Audumber Flower Valley
by AUDUMBER SUPERSTRUCTURES · Juveli, Thane 421503
What’s in the report? →Possession date of Audumber Flower Valley (MahaRERA P51700032044): 30 October 2026, moved from 30 June 2025 (12 months later), and it has already passed. It has 246 homes, 93% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700032044, and currently active. Its completion date has moved from June 2025 to October 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700032044, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Audumber Flower Valley?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Audumber Flower Valley has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EXT51700028016)
Reason the builder gave MahaRERA:
“Dear Sir/Madam, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700032044.The date of completion of project “Audumber Flower Valley” developed by M/s Audumber Superstructures currently is 30th June 2…” Read the full reason
“Dear Sir/Madam, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700032044.The date of completion of project “Audumber Flower Valley” developed by M/s Audumber Superstructures currently is 30th June 2025. We would like to bring to your attention that the Commencement Certificate was received on November 10, 2021, with an FSI of 7,067.04 sq. m. for Wing A and B (Stilt + 8 Floors). Subsequently, a revised Commencement Certificate was received on October 26, 2023, increasing the FSI to 11,144.16 sq. m. for Wing A (Stilt + 13 Floors) and Wing B (Stilt + 1…”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Audumber Flower Valley’s extension records on MahaRERA (P51700032044), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Audumber Flower Valley
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700032044
- Status
- Registered and active
- Builder
- AUDUMBER SUPERSTRUCTURES
- Location
- Juveli, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 3 Dec 2021
- Completion date at registration
- June 2025
- Latest completion date
- October 2026
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 246
- Sold or booked
- 93%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Audumber Flower Valley, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 98% |
| WING B | 100% | 100% | 100% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 13 floors
- WING B: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Audumber Flower Valley every 1–2 months.
Audumber Flower Valley: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (14 floors, 103 units) · WING B (13 floors, 143 units)
- Land: 3,929 sq m (about 1.0 acres) · sanctioned built-up 11,135 sq m · recreational space 490 sq m
- Land, as filed: S NO 5/4/D 5/4/B 5/23/B
- Map: Get directions
The builder’s record and reviews
Audumber Superstructures (a group of 4 linked companies) has 4 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 19 months); 2 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Audumber Flower Valley →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Audumber Flower Valley: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Audumber Flower Valley
What is the possession date of Audumber Flower Valley?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Audumber Flower Valley in Juveli, Thane is 30 October 2026 — 12 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Audumber Flower Valley?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Audumber Flower Valley's builder has filed on MahaRERA, the official one, is 30 October 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Audumber Flower Valley extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Dear Sir/Madam, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700032044.The date of completion of project “Audumber Flower Valley” developed by M/s Audumber Superstructures currently is 30th June 2025. We would like to bring to your attention that the Commencement Certificate was received on November 10, 2021, with an FSI of 7,067.04 sq. m. for Wing A and B (Stilt + 8 Floors). Subsequently, a revised Commencement Certificate was received on October 26, 2023, increasing the FSI to 11,144.16 sq. m. for Wing A (Stilt + 13 Floors) and Wing B (Stilt + 1…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Audumber Flower Valley?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Audumber Flower Valley in Juveli, Thane is P51700032044.
Is Audumber Flower Valley registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley is registered as P51700032044 and its status is "Registered and active".
What is the current construction status of Audumber Flower Valley? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Audumber Flower Valley have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Audumber Flower Valley safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley is registered on MahaRERA as P51700032044, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Audumber Flower Valley?
Audumber Flower Valley is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Audumber Flower Valley?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Audumber Flower Valley: gharkundli.com/tools/property-cost-calculator
Has Audumber Flower Valley received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Audumber Flower Valley uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Audumber Flower Valley was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Audumber Flower Valley's possession date changes?
The latest dates are on Audumber Flower Valley's MahaRERA page (P51700032044). GharKundli's Kundli Watch sends a free WhatsApp update on Audumber Flower Valley every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Audumber Flower Valley have?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley has 2 buildings filed: WING A with 14 floors and 103 units; WING B with 13 floors and 143 units.
How big is the land of Audumber Flower Valley?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley stands on 3,929 sq m of land (about 1.0 acres), with 11,135 sq m of sanctioned built-up area and 490 sq m of recreational open space.
What is the track record of Audumber Flower Valley's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Superstructures (a group of 4 linked companies) has 4 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 19 months); 2 still being built, 1 past the promised date (typically 12 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Audumber Flower Valley?
Google Maps has reviews of Audumber Flower Valley written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Audumber Flower Valley?
Audumber Flower Valley by AUDUMBER SUPERSTRUCTURES is in Juveli, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700032044, per GharKundli's check of MahaRERA records. Its land is filed as S NO 5/4/D 5/4/B 5/23/B. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Audumber Flower Valley, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley has 246 homes in 2 towers registered on MahaRERA, and 93% of them are sold or booked.
When was Audumber Flower Valley registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Audumber Flower Valley was registered on MahaRERA on 3 December 2021. GharKundli did not find a title report on the land on file there.
Does Audumber Flower Valley have any legal issues or court cases?
No court cases are listed for Audumber Flower Valley on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Audumber Flower Valley?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AUDUMBER SUPERSTRUCTURES.
Check it yourself on MahaRERA
- How to check the possession date of Audumber Flower Valley
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Ambarnath
- Daimond Lifespace
- Daimond Lifespace Wing 4
- Nature Vista Building - 1
- Midtown B and C Wing
- Sai Universe
- Mery Villa CHSL
- Dattatray Residency
- Mahadev Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.