Saikrupa Sai Vishwa

by SAIKRUPA BUILDERS AND DEVELOPERS · Nigadi, Pune 412109Registered on MahaRERA as “SAI VISHWA”

What’s in the report? →

Possession date of Saikrupa Sai Vishwa (MahaRERA P52100010527): 31 December 2019, moved from 31 December 2018 (12 months later), and it has already passed. It has 176 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100010527. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100010527, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2019) has passed.

What do you want to know about Saikrupa Sai Vishwa?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Saikrupa Sai Vishwa has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52100001357)

    Reason the builder gave MahaRERA: “Due to adverse market condition there are no bookings for commercials. The construction work of commercial complex is started. Residential buildings work completed soon. We will apply occupancy certificate of residential complex soon.”

Source: Saikrupa Sai Vishwa’s extension records on MahaRERA (P52100010527), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Saikrupa Sai Vishwa

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100010527
Status
Lapsed (registration period ended)
Builder
SAIKRUPA BUILDERS AND DEVELOPERS
Location
Nigadi, Pune · 412109
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
176
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Saikrupa Sai Vishwa, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C67%80%50%0%
B67%80%50%0%
A0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saikrupa Sai Vishwa every 1–2 months.

Saikrupa Sai Vishwa: buildings, flats and land, as filed on MahaRERA

  • Buildings: C (9 floors) · B (9 floors) · A (4 floors)
  • Land: 6,592 sq m (about 1.6 acres) · sanctioned built-up 6,962 sq m · recreational space 6,592 sq m
  • Land, as filed: 125 PART
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Saikrupa Sai Vishwa →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Saikrupa Sai Vishwa: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Saikrupa Sai Vishwa

What is the possession date of Saikrupa Sai Vishwa?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saikrupa Sai Vishwa in Nigadi, Pune is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Saikrupa Sai Vishwa?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Saikrupa Sai Vishwa's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Saikrupa Sai Vishwa extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "Due to adverse market condition there are no bookings for commercials. The construction work of commercial complex is started. Residential buildings work completed soon. We will apply occupancy certificate of residential complex soon.".

What is the RERA number of Saikrupa Sai Vishwa?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saikrupa Sai Vishwa in Nigadi, Pune is P52100010527.

Is Saikrupa Sai Vishwa registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa is registered as P52100010527 and its status is "Lapsed (registration period ended)".

What is the current construction status of Saikrupa Sai Vishwa? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 80% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Saikrupa Sai Vishwa have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Saikrupa Sai Vishwa safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa is registered on MahaRERA as P52100010527, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Saikrupa Sai Vishwa?

Saikrupa Sai Vishwa isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Saikrupa Sai Vishwa?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saikrupa Sai Vishwa: gharkundli.com/tools/property-cost-calculator

Has Saikrupa Sai Vishwa received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Saikrupa Sai Vishwa?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2019) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Saikrupa Sai Vishwa uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saikrupa Sai Vishwa was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Saikrupa Sai Vishwa's possession date changes?

The latest dates are on Saikrupa Sai Vishwa's MahaRERA page (P52100010527). GharKundli's Kundli Watch sends a free WhatsApp update on Saikrupa Sai Vishwa every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Saikrupa Sai Vishwa have?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa has 3 buildings filed: C with 9 floors; B with 9 floors; A with 4 floors.

How big is the land of Saikrupa Sai Vishwa?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa stands on 6,592 sq m of land (about 1.6 acres), with 6,962 sq m of sanctioned built-up area and 6,592 sq m of recreational open space.

What are the reviews of Saikrupa Sai Vishwa?

Google Maps has reviews of Saikrupa Sai Vishwa written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Saikrupa Sai Vishwa?

Saikrupa Sai Vishwa by SAIKRUPA BUILDERS AND DEVELOPERS is in Nigadi, Pune, pincode 412109, Maharashtra, and is registered on MahaRERA as P52100010527, per GharKundli's check of MahaRERA records. Its land is filed as 125 PART. GharKundli lists all 69 MahaRERA projects in Dehu (412109).

How many flats are in Saikrupa Sai Vishwa?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa has 176 homes in 3 towers registered on MahaRERA.

When was Saikrupa Sai Vishwa registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saikrupa Sai Vishwa was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Does Saikrupa Sai Vishwa have any legal issues or court cases?

No court cases are listed for Saikrupa Sai Vishwa on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Saikrupa Sai Vishwa?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAIKRUPA BUILDERS AND DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in Mawal

All 69 projects in Dehu (412109) →

Other projects by SAIKRUPA BUILDERS AND DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.