Matoshree Residency
by M/S MATOSHREE DEVELOPERS · Near Patil Bhavan, Thane 421204Also near Borivali West, Ghatkopar West, Kalyan
What’s in the report? →Possession date of Matoshree Residency (MahaRERA P51700027225): 31 December 2027, moved from 30 June 2025 (26 months later). It has 16 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700027225, and currently active. Its completion date has moved from June 2025 to December 2027: 26 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700027225, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Matoshree Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Matoshree Residency has moved
30 June 2025
Completion date given when the project was registered
31 August 2027
Extended at the builder's request (MahaRERA application EA10072502033)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, We are addressing this communication in connection with our application submitted under Section 5(3) of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the Maharashtra Real Estate (Regulation…” Read the full reason
“Respected Sir/Madam, We are addressing this communication in connection with our application submitted under Section 5(3) of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of Real Estate Agents, Rates of Interest and Disclosure on Website) Rules, 2017, seeking an extension of the registration period for the project titled " MATOSHREE RESIDENCY" bearing MahaRERA Registration No. P51700027225. We respectfully submit that the extension for a period of 26 mon…”31 December 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Matoshree Residency’s extension records on MahaRERA (P51700027225), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Matoshree Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700027225
- Status
- Registered and active
- Builder
- M/S MATOSHREE DEVELOPERS
- Location
- Near Patil Bhavan, Thane · 421204
- Project type
- Others
- Registered on
- 25 Nov 2020
- Completion date at registration
- June 2025
- Latest completion date
- December 2027
- Delay so far
- 26 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 16
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Matoshree Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MATOSHREE RESIDENCY | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- MATOSHREE RESIDENCY: covers stilt + Ground+ Second Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Matoshree Residency every 1–2 months.
Matoshree Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: MATOSHREE RESIDENCY (3 floors, 30 units)
- Land: 1,170 sq m (about 0.3 acres) · sanctioned built-up 911 sq m
- Land, as filed: S NO.22 ,H NO.12
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Matoshree Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Matoshree Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Matoshree Residency
What is the possession date of Matoshree Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Matoshree Residency in Near Patil Bhavan, Thane is 31 December 2027 — 26 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 26 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Matoshree Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Matoshree Residency's builder has filed on MahaRERA, the official one, is 31 December 2027, already 26 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Matoshree Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency's builder applied to MahaRERA to extend the completion date once: to 31 August 2027, giving the reason "Respected Sir/Madam, We are addressing this communication in connection with our application submitted under Section 5(3) of the Real Estate (Regulation and Development) Act, 2016, read with Rule 7 of the Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of Real Estate Agents, Rates of Interest and Disclosure on Website) Rules, 2017, seeking an extension of the registration period for the project titled " MATOSHREE RESIDENCY" bearing MahaRERA Registration No. P51700027225. We respectfully submit that the extension for a period of 26 mon…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Matoshree Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Matoshree Residency in Near Patil Bhavan, Thane is P51700027225.
Is Matoshree Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency is registered as P51700027225 and its status is "Registered and active".
What is the current construction status of Matoshree Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MATOSHREE RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Matoshree Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Matoshree Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency is registered on MahaRERA as P51700027225, its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Matoshree Residency?
Matoshree Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Matoshree Residency?
For a flat in Matoshree Residency (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Matoshree Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Matoshree Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Matoshree Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Matoshree Residency's possession date changes?
The latest dates are on Matoshree Residency's MahaRERA page (P51700027225). GharKundli's Kundli Watch sends a free WhatsApp update on Matoshree Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Matoshree Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency has one building filed: MATOSHREE RESIDENCY with 3 floors and 30 units.
How big is the land of Matoshree Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency stands on 1,170 sq m of land (about 0.3 acres), with 911 sq m of sanctioned built-up area.
What are the reviews of Matoshree Residency?
Google Maps has reviews of Matoshree Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Matoshree Residency?
Matoshree Residency by M/S MATOSHREE DEVELOPERS is in Near Patil Bhavan, Thane, pincode 421204 (near Borivali West, Ghatkopar West, Kalyan), Maharashtra, and is registered on MahaRERA as P51700027225, per GharKundli's check of MahaRERA records. Its land is filed as S NO.22 ,H NO.12. GharKundli lists all 252 MahaRERA projects in Manpada (421204).
How many flats are in Matoshree Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency has 16 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Matoshree Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Matoshree Residency was registered on MahaRERA on 25 November 2020. GharKundli did not find a title report on the land on file there.
Does Matoshree Residency have any legal issues or court cases?
No court cases are listed for Matoshree Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Matoshree Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S MATOSHREE DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Matoshree Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.