Sadguru Symphony - Wing - A, D, E, F and G of Phase-II
by SADGURU INFRA · Badlapur West, ThaneAlso near Kulgaon
Possession date of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II: 30 April 2027, moved from 30 June 2024 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700029442, and currently active. Its completion date has moved from June 2024 to April 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
How the possession date of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II has moved
30 June 2024
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700019902)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 59 % allottees for purpose of extension of RERA registration period of the said project.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sadguru Symphony - Wing - A, D, E, F and G of Phase-II’s extension records on MahaRERA (P51700029442), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sadguru Symphony - Wing - A, D, E, F and G of Phase-II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700029442
- Status
- Registered and active
- Builder
- SADGURU INFRA
- Location
- Badlapur West, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 29 May 2021
- Completion date at registration
- June 2024
- Latest completion date
- April 2027
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 5
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 100% | 100% | 0% |
| Wing D | 100% | 75% | 0% | 0% |
| Wing E | 100% | 100% | 35% | 0% |
| Wing F | 100% | 100% | 50% | 0% |
| Wing G | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sadguru Symphony - Wing - A, D, E, F and G of Phase-II every month.
Sadguru Symphony - Wing - A, D, E, F and G of Phase-II: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A (8 floors) · Wing D (8 floors) · Wing E (5 floors) · Wing F (5 floors) · Wing G (2 floors)
- Land: 10,290 sq m (about 2.5 acres) · sanctioned built-up 5,646 sq m · recreational space 912 sq m
The builder’s record and reviews
Sadguru Associate (a group of 3 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 23 months); 5 still being built, 3 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sadguru Symphony - Wing - A, D, E, F and G of Phase-II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sadguru Symphony - Wing - A, D, E, F and G of Phase-II
What is the possession date of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sadguru Symphony - Wing - A, D, E, F and G of Phase-II in Badlapur West, Thane is 30 April 2027 — 30 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sadguru Symphony - Wing - A, D, E, F and G of Phase-II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 30 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 59 % allottees for purpose of extension of RERA registration period of the said project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II in Badlapur West, Thane is P51700029442.
Is Sadguru Symphony - Wing - A, D, E, F and G of Phase-II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II is registered as P51700029442 and its status is "Registered and active".
What is the construction status of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 75% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Sadguru Symphony - Wing - A, D, E, F and G of Phase-II have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sadguru Symphony - Wing - A, D, E, F and G of Phase-II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II is registered on MahaRERA as P51700029442, its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sadguru Symphony - Wing - A, D, E, F and G of Phase-II's possession date changes?
The latest dates are on Sadguru Symphony - Wing - A, D, E, F and G of Phase-II's MahaRERA page (P51700029442). GharKundli's Kundli Watch sends a free WhatsApp update on Sadguru Symphony - Wing - A, D, E, F and G of Phase-II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sadguru Symphony - Wing - A, D, E, F and G of Phase-II have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II has 5 buildings filed: Wing A with 8 floors; Wing D with 8 floors; Wing E with 5 floors; Wing F with 5 floors; Wing G with 2 floors.
How big is the land of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II stands on 10,290 sq m of land (about 2.5 acres), with 5,646 sq m of sanctioned built-up area and 912 sq m of recreational open space.
What is the track record of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Associate (a group of 3 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 23 months); 5 still being built, 3 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
Google Maps has reviews of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
Sadguru Symphony - Wing - A, D, E, F and G of Phase-II by SADGURU INFRA is in Badlapur West, Thane (pincode 421503), near Kulgaon, Maharashtra, and is registered on MahaRERA as P51700029442, per GharKundli's check of MahaRERA records.
When was Sadguru Symphony - Wing - A, D, E, F and G of Phase-II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Symphony - Wing - A, D, E, F and G of Phase-II was registered on MahaRERA on 29 May 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
No court cases are listed for Sadguru Symphony - Wing - A, D, E, F and G of Phase-II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SADGURU INFRA, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sadguru Symphony - Wing - A, D, E, F and G of Phase-II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421503
- SHIV TIRTH B WING
- DATTATRAY RESIDENCY
- PRABHU DARSHAN CO-OPERATIVE HOUSING SOCIETY LIMITED
- SAI UNIVERSE
- MERY VILLA CHSL
- Gokul Heights
- MAHAVIR HERITAGE
- INFINITY MEADOWS
Other projects by SADGURU INFRA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.