Geetai Panvelkar Galaxy
by GEETAi INFRASTRUCTURE · Ambernath East, Thane 421501Also near Ambernath West, Vadavali, Village KansaiRegistered on MahaRERA as “PANVELKAR GALAXY”
What’s in the report? →Possession date of Geetai Panvelkar Galaxy (MahaRERA P51700031101): 31 July 2026, moved from 29 February 2024 (25 months later), and it has already passed. It has 11 homes, 73% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700031101. Status: Lapsed (registration period ended). Its completion date has moved from February 2024 to July 2026: 25 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700031101, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Geetai Panvelkar Galaxy?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Geetai Panvelkar Galaxy has moved
29 February 2024
Completion date given when the project was registered
28 February 2025
Extended at the builder's request (MahaRERA application EXT51700019258)
Reason the builder gave MahaRERA: “Insufficient funds due to covid”
31 March 2026
Extended at the builder's request (MahaRERA application EA15072502069)
Reason the builder gave MahaRERA:
“As we have Applied for OC on 3/7/2024 but there is non availability of town planner in Ambernath Municipal Corporation. Therefore, the Registrar is not registering the flat. So unfortunately we have to apply for Extension of Project. As we…” Read the full reason
“As we have Applied for OC on 3/7/2024 but there is non availability of town planner in Ambernath Municipal Corporation. Therefore, the Registrar is not registering the flat. So unfortunately we have to apply for Extension of Project. As we have to register the flat to the owner.”31 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Geetai Panvelkar Galaxy’s extension records on MahaRERA (P51700031101), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Geetai Panvelkar Galaxy
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700031101
- Status
- Lapsed (registration period ended)
- Builder
- GEETAi INFRASTRUCTURE
- Location
- Ambernath East, Thane · 421501
- Project type
- Residential / Group Housing
- Registered on
- 5 Oct 2021
- Completion date at registration
- February 2024
- Latest completion date
- July 2026
- Delay so far
- 25 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 11
- Sold or booked
- 73%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Geetai Panvelkar Galaxy, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PANVELKAR GALAXY | 100% | 100% | 95% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- PANVELKAR GALAXY: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Geetai Panvelkar Galaxy every 1–2 months.
Geetai Panvelkar Galaxy: buildings, flats and land, as filed on MahaRERA
- Buildings: PANVELKAR GALAXY (7 floors, 11 units)
- Land: 405 sq m (about 0.1 acres) · sanctioned built-up 673 sq m
- Land, as filed: PLOT NO 399, C.T.S NO 4709, SURYODAY CO-OP HOUSING SOCIETY AT VILLAGE KANSAI AMBERNATH EAST
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Om Sai Shraddha Developers (a group of 10 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 11 months); 3 still being built, 1 past the promised date (typically 21 months late); 3 lapsed. No complaints on MahaRERA.
Read Google reviews of Geetai Panvelkar Galaxy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Geetai Panvelkar Galaxy: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Geetai Panvelkar Galaxy
What is the possession date of Geetai Panvelkar Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Geetai Panvelkar Galaxy in Ambernath East, Thane is 31 July 2026 — 25 months later than 29 February 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 25 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Geetai Panvelkar Galaxy?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Geetai Panvelkar Galaxy's builder has filed on MahaRERA, the official one, is 31 July 2026, already 25 months later than the 29 February 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Geetai Panvelkar Galaxy extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy's builder applied to MahaRERA to extend the completion date 2 times: to 28 February 2025, giving the reason "Insufficient funds due to covid"; to 31 March 2026, giving the reason "As we have Applied for OC on 3/7/2024 but there is non availability of town planner in Ambernath Municipal Corporation. Therefore, the Registrar is not registering the flat. So unfortunately we have to apply for Extension of Project. As we have to register the flat to the owner.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Geetai Panvelkar Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Geetai Panvelkar Galaxy in Ambernath East, Thane is P51700031101.
Is Geetai Panvelkar Galaxy registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy is registered as P51700031101 and its status is "Lapsed (registration period ended)".
What is the current construction status of Geetai Panvelkar Galaxy? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PANVELKAR GALAXY is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Geetai Panvelkar Galaxy have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Geetai Panvelkar Galaxy safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy is registered on MahaRERA as P51700031101, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 25 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Geetai Panvelkar Galaxy?
Geetai Panvelkar Galaxy isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Geetai Panvelkar Galaxy?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Geetai Panvelkar Galaxy: gharkundli.com/tools/property-cost-calculator
Has Geetai Panvelkar Galaxy received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Geetai Panvelkar Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Geetai Panvelkar Galaxy uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Geetai Panvelkar Galaxy was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Geetai Panvelkar Galaxy's possession date changes?
The latest dates are on Geetai Panvelkar Galaxy's MahaRERA page (P51700031101). GharKundli's Kundli Watch sends a free WhatsApp update on Geetai Panvelkar Galaxy every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Geetai Panvelkar Galaxy have?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy has one building filed: PANVELKAR GALAXY with 7 floors and 11 units.
How big is the land of Geetai Panvelkar Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy stands on 405 sq m of land (about 0.1 acres), with 673 sq m of sanctioned built-up area.
What is the track record of Geetai Panvelkar Galaxy's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Om Sai Shraddha Developers (a group of 10 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 11 months); 3 still being built, 1 past the promised date (typically 21 months late); 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Geetai Panvelkar Galaxy?
Google Maps has reviews of Geetai Panvelkar Galaxy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Geetai Panvelkar Galaxy?
Geetai Panvelkar Galaxy by GEETAi INFRASTRUCTURE is in Ambernath East, Thane, pincode 421501 (near Ambernath West, Vadavali, Village Kansai), Maharashtra, and is registered on MahaRERA as P51700031101, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 399, C.T.S NO 4709, SURYODAY CO-OP HOUSING SOCIETY AT VILLAGE KANSAI AMBERNATH EAST. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).
How many flats are in Geetai Panvelkar Galaxy, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy has 11 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.
When was Geetai Panvelkar Galaxy registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Geetai Panvelkar Galaxy was registered on MahaRERA on 5 October 2021. GharKundli did not find a title report on the land on file there.
Does Geetai Panvelkar Galaxy have any legal issues or court cases?
No court cases are listed for Geetai Panvelkar Galaxy on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Geetai Panvelkar Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GEETAi INFRASTRUCTURE.
Check it yourself on MahaRERA
- How to check the possession date of Geetai Panvelkar Galaxy
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Ambernath (421501)
- Paritosh Co Operative Housing Society Limited
- New Neelgagan CHS
- Next Crown Landmark
- Mahadev Heights
- Chadha Residency
- Panvelkar Daffodils-Plot No. 11,12,13
- Neelkanth Royale Palms - F Wing Phase II
- Ishwar Jay Jay Shankara Co-op. Housing Society LTD.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.