Midtown W90
by MIDTOWN SHELTORS LLP · Opp Kailash Garden, Thane 421301
What’s in the report? →Possession date of Midtown W90 (MahaRERA P51700045256): 30 April 2027, moved from 31 December 2025 (12 months later). It has 117 homes, 67% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700045256, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700045256, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Midtown W90?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Midtown W90 has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA11042620617)
Reason the builder gave MahaRERA:
“The project has faced delays due to a sustained slowdown in sales, affecting overall execution momentum. The supply of key raw materials was irregular and impacted by market fluctuations, leading to interruptions in construction activities.…” Read the full reason
“The project has faced delays due to a sustained slowdown in sales, affecting overall execution momentum. The supply of key raw materials was irregular and impacted by market fluctuations, leading to interruptions in construction activities. Additionally, internal works such as plastering and plumbing could not be completed within the planned timelines due to coordination and resource challenges. These factors collectively slowed down the progress of the project. Further, there has been a delay in obtaining the Occupancy Certificate (OC) due to procedural requirements and pending compliances…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Midtown W90’s extension records on MahaRERA (P51700045256), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Midtown W90
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700045256
- Status
- Registered and active
- Builder
- MIDTOWN SHELTORS LLP
- Location
- Opp Kailash Garden, Thane · 421301
- Project type
- Others
- Registered on
- 10 May 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 117
- Sold or booked
- 67%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Midtown W90, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building 1 | 100% | 100% | 90% | 80% |
| Building 2 | 100% | 100% | 100% | 100% |
| Building 3 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Building 1: covers 31 floors
- Building 2: covers 2 floors
- Building 3: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Midtown W90 every 1–2 months.
Midtown W90: buildings, flats and land, as filed on MahaRERA
- Buildings: Building 1 (31 floors, 116 units) · Building 2 (2 floors, 8 units) · Building 3 (2 floors, 8 units)
- Car parking: 161 covered
- Land: 3,900 sq m (about 1.0 acres) · sanctioned built-up 14,033 sq m
- Land, as filed: SURVEY NO 27 HISSA NO 7 P
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Midtown W90 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Midtown W90: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Midtown W90
What is the possession date of Midtown W90?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Midtown W90 in Opp Kailash Garden, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Midtown W90?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Midtown W90's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Midtown W90 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project has faced delays due to a sustained slowdown in sales, affecting overall execution momentum. The supply of key raw materials was irregular and impacted by market fluctuations, leading to interruptions in construction activities. Additionally, internal works such as plastering and plumbing could not be completed within the planned timelines due to coordination and resource challenges. These factors collectively slowed down the progress of the project. Further, there has been a delay in obtaining the Occupancy Certificate (OC) due to procedural requirements and pending compliances…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Midtown W90?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Midtown W90 in Opp Kailash Garden, Thane is P51700045256.
Is Midtown W90 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 is registered as P51700045256 and its status is "Registered and active".
What is the current construction status of Midtown W90? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Midtown W90 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Midtown W90 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 is registered on MahaRERA as P51700045256, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Midtown W90?
Midtown W90 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Midtown W90?
For a flat in Midtown W90 (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Midtown W90 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Midtown W90 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Midtown W90 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Midtown W90's possession date changes?
The latest dates are on Midtown W90's MahaRERA page (P51700045256). GharKundli's Kundli Watch sends a free WhatsApp update on Midtown W90 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Midtown W90 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 has 3 buildings filed: Building 1 with 31 floors and 116 units; Building 2 with 2 floors and 8 units; Building 3 with 2 floors and 8 units.
How much parking does Midtown W90 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 161 covered car parking spaces for Midtown W90.
How big is the land of Midtown W90?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 stands on 3,900 sq m of land (about 1.0 acres), with 14,033 sq m of sanctioned built-up area.
What are the reviews of Midtown W90?
Google Maps has reviews of Midtown W90 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Midtown W90?
Midtown W90 by MIDTOWN SHELTORS LLP is in Opp Kailash Garden, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700045256, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 27 HISSA NO 7 P. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Midtown W90, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 has 117 homes in 3 towers registered on MahaRERA, and 67% of them are sold or booked.
When was Midtown W90 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Midtown W90 was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.
Does Midtown W90 have any legal issues or court cases?
No court cases are listed for Midtown W90 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Midtown W90?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MIDTOWN SHELTORS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Midtown W90
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kalyan
- Majesty Heights
- Royal Hills
- Mangeshi Dhara
- Vidhi Impression
- Balaji Govind
- Swami Elite
- Om Trimurti Darshan
- Ram Janki
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.