SAMARTH PLAZA
by M/S UNIQUE INFRA · Village Tarele, Sindhudurg
Possession date of SAMARTH PLAZA: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900053485, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SAMARTH PLAZA?
How the possession date of SAMARTH PLAZA has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAMARTH PLAZA’s extension records on MahaRERA (P52900053485), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAMARTH PLAZA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900053485
- Status
- Registered and active
- Builder
- M/S UNIQUE INFRA
- Location
- Village Tarele, Sindhudurg · 416801
- Project type
- Others
- Registered on
- 6 Nov 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 45
- Sold or booked
- 36%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAMARTH PLAZA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAMARTH PLAZA | 100% | 70% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAMARTH PLAZA: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMARTH PLAZA every month.
SAMARTH PLAZA: buildings, flats and land, as filed on MahaRERA
- Buildings: SAMARTH PLAZA (7 floors, 57 units)
- Land: 2,697 sq m (about 0.7 acres) · sanctioned built-up 3,603 sq m
The builder’s record and reviews
Unique Infra has 4 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 31 months late). No complaints on MahaRERA.
Read Google reviews of SAMARTH PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAMARTH PLAZA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAMARTH PLAZA
What is the possession date of SAMARTH PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAMARTH PLAZA in Village Tarele, Sindhudurg is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAMARTH PLAZA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMARTH PLAZA's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SAMARTH PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAMARTH PLAZA in Village Tarele, Sindhudurg is P52900053485.
Is SAMARTH PLAZA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA is registered as P52900053485 and its status is "Registered and active".
What is the construction status of SAMARTH PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAMARTH PLAZA is 70% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SAMARTH PLAZA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SAMARTH PLAZA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA is registered on MahaRERA as P52900053485, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAMARTH PLAZA's possession date changes?
The latest dates are on SAMARTH PLAZA's MahaRERA page (P52900053485). GharKundli's Kundli Watch sends a free WhatsApp update on SAMARTH PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAMARTH PLAZA have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA has one building filed: SAMARTH PLAZA with 7 floors and 57 units.
How big is the land of SAMARTH PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA stands on 2,697 sq m of land (about 0.7 acres), with 3,603 sq m of sanctioned built-up area.
What is the track record of SAMARTH PLAZA's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Unique Infra has 4 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 31 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAMARTH PLAZA?
Google Maps has reviews of SAMARTH PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAMARTH PLAZA?
SAMARTH PLAZA by M/S UNIQUE INFRA is in Village Tarele, Sindhudurg (pincode 416801), Maharashtra, and is registered on MahaRERA as P52900053485, per GharKundli's check of MahaRERA records.
How many homes are in SAMARTH PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA has 45 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.
When was SAMARTH PLAZA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAMARTH PLAZA was registered on MahaRERA on 6 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SAMARTH PLAZA?
No court cases are listed for SAMARTH PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAMARTH PLAZA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S UNIQUE INFRA.
Check it yourself on MahaRERA
- How to check the possession date of SAMARTH PLAZA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Sindhudurg →
Other projects in Kankavli
- Shree Sadan
- Royal Enclave
- Anant Pride
- Galaxy Residency
- MAITRI GARDEN
- KAMAT VISHWA - 2
- Adinath Residency
- RAJ & SV HOMES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.