Square Aditya Matruchaya
by SQUARE DEVELOPERS · Ambernath, Thane 421501Registered on MahaRERA as “ADITYA MATRUCHAYA”
What’s in the report? →Possession date of Square Aditya Matruchaya (MahaRERA P51700029295): 30 September 2026, moved from 12 September 2024 (24 months later), and it has already passed. It has 34 homes, 75% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700029295. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700029295, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about Square Aditya Matruchaya?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Square Aditya Matruchaya has moved
12 September 2024
Completion date given when the project was registered
12 September 2025
Extended at the builder's request (MahaRERA application EXT51700016660)
Reason the builder gave MahaRERA: “Due to revision of plan.”
30 September 2026
Extended at the builder's request (MahaRERA application EA22092502665)
Reason the builder gave MahaRERA: “oc applied project completed”
Source: Square Aditya Matruchaya’s extension records on MahaRERA (P51700029295), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Square Aditya Matruchaya
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700029295
- Status
- Lapsed (registration period ended)
- Builder
- SQUARE DEVELOPERS
- Location
- Ambernath, Thane · 421501
- Project type
- Others
- Registered on
- 18 May 2021
- Completion date at registration
- September 2024
- Latest completion date
- September 2026
- Delay so far
- 24 months
- Homes
- 34
- Sold or booked
- 75%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Square Aditya Matruchaya, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ADITYA MATRUCHAYA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- ADITYA MATRUCHAYA: covers 10 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Square Aditya Matruchaya every 1–2 months.
Square Aditya Matruchaya: buildings, flats and land, as filed on MahaRERA
- Buildings: ADITYA MATRUCHAYA (10 floors, 56 units)
- Land: 881 sq m (about 0.2 acres) · sanctioned built-up 1,533 sq m
- Land, as filed: SURVEY NO 43 23 CTS NO 8771 TO 8773
- Map: Get directions
The builder’s record and reviews
Heramb Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 lapsed. No complaints on MahaRERA.
Read Google reviews of Square Aditya Matruchaya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Square Aditya Matruchaya: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Square Aditya Matruchaya
What is the possession date of Square Aditya Matruchaya?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Square Aditya Matruchaya in Ambernath, Thane is 30 September 2026 — 24 months later than 12 September 2024, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Square Aditya Matruchaya?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Square Aditya Matruchaya's builder has filed on MahaRERA, the official one, is 30 September 2026, already 24 months later than the 12 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Square Aditya Matruchaya extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya's builder applied to MahaRERA to extend the completion date 2 times: to 12 September 2025, giving the reason "Due to revision of plan."; to 30 September 2026, giving the reason "oc applied project completed".
What is the RERA number of Square Aditya Matruchaya?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Square Aditya Matruchaya in Ambernath, Thane is P51700029295.
Is Square Aditya Matruchaya registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya is registered as P51700029295 and its status is "Lapsed (registration period ended)".
What is the current construction status of Square Aditya Matruchaya? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ADITYA MATRUCHAYA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Square Aditya Matruchaya have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Square Aditya Matruchaya safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya is registered on MahaRERA as P51700029295, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Square Aditya Matruchaya?
Square Aditya Matruchaya isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Square Aditya Matruchaya?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Square Aditya Matruchaya: gharkundli.com/tools/property-cost-calculator
Has Square Aditya Matruchaya received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Square Aditya Matruchaya?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Square Aditya Matruchaya uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Square Aditya Matruchaya was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Square Aditya Matruchaya's possession date changes?
The latest dates are on Square Aditya Matruchaya's MahaRERA page (P51700029295). GharKundli's Kundli Watch sends a free WhatsApp update on Square Aditya Matruchaya every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Square Aditya Matruchaya have?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya has one building filed: ADITYA MATRUCHAYA with 10 floors and 56 units.
How big is the land of Square Aditya Matruchaya?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya stands on 881 sq m of land (about 0.2 acres), with 1,533 sq m of sanctioned built-up area.
What is the track record of Square Aditya Matruchaya's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Heramb Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Square Aditya Matruchaya?
Google Maps has reviews of Square Aditya Matruchaya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Square Aditya Matruchaya?
Square Aditya Matruchaya by SQUARE DEVELOPERS is in Ambernath, Thane, pincode 421501, Maharashtra, and is registered on MahaRERA as P51700029295, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 43 23 CTS NO 8771 TO 8773. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Square Aditya Matruchaya, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya has 34 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.
When was Square Aditya Matruchaya registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Square Aditya Matruchaya was registered on MahaRERA on 18 May 2021. GharKundli did not find a title report on the land on file there.
Does Square Aditya Matruchaya have any legal issues or court cases?
No court cases are listed for Square Aditya Matruchaya on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Square Aditya Matruchaya?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SQUARE DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Square Aditya Matruchaya
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Ambernath (421501)
- Paritosh Co Operative Housing Society Limited
- New Neelgagan CHS
- Next Crown Landmark
- Mahadev Heights
- Chadha Residency
- Panvelkar Daffodils-Plot No. 11,12,13
- Neelkanth Royale Palms - F Wing Phase II
- Ishwar Jay Jay Shankara Co-op. Housing Society LTD.
Other projects by SQUARE DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.