GNP GALAXY PHASE - III
by ROSHNI ENTERPRISES · Ambernath West, ThaneAlso near O.E.Ambernath
Possession date of GNP GALAXY PHASE - III: 30 January 2027, moved from 30 September 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700028923, and currently active. Its completion date has moved from September 2025 to January 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GNP GALAXY PHASE - III?
How the possession date of GNP GALAXY PHASE - III has moved
30 September 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA25092517935)
Reason the builder gave MahaRERA:
“We sincerely apologize for the delay in the project's progress and the submission of this extension request. The delay has been primarily due to unforeseen and unfortunate circumstances, including the sudden demise of the main contractor, w…” Read the full reason
“We sincerely apologize for the delay in the project's progress and the submission of this extension request. The delay has been primarily due to unforeseen and unfortunate circumstances, including the sudden demise of the main contractor, which significantly impacted the construction schedule. In addition, we have faced procurement challenges, financial constraints, and on-site operational issues that have further contributed to the delay. Despite these setbacks, we remain fully committed to the project's completion and are actively working to resolve the outstanding issues. In light of the…”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GNP GALAXY PHASE - III’s extension records on MahaRERA (P51700028923), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GNP GALAXY PHASE - III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 2 court cases, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- GNP GALAXY PHASE - IP51700002007 · possession 30 Dec 2022
- GNP GALAXY PHASE - IIP51700002123 · possession 30 Jan 2022
- MahaRERA registration
- P51700028923
- Status
- Registered and active
- Builder
- ROSHNI ENTERPRISES
- Location
- Ambernath West, Thane · 421501
- Project type
- Mixed
- Registered on
- 12 Apr 2021
- Completion date at registration
- September 2025
- Latest completion date
- January 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 71%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of GNP GALAXY PHASE - III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ZONE - 3 | 100% | 100% | 90% | 70% |
Commencement certificate (CC), as filed on MahaRERA
- ZONE - 3: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GNP GALAXY PHASE - III every month.
GNP GALAXY PHASE - III: buildings, flats and land, as filed on MahaRERA
- Buildings: ZONE - 3 (4 floors, 173 units)
- Car parking: 51 open
- Land: 7,731 sq m (about 1.9 acres) · sanctioned built-up 10,236 sq m
- Boundaries filed include: KALAYN BADLAPUR ROAD, MIDC ROAD
The builder’s record and reviews
GNP Landmark (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of GNP GALAXY PHASE - III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GNP GALAXY PHASE - III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GNP GALAXY PHASE - III
What is the possession date of GNP GALAXY PHASE - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GNP GALAXY PHASE - III in Ambernath West, Thane is 30 January 2027 — 12 months later than 30 September 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GNP GALAXY PHASE - III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GNP GALAXY PHASE - III's builder has filed on MahaRERA, the official one, is 30 January 2027, already 12 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GNP GALAXY PHASE - III extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "We sincerely apologize for the delay in the project's progress and the submission of this extension request. The delay has been primarily due to unforeseen and unfortunate circumstances, including the sudden demise of the main contractor, which significantly impacted the construction schedule. In addition, we have faced procurement challenges, financial constraints, and on-site operational issues that have further contributed to the delay. Despite these setbacks, we remain fully committed to the project's completion and are actively working to resolve the outstanding issues. In light of the…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of GNP GALAXY PHASE - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GNP GALAXY PHASE - III in Ambernath West, Thane is P51700028923.
Is GNP GALAXY PHASE - III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III is registered as P51700028923 and its status is "Registered and active".
What is the construction status of GNP GALAXY PHASE - III?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ZONE - 3 is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does GNP GALAXY PHASE - III have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GNP GALAXY PHASE - III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III is registered on MahaRERA as P51700028923, its completion date has moved 12 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does GNP GALAXY PHASE - III have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: GNP GALAXY PHASE - I (P51700002007, possession 30 Dec 2022); GNP GALAXY PHASE - II (P51700002123, possession 30 Jan 2022). Check that your agreement names the registration of your own wing.
How can I get updates if GNP GALAXY PHASE - III's possession date changes?
The latest dates are on GNP GALAXY PHASE - III's MahaRERA page (P51700028923). GharKundli's Kundli Watch sends a free WhatsApp update on GNP GALAXY PHASE - III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GNP GALAXY PHASE - III have?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III has one building filed: ZONE - 3 with 4 floors and 173 units.
How much parking does GNP GALAXY PHASE - III have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 51 open car parking spaces for GNP GALAXY PHASE - III.
How big is the land of GNP GALAXY PHASE - III?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III stands on 7,731 sq m of land (about 1.9 acres), with 10,236 sq m of sanctioned built-up area.
What is the track record of GNP GALAXY PHASE - III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP Landmark (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 3 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GNP GALAXY PHASE - III?
Google Maps has reviews of GNP GALAXY PHASE - III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GNP GALAXY PHASE - III?
GNP GALAXY PHASE - III by ROSHNI ENTERPRISES is in Ambernath West, Thane (pincode 421501), near O.E.Ambernath, Maharashtra, and is registered on MahaRERA as P51700028923, per GharKundli's check of MahaRERA records. Its boundaries filed there include KALAYN BADLAPUR ROAD, MIDC ROAD.
How many homes are in GNP GALAXY PHASE - III?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III has 0 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.
When was GNP GALAXY PHASE - III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GNP GALAXY PHASE - III was registered on MahaRERA on 12 April 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on GNP GALAXY PHASE - III?
2 court cases are listed for GNP GALAXY PHASE - III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of GNP GALAXY PHASE - III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ROSHNI ENTERPRISES, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GNP GALAXY PHASE - III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 421501
- NEELKANTH ROYALE PALMS - F WING PHASE II
- CHADHA RESIDENCY
- NEW NEELGAGAN CHS
- Mahadev Heights
- PARITOSH CO OPERATIVE HOUSING SOCIETY LIMITED
- NEXT CROWN LANDMARK
- ISHWAR JAY JAY SHANKARA CO-OP. HOUSING SOCIETY LTD.
- Panvelkar Daffodils-Plot No. 11,12,13
Other projects by ROSHNI ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.