GharKundli

Saikrupa Nandanvan

by SAIKRUPA BUILDERS AND DEVELOPERS · Maneri, Sindhudurg 416512Registered on MahaRERA as “NANDANVAN”

What’s in the report? →

Possession date of Saikrupa Nandanvan (MahaRERA P52900020440): 29 March 2021, moved from 30 September 2019 (18 months later), and it has already passed. It has 21 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900020440. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52900020440, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (March 2021) has passed.

What do you want to know about Saikrupa Nandanvan?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Saikrupa Nandanvan has moved

  1. 30 September 2019

    Completion date given when the project was registered

  2. 29 September 2020

    Extended at the builder's request (MahaRERA application EXT52900002480)

    Reason the builder gave MahaRERA:
    “Respected sir, we got a permission for construction on 08/06/2018 but and rera done on 10/04/2019 . till date we have not done any agreement with any customer. just take a token ammount and they have no any objection for extension.we are su…” Read the full reason“Respected sir, we got a permission for construction on 08/06/2018 but and rera done on 10/04/2019 . till date we have not done any agreement with any customer. just take a token ammount and they have no any objection for extension.we are submitting resolution of allottees below for the same. So please we request you to extend our rera registration for next one year i.e.29/09/2020. Thanks and regards Ganesh shetye Saikrupa builders and developers.”
  3. 29 March 2021

    Revised completion date on MahaRERA

Source: Saikrupa Nandanvan’s extension records on MahaRERA (P52900020440), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Saikrupa Nandanvan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900020440
Status
Lapsed (registration period ended)
Builder
SAIKRUPA BUILDERS AND DEVELOPERS
Location
Maneri, Sindhudurg · 416512
Project type
Commercial
Registered on
10 Apr 2019
Completion date at registration
September 2019
Latest completion date
March 2021
Delay so far
18 months
Homes
21
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Saikrupa Nandanvan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NANDANVAN100%100%75%75%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saikrupa Nandanvan every 1–2 months.

Saikrupa Nandanvan: buildings, flats and land, as filed on MahaRERA

  • Buildings: NANDANVAN (4 floors)
  • Land: 1,250 sq m (about 0.3 acres) · sanctioned built-up 1,226 sq m · recreational space 571 sq m
  • Boundaries filed include: INTERNAL PLOTING ROAD, BANDA DODAMARG STATE HIGHWAY
  • Land, as filed: 123B
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Saikrupa Nandanvan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Saikrupa Nandanvan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Saikrupa Nandanvan

What is the possession date of Saikrupa Nandanvan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saikrupa Nandanvan in Maneri, Sindhudurg is 29 March 2021 — 18 months later than 30 September 2019, the date given at registration. That date has already passed.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Saikrupa Nandanvan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Saikrupa Nandanvan's builder has filed on MahaRERA, the official one, is 29 March 2021, already 18 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Saikrupa Nandanvan extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan's builder applied to MahaRERA to extend the completion date once: to 29 September 2020, giving the reason "Respected sir, we got a permission for construction on 08/06/2018 but and rera done on 10/04/2019 . till date we have not done any agreement with any customer. just take a token ammount and they have no any objection for extension.we are submitting resolution of allottees below for the same. So please we request you to extend our rera registration for next one year i.e.29/09/2020. Thanks and regards Ganesh shetye Saikrupa builders and developers.".

What is the RERA number of Saikrupa Nandanvan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saikrupa Nandanvan in Maneri, Sindhudurg is P52900020440.

Is Saikrupa Nandanvan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan is registered as P52900020440 and its status is "Lapsed (registration period ended)".

What is the current construction status of Saikrupa Nandanvan? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NANDANVAN is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does Saikrupa Nandanvan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Saikrupa Nandanvan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan is registered on MahaRERA as P52900020440, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Saikrupa Nandanvan?

Saikrupa Nandanvan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Saikrupa Nandanvan?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saikrupa Nandanvan: gharkundli.com/tools/property-cost-calculator

Has Saikrupa Nandanvan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 29 March 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Saikrupa Nandanvan?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (29 March 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Saikrupa Nandanvan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saikrupa Nandanvan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Saikrupa Nandanvan's possession date changes?

The latest dates are on Saikrupa Nandanvan's MahaRERA page (P52900020440). GharKundli's Kundli Watch sends a free WhatsApp update on Saikrupa Nandanvan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Saikrupa Nandanvan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan has one building filed: NANDANVAN with 4 floors.

How big is the land of Saikrupa Nandanvan?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan stands on 1,250 sq m of land (about 0.3 acres), with 1,226 sq m of sanctioned built-up area and 571 sq m of recreational open space.

What are the reviews of Saikrupa Nandanvan?

Google Maps has reviews of Saikrupa Nandanvan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Saikrupa Nandanvan?

Saikrupa Nandanvan by SAIKRUPA BUILDERS AND DEVELOPERS is in Maneri, Sindhudurg, pincode 416512, Maharashtra, and is registered on MahaRERA as P52900020440, per GharKundli's check of MahaRERA records. Its boundaries filed there include INTERNAL PLOTING ROAD, BANDA DODAMARG STATE HIGHWAY. Its land is filed as 123B. GharKundli lists all 23 MahaRERA projects in Dodamarg (416512).

How many flats are in Saikrupa Nandanvan?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan has 21 homes in 1 tower registered on MahaRERA.

When was Saikrupa Nandanvan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Nandanvan was registered on MahaRERA on 10 April 2019. GharKundli did not find a title report on the land on file there.

Does Saikrupa Nandanvan have any legal issues or court cases?

No court cases are listed for Saikrupa Nandanvan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Saikrupa Nandanvan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAIKRUPA BUILDERS AND DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in Dodamarg (416512)

All 23 projects in Dodamarg (416512) →

Other projects by SAIKRUPA BUILDERS AND DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.