Radhe Mohan
by K T HOMES (AND) · Kopar Khairne, Thane 400709Also near Koparkhairane, Vashi
What’s in the report? →Possession date of Radhe Mohan (MahaRERA P51700029410): 31 December 2025, moved from 31 December 2024 (12 months later), and it has already passed. It has 144 homes, 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700029410. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700029410, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Radhe Mohan?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Radhe Mohan has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025091)
Reason the builder gave MahaRERA:
“1. Project Background and Compliance Obligation: As per the Commencement Certificate dated 12/02/2021, issued by the Navi Mumbai Municipal Corporation (NMMC), the Developer is obligated to transfer 12.15 SQ.Meters of the constructed area to…” Read the full reason
“1. Project Background and Compliance Obligation: As per the Commencement Certificate dated 12/02/2021, issued by the Navi Mumbai Municipal Corporation (NMMC), the Developer is obligated to transfer 12.15 SQ.Meters of the constructed area to the City and Industrial Development Corporation (CIDCO) prior to the issuance of the Occupancy Certificate. A copy of the Commencement Certificate is attached for your reference. 2. Intimation to CIDCO for Handover Process: On 12/01/2021, the NMMC issued a notification to CIDCO, advising the initiation of the handover process for the specified 12.15 Sq.…”
Source: Radhe Mohan’s extension records on MahaRERA (P51700029410), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Radhe Mohan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700029410
- Status
- Lapsed (registration period ended)
- Builder
- K T HOMES
- Location
- Kopar Khairne, Thane · 400709
- Project type
- Residential / Group Housing
- Registered on
- 29 May 2021
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 144
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Radhe Mohan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RADHE MOHAN | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RADHE MOHAN: covers 28 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Radhe Mohan every 1–2 months.
Radhe Mohan: buildings, flats and land, as filed on MahaRERA
- Buildings: RADHE MOHAN (28 floors, 144 units)
- Car parking: 2 covered
- Land: 1,880 sq m (about 0.5 acres) · sanctioned built-up 4,680 sq m · recreational space 282 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
B AND B Properties (a group of 6 linked companies) has 8 projects on MahaRERA since 2018, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Radhe Mohan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Radhe Mohan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Radhe Mohan
What is the possession date of Radhe Mohan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Radhe Mohan in Kopar Khairne, Thane is 31 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Radhe Mohan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Radhe Mohan's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Radhe Mohan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "1. Project Background and Compliance Obligation: As per the Commencement Certificate dated 12/02/2021, issued by the Navi Mumbai Municipal Corporation (NMMC), the Developer is obligated to transfer 12.15 SQ.Meters of the constructed area to the City and Industrial Development Corporation (CIDCO) prior to the issuance of the Occupancy Certificate. A copy of the Commencement Certificate is attached for your reference. 2. Intimation to CIDCO for Handover Process: On 12/01/2021, the NMMC issued a notification to CIDCO, advising the initiation of the handover process for the specified 12.15 Sq.…".
What is the RERA number of Radhe Mohan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Radhe Mohan in Kopar Khairne, Thane is P51700029410.
Is Radhe Mohan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan is registered as P51700029410 and its status is "Lapsed (registration period ended)".
What is the current construction status of Radhe Mohan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on RADHE MOHAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Radhe Mohan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Radhe Mohan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan is registered on MahaRERA as P51700029410, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Radhe Mohan?
Radhe Mohan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Radhe Mohan?
For a flat in Radhe Mohan (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Radhe Mohan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Radhe Mohan?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Radhe Mohan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Radhe Mohan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Radhe Mohan's possession date changes?
The latest dates are on Radhe Mohan's MahaRERA page (P51700029410). GharKundli's Kundli Watch sends a free WhatsApp update on Radhe Mohan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Radhe Mohan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan has one building filed: RADHE MOHAN with 28 floors and 144 units.
How much parking does Radhe Mohan have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 covered car parking spaces for Radhe Mohan.
How big is the land of Radhe Mohan?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan stands on 1,880 sq m of land (about 0.5 acres), with 4,680 sq m of sanctioned built-up area and 282 sq m of recreational open space.
What is the track record of Radhe Mohan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), B AND B Properties (a group of 6 linked companies) has 8 projects on MahaRERA since 2018, this one included. Of the 8 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Radhe Mohan?
Google Maps has reviews of Radhe Mohan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Radhe Mohan?
Radhe Mohan by K T HOMES (AND) is in Kopar Khairne, Thane, pincode 400709 (near Koparkhairane, Vashi), Maharashtra, and is registered on MahaRERA as P51700029410, per GharKundli's check of MahaRERA records. GharKundli lists all 25 MahaRERA projects in Koparkhairane (400709).
How many flats are in Radhe Mohan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan has 144 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Radhe Mohan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Radhe Mohan was registered on MahaRERA on 29 May 2021. GharKundli did not find a title report on the land on file there.
Does Radhe Mohan have any legal issues or court cases?
No court cases are listed for Radhe Mohan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Radhe Mohan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K T HOMES, the company AND files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Radhe Mohan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Koparkhairane (400709)
- Satyam Stella
- Kamdhenu 23 West Grande
- The Trellis
- Krishna Park view
- Satyam Dwarka
- Bhoomi Icon Wing A
- Bhoomi Icon Wing B
- Opal Bay
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.