The Anantaa Phase I
by Ashtha Vinayak Developers LLP (Anjani) · Uttan, Thane 401106
What’s in the report? →Possession date of The Anantaa Phase I (MahaRERA P51700026651): 31 May 2030, moved from 31 January 2026 (48 months later). It has 22 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700026651, and currently active. Its completion date has moved from January 2026 to May 2030: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700026651, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about The Anantaa Phase I?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of The Anantaa Phase I has moved
31 January 2026
Completion date given when the project was registered
31 January 2030
Extended at the builder's request (MahaRERA application EA09022619770)
Reason the builder gave MahaRERA:
“1. As on date, around 20% of the construction work of the project has been completed. 2. Due to various administrative, financial, and technical constraints, there has been a delay in the progress of the project. 3. No bookings have been ma…” Read the full reason
“1. As on date, around 20% of the construction work of the project has been completed. 2. Due to various administrative, financial, and technical constraints, there has been a delay in the progress of the project. 3. No bookings have been made, and no funds have been collected from any allottee till date. 4. We are fully committed to completing the project and are in the process of arranging the necessary resources to continue the work in a phased and time-bound manner. 5. Based on the current work plan and realistic project schedule, we expect to complete the entire project including all re…”31 May 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: The Anantaa Phase I’s extension records on MahaRERA (P51700026651), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Anantaa Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700026651
- Status
- Registered and active
- Builder
- Ashtha Vinayak Developers LLP
- Location
- Uttan, Thane · 401106
- Project type
- Residential / Group Housing
- Registered on
- 21 Oct 2020
- Completion date at registration
- January 2026
- Latest completion date
- May 2030
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 22
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of The Anantaa Phase I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 1 | 18.18% | 9.09% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 1: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Anantaa Phase I every 1–2 months.
The Anantaa Phase I: buildings, flats and land, as filed on MahaRERA
- Buildings: 1 (56 floors, 22 units)
- Land: 15,591 sq m (about 3.9 acres) · sanctioned built-up 1,414 sq m · recreational space 2,339 sq m
- Boundaries filed include: Uttan Gorai Road
- Land, as filed: 340/9Pt,203/8,203/9,203/10,203/12
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Geeta Developers (a group of 11 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 9 finished, all within the promised date; 8 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of The Anantaa Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Anantaa Phase I: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about The Anantaa Phase I
What is the possession date of The Anantaa Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Anantaa Phase I in Uttan, Thane is 31 May 2030 — 48 months later than 31 January 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for The Anantaa Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Anantaa Phase I's builder has filed on MahaRERA, the official one, is 31 May 2030, already 48 months later than the 31 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Anantaa Phase I extended?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I's builder applied to MahaRERA to extend the completion date once: to 31 January 2030, giving the reason "1. As on date, around 20% of the construction work of the project has been completed. 2. Due to various administrative, financial, and technical constraints, there has been a delay in the progress of the project. 3. No bookings have been made, and no funds have been collected from any allottee till date. 4. We are fully committed to completing the project and are in the process of arranging the necessary resources to continue the work in a phased and time-bound manner. 5. Based on the current work plan and realistic project schedule, we expect to complete the entire project including all re…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of The Anantaa Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Anantaa Phase I in Uttan, Thane is P51700026651.
Is The Anantaa Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I is registered as P51700026651 and its status is "Registered and active".
What is the current construction status of The Anantaa Phase I? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 1 is 9.09% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does The Anantaa Phase I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is The Anantaa Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I is registered on MahaRERA as P51700026651, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in The Anantaa Phase I?
The Anantaa Phase I is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in The Anantaa Phase I?
For a flat in The Anantaa Phase I (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has The Anantaa Phase I received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I is still under construction, with 31 May 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has The Anantaa Phase I uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Anantaa Phase I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if The Anantaa Phase I's possession date changes?
The latest dates are on The Anantaa Phase I's MahaRERA page (P51700026651). GharKundli's Kundli Watch sends a free WhatsApp update on The Anantaa Phase I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Anantaa Phase I have?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I has one building filed: 1 with 56 floors and 22 units.
How big is the land of The Anantaa Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I stands on 15,591 sq m of land (about 3.9 acres), with 1,414 sq m of sanctioned built-up area and 2,339 sq m of recreational open space.
What is the track record of The Anantaa Phase I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Geeta Developers (a group of 11 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 9 finished, all within the promised date; 8 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of The Anantaa Phase I?
Google Maps has reviews of The Anantaa Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of The Anantaa Phase I?
The Anantaa Phase I by Ashtha Vinayak Developers LLP (Anjani) is in Uttan, Thane, pincode 401106, Maharashtra, and is registered on MahaRERA as P51700026651, per GharKundli's check of MahaRERA records. Its boundaries filed there include Uttan Gorai Road. Its land is filed as 340/9Pt,203/8,203/9,203/10,203/12. GharKundli lists all 5 MahaRERA projects in Uttan (401106).
How many flats are in The Anantaa Phase I, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I has 22 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was The Anantaa Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Anantaa Phase I was registered on MahaRERA on 21 October 2020. GharKundli did not find a title report on the land on file there.
Does The Anantaa Phase I have any legal issues or court cases?
No court cases are listed for The Anantaa Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of The Anantaa Phase I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ashtha Vinayak Developers LLP, the company Anjani files this project under.
Check it yourself on MahaRERA
- How to check the possession date of The Anantaa Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Thane →
Other projects in Thane
- Pride of Uttan
- Estrella Villas
- Towncrest
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Gurukrupa Nityam
- Mauli Krupa
- Panache
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.