Panvelkar Estate - Greenford - E Wing
by Panvelkar Infrastructures Private Limited · Mankivali, Thane 421503Also near Kulgaon
What’s in the report? →Possession date of Panvelkar Estate - Greenford - E Wing (MahaRERA P51700032902): 30 June 2026, moved from 31 December 2025 (6 months later), and it has already passed. It has 95 homes, 81% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700032902. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700032902, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about Panvelkar Estate - Greenford - E Wing?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Panvelkar Estate - Greenford - E Wing has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA29122519079)
Reason the builder gave MahaRERA:
“Dear Sir, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700032902. The date of completion of project Panvelkar Estate Greenford- E Wing developed by M/s Panvelkar Infrastructures Private Limited cu…” Read the full reason
“Dear Sir, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700032902. The date of completion of project Panvelkar Estate Greenford- E Wing developed by M/s Panvelkar Infrastructures Private Limited currently is 31st December 2025. The project has been delayed due to general market slowdowns and disruptions in material availability, which have affected the pace of construction. We are in the final stages of completion and require additional time to complete the remaining work. We request the Authority to kindly grant a 6-month extension up to 30th June…”
Source: Panvelkar Estate - Greenford - E Wing’s extension records on MahaRERA (P51700032902), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Panvelkar Estate - Greenford - E Wing
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700032902
- Status
- Lapsed (registration period ended)
- Builder
- Panvelkar Infrastructures Private Limited
- Location
- Mankivali, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 2 Feb 2022
- Completion date at registration
- December 2025
- Latest completion date
- June 2026
- Delay so far
- 6 months
- Homes
- 95
- Sold or booked
- 81%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of Panvelkar Estate - Greenford - E Wing, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Greenford E Wing | 100% | 100% | 60% | 60% |
Commencement certificate (CC), as filed on MahaRERA
- Greenford E Wing: covers 13 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Panvelkar Estate - Greenford - E Wing every 1–2 months.
Panvelkar Estate - Greenford - E Wing: buildings, flats and land, as filed on MahaRERA
- Buildings: Greenford E Wing (13 floors, 95 units)
- Land: 4,775 sq m (about 1.2 acres) · sanctioned built-up 4,775 sq m
- Land, as filed: Survey No 42 Hissa No 2 and 3
- Map: Get directions
The builder’s record and reviews
Panvelkar Infrastructures (a group of 8 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 12 finished, 9 within the promised date and 3 needed more time (typically 12 months); 6 still being built, 3 past the promised date (typically 34 months late); 7 lapsed. 7 complaints on MahaRERA across 4 projects.
Read Google reviews of Panvelkar Estate - Greenford - E Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Panvelkar Estate - Greenford - E Wing: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Panvelkar Estate - Greenford - E Wing
What is the possession date of Panvelkar Estate - Greenford - E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Panvelkar Estate - Greenford - E Wing in Mankivali, Thane is 30 June 2026 — 6 months later than 31 December 2025, the date given at registration. That date has already passed.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Panvelkar Estate - Greenford - E Wing?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Panvelkar Estate - Greenford - E Wing's builder has filed on MahaRERA, the official one, is 30 June 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Panvelkar Estate - Greenford - E Wing extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Dear Sir, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700032902. The date of completion of project Panvelkar Estate Greenford- E Wing developed by M/s Panvelkar Infrastructures Private Limited currently is 31st December 2025. The project has been delayed due to general market slowdowns and disruptions in material availability, which have affected the pace of construction. We are in the final stages of completion and require additional time to complete the remaining work. We request the Authority to kindly grant a 6-month extension up to 30th June…".
What is the RERA number of Panvelkar Estate - Greenford - E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Panvelkar Estate - Greenford - E Wing in Mankivali, Thane is P51700032902.
Is Panvelkar Estate - Greenford - E Wing registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing is registered as P51700032902 and its status is "Lapsed (registration period ended)".
What is the current construction status of Panvelkar Estate - Greenford - E Wing? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Greenford E Wing is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does Panvelkar Estate - Greenford - E Wing have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Panvelkar Estate - Greenford - E Wing safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing is registered on MahaRERA as P51700032902, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Panvelkar Estate - Greenford - E Wing?
Panvelkar Estate - Greenford - E Wing isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Panvelkar Estate - Greenford - E Wing?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Panvelkar Estate - Greenford - E Wing: gharkundli.com/tools/property-cost-calculator
Has Panvelkar Estate - Greenford - E Wing received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Panvelkar Estate - Greenford - E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Panvelkar Estate - Greenford - E Wing uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Panvelkar Estate - Greenford - E Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Panvelkar Estate - Greenford - E Wing's possession date changes?
The latest dates are on Panvelkar Estate - Greenford - E Wing's MahaRERA page (P51700032902). GharKundli's Kundli Watch sends a free WhatsApp update on Panvelkar Estate - Greenford - E Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Panvelkar Estate - Greenford - E Wing have?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing has one building filed: Greenford E Wing with 13 floors and 95 units.
How big is the land of Panvelkar Estate - Greenford - E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing stands on 4,775 sq m of land (about 1.2 acres), with 4,775 sq m of sanctioned built-up area.
What is the track record of Panvelkar Estate - Greenford - E Wing's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Infrastructures (a group of 8 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 12 finished, 9 within the promised date and 3 needed more time (typically 12 months); 6 still being built, 3 past the promised date (typically 34 months late); 7 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Panvelkar Estate - Greenford - E Wing?
Google Maps has reviews of Panvelkar Estate - Greenford - E Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Panvelkar Estate - Greenford - E Wing?
Panvelkar Estate - Greenford - E Wing by Panvelkar Infrastructures Private Limited is in Mankivali, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700032902, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 42 Hissa No 2 and 3. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Panvelkar Estate - Greenford - E Wing, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing has 95 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.
When was Panvelkar Estate - Greenford - E Wing registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Panvelkar Estate - Greenford - E Wing was registered on MahaRERA on 2 February 2022. GharKundli did not find a title report on the land on file there.
Does Panvelkar Estate - Greenford - E Wing have any legal issues or court cases?
No court cases are listed for Panvelkar Estate - Greenford - E Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Panvelkar Estate - Greenford - E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Panvelkar Infrastructures Private Limited, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Panvelkar Estate - Greenford - E Wing
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kulgaon (421503)
- Sai Universe
- Mery Villa CHSL
- Mahavir Heritage
- Infinity Meadows
- Gokul Heights
- Shiv Tirth B Wing
- Hari Shrushti Wing A Phase II
- Dattatray Residency
Other projects by Panvelkar Infrastructures Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.