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Siddhi Rajeshwari Residency Phase II in Umbharani, Thane is 31 December 2027 — 33 months later than 30 March 2025, the date given at registration.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Siddhi Rajeshwari Residency Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Siddhi Rajeshwari Residency Phase II's builder has filed on MahaRERA, the official one, is 31 December 2027, already 33 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Siddhi Rajeshwari Residency Phase II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "As per submission attached."; to 31 December 2027, giving the reason "We, M/s RAJESHWARI RESIDENCY PHASE II, ("SHREE SIDDHI"), and we are writing you with regards to our application for extension of time till 31st December, 2027; 1. As you are aware that the company is engaged in the constructing a real estate project at Kalyan, Maharashtra on its plot of land comprising of 1 Building Wings having 7 floors.” [hereinafter collectively referred to as "the Proiect"). 2. We say that we obtained the Rera registration number P51700025220 on 23-03-2020 for Project RAJESHWARI RESIDENCY PHASE II at Kalyan, Thane. 3. We say that we have applied for the Part Occupancy C…".

What is the RERA number of Siddhi Rajeshwari Residency Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Siddhi Rajeshwari Residency Phase II in Umbharani, Thane is P51700025220.

Is Siddhi Rajeshwari Residency Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II is registered as P51700025220 and its status is "Registered and active".

What is the current construction status of Siddhi Rajeshwari Residency Phase II? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAJESHWARI RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Siddhi Rajeshwari Residency Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Siddhi Rajeshwari Residency Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II is registered on MahaRERA as P51700025220, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Siddhi Rajeshwari Residency Phase II?

Siddhi Rajeshwari Residency Phase II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Siddhi Rajeshwari Residency Phase II?

For a flat in Siddhi Rajeshwari Residency Phase II (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Siddhi Rajeshwari Residency Phase II received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Siddhi Rajeshwari Residency Phase II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Siddhi Rajeshwari Residency Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Siddhi Rajeshwari Residency Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: RAJESHWARI RESIDENCY (P51700005861, possession 20 Jun 2022). Check that your agreement names the registration of your own wing.

How can I get updates if Siddhi Rajeshwari Residency Phase II's possession date changes?

The latest dates are on Siddhi Rajeshwari Residency Phase II's MahaRERA page (P51700025220). GharKundli's Kundli Watch sends a free WhatsApp update on Siddhi Rajeshwari Residency Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Siddhi Rajeshwari Residency Phase II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II has one building filed: RAJESHWARI RESIDENCY with 8 floors and 42 units.

How big is the land of Siddhi Rajeshwari Residency Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II stands on 1,428 sq m of land (about 0.4 acres), with 1,428 sq m of sanctioned built-up area.

What is the track record of Siddhi Rajeshwari Residency Phase II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Siddhi Construction has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 7 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Siddhi Rajeshwari Residency Phase II?

Google Maps has reviews of Siddhi Rajeshwari Residency Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Siddhi Rajeshwari Residency Phase II?

Siddhi Rajeshwari Residency Phase II by SHREE SIDDHI CONSTRUCTION is in Umbharani, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700025220, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 30/2, 30/3/2/1, 30/3/2/2. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).

How many flats are in Siddhi Rajeshwari Residency Phase II, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II has 42 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was Siddhi Rajeshwari Residency Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Siddhi Rajeshwari Residency Phase II was registered on MahaRERA on 23 March 2020. GharKundli did not find a title report on the land on file there.

Does Siddhi Rajeshwari Residency Phase II have any legal issues or court cases?

No court cases are listed for Siddhi Rajeshwari Residency Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Siddhi Rajeshwari Residency Phase II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SIDDHI CONSTRUCTION, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Kalyan

All 582 projects in Kalyan (421301) →

Other projects by SHREE SIDDHI CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.