Possession date of Kasturi Van Building No-1 (MahaRERA P51700025276): 30 April 2030. It has 344 homes, 11% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700025276, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700025276, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kasturi Van Building No-1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kasturi Van Building No-1 has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kasturi Van Building No-1’s extension records on MahaRERA (P51700025276), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kasturi Van Building No-1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700025276
Status
Registered and active
Builder
GUJARAT ESTATE
Location
Bhayander East, Thane · 401105
Project type
Residential / Group Housing
Registered on
31 Mar 2020
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
344
Sold or booked
11%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Kasturi Van Building No-1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KASTURI VAN BUILDING NO 1100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

Latest CC order on MahaRERA: dated 21/10/2022.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kasturi Van Building No-1 every 1–2 months.

Kasturi Van Building No-1: buildings, flats and land, as filed on MahaRERA

  • Buildings: KASTURI VAN BUILDING NO 1 (36 floors, 362 units)
  • Car parking: 245 covered
  • Land: 5,822 sq m (about 1.4 acres) · sanctioned built-up 29,990 sq m · recreational space 988 sq m
  • Land, as filed: OLD SURVEY NO 63 66 NEW SURVEY NO 108 109
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Reliance Corporation (a group of 13 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 10 finished, 9 within the promised date and 1 needed more time (typically 40 months); 5 still being built, 2 past the promised date (typically 26 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Kasturi Van Building No-1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kasturi Van Building No-1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kasturi Van Building No-1

What is the possession date of Kasturi Van Building No-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kasturi Van Building No-1 in Bhayander East, Thane is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kasturi Van Building No-1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kasturi Van Building No-1's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kasturi Van Building No-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kasturi Van Building No-1 in Bhayander East, Thane is P51700025276.

Is Kasturi Van Building No-1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 is registered as P51700025276 and its status is "Registered and active".

What is the current construction status of Kasturi Van Building No-1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KASTURI VAN BUILDING NO 1 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Kasturi Van Building No-1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kasturi Van Building No-1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 is registered on MahaRERA as P51700025276, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kasturi Van Building No-1?

Kasturi Van Building No-1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kasturi Van Building No-1?

For a flat in Kasturi Van Building No-1 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kasturi Van Building No-1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Kasturi Van Building No-1 a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1's planning authority on MahaRERA is MCGM File or Ref. Number, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Kasturi Van Building No-1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kasturi Van Building No-1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kasturi Van Building No-1's possession date changes?

The latest dates are on Kasturi Van Building No-1's MahaRERA page (P51700025276). GharKundli's Kundli Watch sends a free WhatsApp update on Kasturi Van Building No-1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kasturi Van Building No-1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 has one building filed: KASTURI VAN BUILDING NO 1 with 36 floors and 362 units.

How much parking does Kasturi Van Building No-1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 245 covered car parking spaces for Kasturi Van Building No-1.

How big is the land of Kasturi Van Building No-1?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 stands on 5,822 sq m of land (about 1.4 acres), with 29,990 sq m of sanctioned built-up area and 988 sq m of recreational open space.

What is the track record of Kasturi Van Building No-1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Reliance Corporation (a group of 13 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 10 finished, 9 within the promised date and 1 needed more time (typically 40 months); 5 still being built, 2 past the promised date (typically 26 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kasturi Van Building No-1?

Google Maps has reviews of Kasturi Van Building No-1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kasturi Van Building No-1?

Kasturi Van Building No-1 by GUJARAT ESTATE (Annapurna) is in Bhayander East, Thane, pincode 401105 (near Bhayander West, Goddev Village, Vinay Nagar), Maharashtra, and is registered on MahaRERA as P51700025276, per GharKundli's check of MahaRERA records. Its land is filed as OLD SURVEY NO 63 66 NEW SURVEY NO 108 109. GharKundli lists all 99 MahaRERA projects in Bhayander East (401105).

How many flats are in Kasturi Van Building No-1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 has 344 homes in 1 tower registered on MahaRERA, and 11% of them are sold or booked.

When was Kasturi Van Building No-1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kasturi Van Building No-1 was registered on MahaRERA on 31 March 2020. GharKundli did not find a title report on the land on file there.

Does Kasturi Van Building No-1 have any legal issues or court cases?

No court cases are listed for Kasturi Van Building No-1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kasturi Van Building No-1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GUJARAT ESTATE, the company Annapurna files this project under.

All projects with possession due in 2030 in Palghar →

Other projects in Bhayander East (401105)

All 99 projects in Bhayander East (401105) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.