Manas Tulsi Galaxy

by Manas Associates · Ambernath, Thane 421501Registered on MahaRERA as “Tulsi Galaxy”

What’s in the report? →

Possession date of Manas Tulsi Galaxy (MahaRERA P51700033355): 31 March 2027, moved from 31 December 2025 (15 months later). It has 354 homes, 46% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700033355, and currently active.

Source: MahaRERA website — records for P51700033355, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Manas Tulsi Galaxy?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Manas Tulsi Galaxy has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA04022619707)

    Reason the builder gave MahaRERA:
    “We could not complete and obtain occupancy certificate of Wing A and F on or before 31/12/2025 (date of completion as reported in MahaRERA regn certificate) due to slow bookings during the course of construction of the project. We regret to…” Read the full reason“We could not complete and obtain occupancy certificate of Wing A and F on or before 31/12/2025 (date of completion as reported in MahaRERA regn certificate) due to slow bookings during the course of construction of the project. We regret to inform that no bookings have been received for Wing A till date, which has significantly impacted cash flow and consequently affected the pace of construction”

Source: Manas Tulsi Galaxy’s extension records on MahaRERA (P51700033355), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Manas Tulsi Galaxy

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700033355
Status
Registered and active
Builder
Manas Associates
Location
Ambernath, Thane · 421501
Project type
Residential / Group Housing
Registered on
16 Feb 2022
Completion date at registration
December 2025
Latest completion date
March 2027
Delay so far
15 months
Homes
354
Sold or booked
46%
Towers
6
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Manas Tulsi Galaxy, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B Wing0%0%0%0%
C Wing0%0%0%0%
D Wing0%0%0%0%
E Wing0%0%0%0%
F Wing0%0%0%0%
A Wing0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • B Wing: covers 9 floors
  • C Wing: covers 9 floors
  • D Wing: covers 9 floors
  • E Wing: covers 9 floors
  • F Wing: covers 9 floors
  • A Wing: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Manas Tulsi Galaxy every 1–2 months.

Manas Tulsi Galaxy: buildings, flats and land, as filed on MahaRERA

  • Buildings: B Wing (9 floors, 49 units) · C Wing (9 floors, 63 units) · D Wing (9 floors, 28 units) · E Wing (9 floors, 56 units) · F Wing (9 floors, 63 units) · A Wing (8 floors, 95 units)
  • Land: 6,750 sq m (about 1.7 acres) · sanctioned built-up 15,955 sq m
  • Land, as filed: S No 69 H No 16, S No 69 H No.17, S no. 69 H No. 17P B, S No. 51, H No.5
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Manas Tulsi Galaxy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Manas Tulsi Galaxy: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Manas Tulsi Galaxy

What is the possession date of Manas Tulsi Galaxy?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Manas Tulsi Galaxy in Ambernath, Thane is 31 March 2027 — 15 months later than 31 December 2025, the date given at registration.

The date has already moved 15 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Manas Tulsi Galaxy?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Manas Tulsi Galaxy's builder has filed on MahaRERA, the official one, is 31 March 2027, already 15 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Manas Tulsi Galaxy extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "We could not complete and obtain occupancy certificate of Wing A and F on or before 31/12/2025 (date of completion as reported in MahaRERA regn certificate) due to slow bookings during the course of construction of the project. We regret to inform that no bookings have been received for Wing A till date, which has significantly impacted cash flow and consequently affected the pace of construction".

What is the RERA number of Manas Tulsi Galaxy?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Manas Tulsi Galaxy in Ambernath, Thane is P51700033355.

Is Manas Tulsi Galaxy registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy is registered as P51700033355 and its status is "Registered and active".

What is the current construction status of Manas Tulsi Galaxy? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does Manas Tulsi Galaxy have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Manas Tulsi Galaxy safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy is registered on MahaRERA as P51700033355, its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Manas Tulsi Galaxy?

Manas Tulsi Galaxy is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Manas Tulsi Galaxy?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Manas Tulsi Galaxy: gharkundli.com/tools/property-cost-calculator

Has Manas Tulsi Galaxy received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy is still under construction, with 31 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Manas Tulsi Galaxy uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Manas Tulsi Galaxy was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Manas Tulsi Galaxy's possession date changes?

The latest dates are on Manas Tulsi Galaxy's MahaRERA page (P51700033355). GharKundli's Kundli Watch sends a free WhatsApp update on Manas Tulsi Galaxy every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Manas Tulsi Galaxy have?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy has 6 buildings filed: B Wing with 9 floors and 49 units; C Wing with 9 floors and 63 units; D Wing with 9 floors and 28 units; E Wing with 9 floors and 56 units; F Wing with 9 floors and 63 units; A Wing with 8 floors and 95 units.

How big is the land of Manas Tulsi Galaxy?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy stands on 6,750 sq m of land (about 1.7 acres), with 15,955 sq m of sanctioned built-up area.

What are the reviews of Manas Tulsi Galaxy?

Google Maps has reviews of Manas Tulsi Galaxy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Manas Tulsi Galaxy?

Manas Tulsi Galaxy by Manas Associates is in Ambernath, Thane, pincode 421501, Maharashtra, and is registered on MahaRERA as P51700033355, per GharKundli's check of MahaRERA records. Its land is filed as S No 69 H No 16, S No 69 H No.17, S no. 69 H No. 17P B, S No. 51, H No.5. GharKundli lists all 486 MahaRERA projects in Ambernath (421501).

How many flats are in Manas Tulsi Galaxy, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy has 354 homes in 6 towers registered on MahaRERA, and 46% of them are sold or booked.

When was Manas Tulsi Galaxy registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Manas Tulsi Galaxy was registered on MahaRERA on 16 February 2022. GharKundli did not find a title report on the land on file there.

Does Manas Tulsi Galaxy have any legal issues or court cases?

No court cases are listed for Manas Tulsi Galaxy on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Manas Tulsi Galaxy?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Manas Associates.

All projects with possession due in 2027 in Thane →

Other projects in Ambernath (421501)

All 486 projects in Ambernath (421501) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.