Possession date of WISTERIA SQUARE 1: 30 April 2029, moved from 30 June 2024 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700028141, and currently active. Its completion date has moved from June 2024 to April 2029: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 9 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about WISTERIA SQUARE 1?
How the possession date of WISTERIA SQUARE 1 has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT51700024318)
Reason the builder gave MahaRERA: “document uploaded”
31 December 2028
Extended at the builder's request (MahaRERA application EA23072502171)
Reason the builder gave MahaRERA:
“We respectfully seek an extension of registration for Wisteria Square 1 up to 31/12/2028 due to multiple unforeseen but justifiable delays: 1. Regulatory Coordination Delays: There were unavoidable delays in obtaining revised building permi…” Read the full reason
“We respectfully seek an extension of registration for Wisteria Square 1 up to 31/12/2028 due to multiple unforeseen but justifiable delays: 1. Regulatory Coordination Delays: There were unavoidable delays in obtaining revised building permissions and NOCs from concerned authorities despite timely submissions and proactive follow-ups. These procedural dependencies significantly extended our timelines. 2. Labour Shortages & Migration: The construction schedule was affected by intermittent labour shortages during FY 2023–2024, caused by seasonal migration patterns and post-pandemic workforce f…”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: WISTERIA SQUARE 1’s extension records on MahaRERA (P51700028141), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on WISTERIA SQUARE 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 9 complaints, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700028141
- Status
- Registered and active
- Builder
- RAJDEEP REALTORS
- Location
- Vinay Nagar, Thane · 401107
- Project type
- Residential / Group Housing
- Registered on
- 4 Feb 2021
- Completion date at registration
- June 2024
- Latest completion date
- April 2029
- Delay so far
- 54 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 299
- Sold or booked
- 81%
- Towers
- 1
- Complaints on MahaRERA
- 9
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of WISTERIA SQUARE 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WISTERIA SQUARE 1 | 100% | 60.87% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WISTERIA SQUARE 1: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on WISTERIA SQUARE 1 every month.
WISTERIA SQUARE 1: buildings, flats and land, as filed on MahaRERA
- Buildings: WISTERIA SQUARE 1 (23 floors, 355 units)
- Land: 397 sq m (about 0.1 acres)
The builder’s record and reviews
Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.
Read Google reviews of WISTERIA SQUARE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
WISTERIA SQUARE 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about WISTERIA SQUARE 1
What is the possession date of WISTERIA SQUARE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for WISTERIA SQUARE 1 in Vinay Nagar, Thane is 30 April 2029 — 54 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for WISTERIA SQUARE 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date WISTERIA SQUARE 1's builder has filed on MahaRERA, the official one, is 30 April 2029, already 54 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of WISTERIA SQUARE 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "document uploaded"; to 31 December 2028, giving the reason "We respectfully seek an extension of registration for Wisteria Square 1 up to 31/12/2028 due to multiple unforeseen but justifiable delays: 1. Regulatory Coordination Delays: There were unavoidable delays in obtaining revised building permissions and NOCs from concerned authorities despite timely submissions and proactive follow-ups. These procedural dependencies significantly extended our timelines. 2. Labour Shortages & Migration: The construction schedule was affected by intermittent labour shortages during FY 2023–2024, caused by seasonal migration patterns and post-pandemic workforce f…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of WISTERIA SQUARE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of WISTERIA SQUARE 1 in Vinay Nagar, Thane is P51700028141.
Is WISTERIA SQUARE 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1 is registered as P51700028141 and its status is "Registered and active".
What is the construction status of WISTERIA SQUARE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WISTERIA SQUARE 1 is 60.87% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does WISTERIA SQUARE 1 have complaints on MahaRERA?
9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is WISTERIA SQUARE 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1 is registered on MahaRERA as P51700028141, its completion date has moved 54 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if WISTERIA SQUARE 1's possession date changes?
The latest dates are on WISTERIA SQUARE 1's MahaRERA page (P51700028141). GharKundli's Kundli Watch sends a free WhatsApp update on WISTERIA SQUARE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does WISTERIA SQUARE 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1 has one building filed: WISTERIA SQUARE 1 with 23 floors and 355 units.
How big is the land of WISTERIA SQUARE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1 stands on 397 sq m of land (about 0.1 acres).
What is the track record of WISTERIA SQUARE 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of WISTERIA SQUARE 1?
Google Maps has reviews of WISTERIA SQUARE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is WISTERIA SQUARE 1?
WISTERIA SQUARE 1 by RAJDEEP REALTORS (Ravi) is in Vinay Nagar, Thane (pincode 401107), Maharashtra, and is registered on MahaRERA as P51700028141, per GharKundli's check of MahaRERA records.
How many homes are in WISTERIA SQUARE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1 has 299 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.
When was WISTERIA SQUARE 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), WISTERIA SQUARE 1 was registered on MahaRERA on 4 February 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on WISTERIA SQUARE 1?
No court cases are listed for WISTERIA SQUARE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of WISTERIA SQUARE 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJDEEP REALTORS, the company Ravi files this project under.
Check it yourself on MahaRERA
- How to check the possession date of WISTERIA SQUARE 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in Thane
- JP CONNECT-MIRAROAD
- The Palace Tower A
- ARCH GARDENS I AND II
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- MAULI KRUPA
- GURUKRUPA NITYAM
- ASAVARI CO OP HSG SOC LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.